• Title/Summary/Keyword: Large Diameter Battered Pile

Search Result 2, Processing Time 0.015 seconds

Case Studies of Several Load Tests for Large Diameter Battered Steel Pipe Piles Constructed on the Offshore Area. (대구경 해상 강관말뚝의 설계지지력 확인을 위한 여러 가지 재하시험의 적용)

  • 이정학;서덕동;정헌주
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2001.03a
    • /
    • pp.291-298
    • /
    • 2001
  • It is very difficult to accomplish load tests of piles with large diameter constructed on the offshore area, because of requirement for large scaled loading equipment and bad testing conditions. Therefore, so far in many cases pile driving dynamic formulas have applied to quality control, and recently dynamic load test method is widely used for confirming bearing capacities of such piles. However, in cases of piles with very large diameter about 2,500mm, it is nearly impossible for regular type load test methods of piles such as static and dynamic to apply owing to very large design load. This is case studies of load tests such as modified static and dynamic load tests of piles and point load tests of rock samples for estimating rational allowable bearing capacity of very large diameter piles constructed on the marine area.

  • PDF

Case Study on the Vertical Capacity of the Repaired Large Diameter Rock-Socketed Stool Pipe Pile (보수된 대구경 암반 소켈강관말뚝의 연직지지력에 관한 사례연구)

  • 최용규;김승종;김병희;이광욱;김상일
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 1999.03a
    • /
    • pp.185-192
    • /
    • 1999
  • It had found that, as a result of cross-hole tonic logging test, concrete was not filled partially within the bottom 2.0 m of the large diameter (Ø= 2,500mm) rock socketed pile, MP20-P11(socket diameter (Ø= 2,200mm), which was a pile among piles group supporting a pier of Kwangan Grand Bridge. The pile was repaired by the combined cement grout injected through the pipes for the cross-hole sonic logging test and the bore holes for core samples. A month after the cement grouting, repairing was checked by coring and cross-hole sonic logging then 3 times of grouting and 2 times of coring were, in turns, peformed, then repairing was completed successfully. The vertical compressive capacity of the repaired large diameter socketed pile was evaluated by several formulas and software ROCKET, and was more conservative than design load (1,882 ton) of MP20-P11. It is expected that, in the case of the battered socketed piles, it could be more reasonable to analyze the behaviors of a battered pile using 3-D model. A 3-D analysis will be peformed in the future study.

  • PDF