• Title/Summary/Keyword: Pile load test

Search Result 553, Processing Time 0.027 seconds

A Study on the Loading Capacity Standard of Bi-directional Pile Load Test (BD PLT) (양방향말뚝재하시험의 재하용량 기준에 관한 연구)

  • Choi, Yongkyu
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.28 no.6C
    • /
    • pp.379-388
    • /
    • 2008
  • In the bi-directional pile load test (BD PLT) for pile load tests of Mega pile foundations, loading capacity standard is not specified exactly. Therefore there are so many confusions in performing the BD PLT and variations up to maximum 2 times in loading capacity are come out. In this study, standards of bi-directional pile load test (BD PLT) were considered. Based on cases of the bi-directional pile load test performed in domestic areas, maximum equivalent test load, test load increasing ratio, loading capacity increasing ratio and sufficiency ratio of design load were analyzed. It could be known that the loading capacity standard of bi-directional pile load test must be defined as 1-directional loading capacity and also must be established as more than 2 times of design load.

Numerical Analyses of O-Cell Load Test on Pile (양방향말뚝재하시험의 수치해석)

  • Joo, Yong-Sun;Kim, Nak-Kyoung;Kim, Woong-Jin;Park, Jong-Sik
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2008.10a
    • /
    • pp.748-753
    • /
    • 2008
  • Bi-directional load test is one of O-cell tests. The O-cell test is a system which may be used for performing static load tests on cast in situ reinforced concrete bored piles. The technique was devised and developed by Osterberg of Northwestern University(USA) and has been in use around the world. The principle of the method is that an O-cell is installed in a cast in situ bored pile base. Once the pile concrete reaches its design strength the cell is connected to an hydraulic pump and pressured. Pressurisation causes the cell to expand, developing an upward force on the section of pile above the cell loads, pile movements and strains within the pile then enable the capacity of the pile and its load settlement curves to be ascertained. Bi-directional load tests using O-cell are now becoming common practice around the world, particularly where the loads to be applied are high or where it is not convenient to perform top-down loading tests. In the study, calculate ultimate capacity of bi-directional load test using FEM and beam on elasto-plastic foundation theory.

  • PDF

The Behavior of Axial Load Transfer for S.L. Coated Pile And Uncoated Pile (S.L. 도포 및 미도포 말뚝의 축하중전이거동)

  • 배기열;김정환;이민희;최용규
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2002.03a
    • /
    • pp.373-380
    • /
    • 2002
  • In this study, In order to compare the behavior of axail load transfer for S.L. coated piles and uncoated piles installed at a field test site. During static pile load tests, axial load transfer for S.L. coated piles and uncoated piles were measured.

  • PDF

A Case Study on Application of Bi-directional Pile Load Test for verifing the Bearing Capacity of a Large-diameter Drilled Shaft Pile (자갈층에 근입된 대구경 현장타설말뚝의 지지능력 확인을 위한 양방향 재하시험 적용사례)

  • Lee, Min-Hee;Jung, Sung-Min;Kim, Sang-Il;Choi, Yong-Kyu
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2006.03a
    • /
    • pp.506-513
    • /
    • 2006
  • In this study, multi-level hi-direction pile load tests for drilled shaft pile socketed into the gravel were performed. The lower and upper hi-direction load test assemblies were located on tip of pile and 15m above the tip of pile. Based on the results of pile load test, it was analyzed bearing capacity of gravel, skin firction of upper soils and skin friction of lower soils. It was confirmed that drilled shaft socketed into the gravel had enough bearing capacity.

  • PDF

Pile Load test on a Large Barrette Pile and a Bored Pile for the Identification of the Load Transfer Characteristics (대형 바렛말뚝과 현장타설말뚝의 하중전이특성 파악을 위한 재하시험)

  • Han Sung-Gil;Park Jong-Kwan
    • Journal of the Korean Society for Railway
    • /
    • v.9 no.4 s.35
    • /
    • pp.493-498
    • /
    • 2006
  • In this study, two large pile load tests were performed in the deep sand gravel deposit of Nakdong river basin so that the characteristics of the load transfer was identified. The fully instrumented rectangular barrette pile in the size of $1.5\times3.0m$ and the circular bored pile of the diameter 1.5 m were placed into the ground below 50 m. Under the applied loads of 2,400 tonf and 4,000 tonf, the test results of the load transfer showed the portion of 83% and 93% of the applied loads on the barrette pile and the bored pile, respectively, were supported by the skin friction along the pile shaft. It was revealed that the most of these skin friction mobilized in sand layer underlying clay layer having N-value more than 30 and that the friction per unit area of the bored pile was larger than the friction of barrette pile. However, if embedded in the stiff sand graval layer, the both piles were proven to be sufficient for using as the friction piles.

Study on Development of the Bi-directional High Pressure Pile Load Test(BDH PLT) and Its Application (양방향 고유압 말뚝재하시험(BDH PLT)의 개발 및 적용성에 관한 연구)

  • Lee, Chung-Sook;Lee, Min-Hee;Kim, Sang-Il;Choi, Yong-Kyu
    • Journal of the Korean Geotechnical Society
    • /
    • v.23 no.6
    • /
    • pp.23-36
    • /
    • 2007
  • To overcome the limits of the static pile load test for large diameter drilled shafts, bi-directional low pressure pile load test (BDL PLT) has been used but this test method containes some problems that has not been solved basically. That is, BDL PLT has some problems: difficulty in jack (or cell) arrangement for large test capacity, void remain inside jack (or cell) due to the unrecovery of piston after test etc. In this study, bi-directional double-acting high pressure pile load test (BDH PLT W/DOJ) was developed and confirmed for a in-situ large diameter drilled shaft. At present, test specification of bi-directional pile load test (BDPLT) is being made, and severed main issues (such as, test kinds, test capacity, necessity of use of double-acting and attention of application to service pile) will be contained at the specification.

Bearing Capacity and Control Method of Driven Piles (기성말뚝의 지지력 거동해석과 시공관리방안)

  • 박영호;김경석
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 1999.03a
    • /
    • pp.249-258
    • /
    • 1999
  • Dynamic load and static load tests are performed on steel pipe piles and concrete piles at five construction sites in highway to compare the difference of load bearing mechanisms. At each site, one steel pile is instrumented with electric strain gages and dynamic tests are performed on the pile during installation. Damages of strain gages due to the installation are checked and static test is performed upon the same pile after two or seven days as well. It shows that load transfer from side friction to base resistance behaves somewhat differently according to the results of load-settlement analysis obtained from PDA and static load test. Initial elastic stage of load settlement curves of two load tests is almost similar. But after the yielding point, dynamic resistance of pile behaves more stiffer than static resistance, thus, dynamic load test result might overestimate the real pile capacity compared with static result. Analysis of gage readings shows that unit skin friction increases exponentially with depth. The skin friction is mobilized at the 1∼2m above the pile tip and contributes to the considerable side resistance. Comparison of side and base resistances between the measured value and the calculated value by Meyerhof's bearing capacity equation using SPT N value shows that the calculated base resistance is higher than the measured. Therefore, contribution of side resistance to total capacity shouldn't be ignored or underestimated. Finally, based upon the overall test results, a construction control procedure is suggested.

  • PDF

Axial Load Transfer Behavior of a Large Diameter Drilled Shaft by Osterberg Type Load Test (오스트버그식 재하시험을 이용한 대구경 현장타설말뚝의 축하중전이거동)

  • 임태경;정창규;정성민;최용규
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2003.03a
    • /
    • pp.447-454
    • /
    • 2003
  • In this test, two separated oil jacks were placed at bottom of drilled shaft(D = 1,500mm, L = 33m), and maximum upward and downward load of 1,250 tonf was applied. Also, the deformable rod sensors were placed on each level, and axial strains at each level were measured. Because the side skin friction and the end bearing could be measured separately in the Osterberg type pile load test, this test might be more economical and more applicable than a conventional static pile load test. Thus, if this Osterberg type pile load test could be established during design stage, construction cost might be reduced and its application for large diameter pile could be enhance greatly.

  • PDF

Reliability Updates of Driven Piles Using Proof Pile Load Test Results (검증용 정재하시험 자료를 이용한 항타강관말뚝의 신뢰성 평가)

  • Park, Jae-Hyun;Kim, Dong-Wook;Kwak, Ki-Seok;Chung, Moon-Kyung;Kim, Jun-Young;Chung, Choong-Ki
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2010.03a
    • /
    • pp.324-337
    • /
    • 2010
  • For the development of load and resistance factor design, reliability analysis is required to calibrate resistance factors in the framework of reliability theory. The distribution of measured-to-predicted pile resistance ratio was constructed based on only the results of load tests conducted to failure for the assessment of uncertainty regarding pile resistance and used in the conventional reliability analysis. In other words, successful pile load test (piles resisted twice their design loads without failure) results were discarded, and therefore, were not reflected in the reliability analysis. In this paper, a new systematic method based on Bayesian theory is used to update reliability index of driven steel pile piles by adding more pile load test results, even not conducted to failure, into the prior distribution of pile resistance ratio. Fifty seven static pile load tests performed to failure in Korea were compiled for the construction of prior distribution of pile resistance ratio. Reliability analyses were performed using the updated distribution of pile resistance ratio and the total load distribution using First-order Reliability Method (FORM). The challenge of this study is that the distribution updates of pile resistance ratio are possible using the load test results even not conducted to failure, and that Bayesian update are most effective when limited data are available for reliability analysis or resistance factors calibration.

  • PDF