• Title/Summary/Keyword: Enlarged tunnel

Search Result 29, Processing Time 0.019 seconds

A numerical study on the behavior of existing and enlarged tunnels when widened by applying the pre-cutting method (Pre-cutting 공법을 적용한 터널 확폭 시 기존 및 확폭터널의 거동에 관한 수치해석적 연구)

  • Kim, Han-Eol;Nam, Kyoung-Min;Ha, Sang-Gui;Yoo, Han-Kyu
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.22 no.4
    • /
    • pp.451-468
    • /
    • 2020
  • Aging tunnels with small cross-sections can cause chronic traffic jams. This problem can be solved by widening the tunnel. In general, when the tunnel is expanded, the outer portion of the existing tunnel is excavated through a mechanical or blasting method. Such excavation affects not only the surrounding ground but also the existing tunnel. The application of the pre-cutting method can be a solution to these problems effectively. Therefore, if the widening of tunnel is performed by applying pre-cutting method, analysis of the impact of this method must be performed. In this study, in order to analyze the effect of applying pre-cutting in tunnel widening, numerical analysis is performed at six ground grades, from grade I to weathered rock. The analysis is performed with the expanding lane and the excavation length of pre-cutting as variables. In addition, the analysis is focused on the displacement of crown of the existing tunnel and the enlarged tunnel. As a result, the crown displacement of the enlarged tunnel is confirmed to converge at the same value regardless of the excavation length of the pre-cutting when the tunnel widening is completed. In the case of existing tunnels, uplift of crown occurs within 5 m of the front of the tunnel surface, and the shorter the excavation length of pre-cutting is found to be effective in preventing the occurrence of uplift.

Behavior and pillar stability of enlarged existing parallel tunnels (기존 병설터널의 확폭에 따른 터널 거동 및 필라 안정성 분석)

  • Lee, Myeong-Han;Kim, Bumjoo;Jang, Yeon-Soo;Yun, Ji-Nam;Park, Hyun-Gon
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.15 no.5
    • /
    • pp.537-546
    • /
    • 2013
  • Traffic congestion in existing tunnels has increased due to increased traffic volume and enlarged vehicles. Enlarging existing tunnels has advantages over constructing new tunnels by reducing land purchasing costs as well as minimizing natural environment destruction. In fact, many overseas projects for enlarging existing tunnels have been reported. Thus, it appears that the demand on enlarging existing tunnels continues to rise in Korea in near future. Nonetheless, the studies related to the enlarged tunnels have been relatively rare since there have been few tunnel enlargement projects in Korea. In the present study, the tunnel behavior and the stability of rock pillar when enlarging existing parallel tunnels were investigated by performing FE analysis and using existing theory and empirical relationships. Four different enlarging cases, depending on the enlargement types and directions, were examined in the study. According to the results, for the tunnels with the same pillar width after enlarged, the uni-laterally enlarged tunnel indicated 5 to 20% higher crown settlement compared to the bi-laterally enlarged tunnel, and for the tunnel with the narrowest pillar, the highest shotcrete stress was observed. Also, the strength/stress ratio for rock pillar was more than 1.0 for all four enlargement cases, and the Matsuda's method was found to give higher strength/stress ratio by about 50% compared to the Peck's method.

Analysis on the behavior of a old tunnel supporting system by enlargement (노후터널 확대시 기존터널 지보재 응력 변화에 대한 분석)

  • Baek, Ki-Hyun;Kim, Woong-Ku;Seo, Kyoung-Won
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2010.03a
    • /
    • pp.1382-1387
    • /
    • 2010
  • A 3D FEM numerical analysis was performed to observe the changes of supporting system of a old 1-lane tunnel when it is enlarged to 2-lane, 3-lane and 4-lane. The standard Type-III supporting pattern was applied to the new tunnel because the ground was assumed as Type-III. The observation was carried out at the middle supporting system of the old 1-lane tunnel alignment. The results shows that the changes of old tunnel supporting system began when the new tunnel was excavated at 2D(D is the equivalent diameter of 1-lane tunnel) behind of the observation place and became very rapid from 1D.

  • PDF

Reinforcement of Shotcrete Lining on the Side Wall of Tunnel in Enlargement of Existing ASSM Road Tunnel (측벽부 숏크리트 보강에 의한 재래식 도로터널 단면확대)

  • Kim, Donggyou;Shin, Youngwan
    • Journal of the Korean GEO-environmental Society
    • /
    • v.13 no.12
    • /
    • pp.81-89
    • /
    • 2012
  • The existing tunnel in urban area can be enlarged because of requirement of road-widening by traffic growth. The protector with rectangular cross section can be set up in the tunnel, which will be constructed for enlargement of width, to solve traffic jam around the tunnel. It is impossible to install the rockbolt in the lower area of tunnel due to a limited space between the protector and cutting surface. The objective of this study is to suggest the method of shotcrete thickness increase instead of rockbolt installation in the side wall of tunnel for the stability of tunnel. Numerical analysis was performed to evaluate displacement at the crown of tunnel, convergence of tunnel, and stress in shotcrete lining in 3-lane and 4-lane NATM tunnels enlarged from 2-lane conventional tunnel. There were three types of analysis condition, rockbolt installation, no rockbolt installation, and increase of shotcrete thickness without rockbolt in the side wall of tunnel. There was no difference on the displacement at the crown and the convergence of upper tunnel. In the lower tunnel, the convergence in case of no rockbolt installation was larger as maximum 1.3mm than that in case of rockbolt installation. The stress in shotcrete lining in case of no rockbolt installation was larger as maximum 1.3MPa than that in case of rockbolt installation. Numerical analysis was performed to compare the behavior of shotcrete with rockbolt with that of shotcrete, which its thickness was increased, without rockbolt. The shotcrete has an increase of 20%(250mm ${\rightarrow}$ 300mm, 4-lane tunnel)~25%(200mm ${\rightarrow}$ 250mm, 3-lane tunnel) in its thickness to reduce the stress in shotcrete lining. The behavior of shotcrete lining increased the shotcrete thickness by 20%~25% was similar to that of existing shotcrete lining with rockbolt.

Section enlargement by reinforcement of shotcrete lining on the side wall of operating road tunnel (운영중인 도로터널의 측벽하부 숏크리트 보강에 의한 단면확대)

  • Kim, Dong-Gyou;Shin, Young-Wan;Shin, Young-Suk
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.14 no.6
    • /
    • pp.637-652
    • /
    • 2012
  • The protector with the shape of '${\sqcap}$' in cross section can be set up in the tunnel, which can be constructed for enlargement of cross section, to keep traffic flow in the tunnel. It is impossible to install the rockbolt in the side wall of tunnel due to a limited space between the protector and cutting surface of side wall. The objective of this study is to suggest the optimum thickness of shotcrete lining without rockbolt on the side wall and to evaluate the stability of tunnel enlarged. Numerical analysis was performed to evaluate the displacement at the center of tunnel, the convergence of tunnel, and the stress in shotcrete lining in 4-lane NATM road tunnel enlarged from 3-lane NATM road tunnel. The vertical displacement at the center of tunnel and the convergence of crown in the tunnel with rockbolt in the side wall were almost similar to those in the tunnel without rockbolt in the side wall. The convergence of bench/invert and the stress in shotcrete lining without rockbolt on the side wall were greater maximum 0.57 mm and 1,300 kN/$m^2$ than those with rockbolt in the side wall. The increased convergence and the stress in shotcrete lining can be reduced in incerasing of thickness of shotcrete lining about 20% (5 cm) of standard thickness, 25 cm, of shotcrete lining.

A stability study of deep and double-deck tunnels considering shape and reinforcing method of an enlarged section by using numerical analyses (수치해석을 이용한 대심도 복층터널의 확폭단면 형상 및 보강방법에 대한 안정성 연구)

  • You, Kwang-Ho;Jin, Su-Hyun;Kim, Young-Jin
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.19 no.1
    • /
    • pp.41-56
    • /
    • 2017
  • Recently, the necessity of deep and double-deck tunnels has been grown day by day due to the increase of traffic volume at metropolitans and thus the study on the divergence of those tunnels becomes required. Therefore sensitivity analyses were conducted with FLAC 2D program by selecting ground condition, coefficient of lateral pressure, support pattern, and depth of rock cover as parameters. Ultimately, this study is to find the optimal shape and support method of a diverged section. As the results of this study, it turned out that the box type gave higher stability of the section than arch type unlike the general thought. It can be explained that the arch type has about 30% bigger excavation area than the box type. When the ground conditions are poor, steel pipe grouting reinforcement gives higher stability than rockbolt reinforcement, but its thickness and range do not give a great influence on the stability of the enlarged section.

A Case Study on the Construction of Large Cross Section Tunnel for Underground Ventilation System (지하환기소 대단면 터널 시공 사례 연구)

  • Noh, Seung Hwan;Choi, Sung Wook;Noh, Sang Lim
    • Tunnel and Underground Space
    • /
    • v.27 no.4
    • /
    • pp.195-204
    • /
    • 2017
  • This case study introduces the construction of large cross section tunnel for underground ventilation system in Sillim-Bongcheon Tunnel Project. In order to grant the safety and efficiency in connecting the ventilation shaft (7.8 m of width, and 6.6 m of height) to a tunnel for axial fan facility (20.8 m of width, and 12.3 m of height), gradual enlargement of tunnel cross section was employed between those and temporary support method was determined based on Q system. In addition, some original designs were revised during construction stage to improve the efficiency of excavation in large cross section tunnel. The advance length was optimized and top heading of the tunnel was excavated without partition in accordance with ground condition and numerical stability analysis results. It is believed that some experiences and considerations in this case study will be useful for the future design and construction in similar large cross section tunnel such as large underground ventilation system or road tunnel with four lanes.

Dynamic Behaviors of a Corrugated Steel Tunnel Lining System due to Wind Loads by Passing Vehicles according to the Boundary Conditions (구조물 경계조건에 따른 파형강판 터널라이닝의 풍하중에 대한 동적 거동분석)

  • Mha, Ho-Seong;Cho, Kwang-Il;Yoo, Sung-Heum
    • Journal of Korean Society of Steel Construction
    • /
    • v.24 no.1
    • /
    • pp.47-58
    • /
    • 2012
  • Dynamic behaviors of a corrugated steel plate tunnel lining system are examined under wind loads due to passing vehicles. Applied wind loads are simulated by applying the time functions as a vehicle moves through the tunnel. Wind loads are described by the pressure and suction as a vehicle arrives and leaves target positions in the tunnel. The tunnel lining is modeled using the simplified shell elements that retain the characteristics of the corrugated shapes. The displacements of the tunnel lining are evaluated under various conditions regarding wind velocity and the passing vehicles. The responses are found to increase as the vehicle velocity and wind velocity increase. A maximum displacement of 25mm occurs when two vehicles are crossing at the speed of 120km/h. A row of vehicles running consecutively minimally affects the dynamic responses with less than 2.5% of the dynamic responses enlarged and attributed to one running vehicle. It should be noted that the dynamic responses of the tunnel lining should be considered when there is no shotcrete applied.

Analyses of Existing Tunnel Liner Behaviors Caused by Excavation of Upper Layer with Using Laser Scanning Technology (레이저 스캐닝 기술을 이용한 기존 터널 상부굴착에 따른 라이닝 거동 분석)

  • Park, Tae-Soo;Lee, Seung-Ho
    • Journal of the Korean Geotechnical Society
    • /
    • v.31 no.10
    • /
    • pp.29-36
    • /
    • 2015
  • This paper deals with inspecting and monitoring cracks developed on a subway tunnel liner during the construction of temporary supports and excavation. The cracks have developed near a enlarged part of the tunnel. Several measurements, crack gauge, internal displacement measurement, 3-D laser scanner have been conducted to monitor the progress of cracks and effects of them on the tunnel. Local measurement, additional propagation of cracks and deformation of liner, have been conducted by crack gauge and internal displacement measurement. Global inspection has been conducted by 3-D laser scanner. From the scanned data, occurrence of global deformation of tunnel and rail has been evaluated. Because of limited sequence of construction at the ground, no apparent deformation of crack propagation has been measured. As presented in this paper, deformation of tunnel liner and effects of rail need to be investigated in view of local and global aspects.

An Assessment of the Excavation Damaged Zone in the KAERI Underground Research Tunnel (원자력연구원 내 지하처분연구시설의 암반 손상대 발생영향 분석)

  • Kim, Jin-Seop;Kwon, Sang-Ki;Cho, Won-Jin
    • Explosives and Blasting
    • /
    • v.27 no.1
    • /
    • pp.21-31
    • /
    • 2009
  • An excavation damaged zone (EDZ) is created by fracturing, excavation or stress redistribution of tunnels. In this zone the mechanical and hydraulic properties of rock are changed, which makes additional cracks and serves as a dominant pathway of groundwater flow. In this study, an assessment on an EDZ size was practiced by the measurement of the deformation modulus at the KAERI underground research tunnel (KURT), and the information was applied to the modelling analysis using FLAC2D software. The EDZ at KURT fell into the range of 0.6~1.8m and the deformation moduli of the EDZ generally correspond to about 40% of intact rock mass. With a consideration of the EDZ in numerical analysis, tunnel displacements increased by about 65% and the maximum principal stress decreased to 58% from the case without EDZ. The plastic zone of the tunnel was enlarged to the crown and invert zones of the tunnel within the range of the length of rock bolts. About 2% of the total tunnel displacement with EDZ was suppressed by the KURT support system. It is anticipated that the investigation of an EDZ can be used as an important and fundamental research for validating the overall performance of a high level waste disposal system.