• Title/Summary/Keyword: Block paint-shop

Search Result 6, Processing Time 0.023 seconds

A Case Study on the Measurement Volatile Organic Compounds and Total Hydrocarbon Concentrations in Block Paint-Shops at a Shipyard (조선소 블록 도장시설에서의 휘발성 유기화합물과 총 탄화수소 농도측정 사례)

  • Yang, Sung-Bong;Yu, Mee Seon;Woo, Kyung-Bin
    • Journal of Environmental Science International
    • /
    • v.25 no.8
    • /
    • pp.1177-1189
    • /
    • 2016
  • In order to prepare the information needed to construct a reduction system for volatile organic compounds (VOCs) exhausted from ship-block paint-booths in a giant shipyard, VOCs in paint-shop airs were analyzed and compared to the components in paint thinners. Aromatic hydrocarbons containing eight and nine carbon atoms are known to be major VOC compounds found in shipyard paint-shops. The total hydrocarbon (THC(C7)) concentrations calibrated using toluene gas, were measured in block paint-shops with two photo-ionization detector (PID) meters, and the resulting THC(C7) data were converted to THC(C1) concentrations according to the Standard Methods for the Measurements of Air Pollution in South Korea. THC(C1) concentrations near the spray site ranged from 10 to 2,000 ppm, but they were less than 400 ppm near the walls of the paint-booth. The measurements of THC concentrations, based on the height of the monitoring sites, were related to the height of the target to which the spray paints were applied. The maximum concentrations occurred at almost the same height as the spray targets. When painted blocks had been dried-by warming with no spraying, the THC concentrations were 80~100 ppm.

Rough-cut simulation algorithm for the decision of operations policy at the block paint shop in shipbuilding (조선 도장공정 운영전략 수립을 위한 사전모의실험기법)

  • Chung, Kuy-Hoon;Park, Chang-Kyu;Min, Sang-Gyu;Park, Ju-Chull;Cho, Kyu-Kab
    • IE interfaces
    • /
    • v.14 no.1
    • /
    • pp.59-66
    • /
    • 2001
  • This paper introduces the case study that has been performed at the block paint shop, Hyundai Heavy Industries. First of all, the overall production processes of shipbuilding and research activities conducted by Korean are reviewed with a view-point of production planning. Then HYPOS(Hyundai heavy industries Painting shop Operation System) project is briefly described, which has several modules such as planning module, scheduling module, work order module, and DB(database) management module. Although the HYPOS system has several modules, this paper mainly focuses on the planning module that utilizes the rough-cut simulation algorithm to make a decision about the policy for production schedule. The HYPOS has been operated since June, 2000 and the operation data has been collected for the purpose of future evaluation about the performance of HYPOS system. The evaluation of HYPOS will be shown in a public domain as soon as the enough operation data is available.

  • PDF

A Study on Correlation of Dry Film Thickness with Multi-Nozzle Spray Pattern of Shop Primer (Shop Primer의 다중 노즐 분사 스프레이 패턴 인자와 도막두께의 상관관계에 관한 연구)

  • Yun, Won-Jun;Choi, Min-Kyu;Ro, Young-Shic
    • Journal of the Society of Naval Architects of Korea
    • /
    • v.47 no.5
    • /
    • pp.743-749
    • /
    • 2010
  • Multi-nozzle spray painting procedure of the inorganic zinc shop primer was established in order to obtain uniform film thickness. The shop primer paint prevents the corrosion of steel block during shipbuilding. When the dry film thickness of shop primer is insufficient, rust will be generated on the steel block. Otherwise, thick coating of shop primer may be a problem of weld defect. So, it is important to obtain the uniform film thickness of shop primer. The uniformity of dry film thickness is affected by spray speed, distance from spray gun to target surface and overlapping span of spray path. In order to uniformly maintain coating thickness of shop primer, the coating procedure was established based on the correlation of shop primer spray variables.

Development of the Spatial Scheduling System and Its Applications in Shipbuilding Industry (조선공업에서의 공간일정계획 시스템 개발 및 응용)

  • Chung, Kuy-Hoon;Baek, Tae-Hyun;Min, Sang-Gyu;Kim, Hyung-Shik;Park, Ju-Chull;Cho, Kyu-Kab;Park, Chang-Kyu
    • IE interfaces
    • /
    • v.14 no.4
    • /
    • pp.394-402
    • /
    • 2001
  • In this study, we deal a spatial scheduling system for the block painting process in the shipbuilding industry. In general, the spatial scheduling for the block painting process is a very complicated task. Because spatial allocation of each block in blasting and painting cells is considered simultaneously. Thus the spatial scheduling for the block painting process is the problem of planning and control of operation, which arises in shipyard. This system is developed for blocks to meet the delivery date given by the shipyard production planning system, to maximize space utilization of blasting and painting cells and to balance workload among working teams. And it has been tested using actual scheduling data from a shipyard and successfully applied in a paint shop in a shipbuilding company.

  • PDF

조선 도장 공장 운영 방안 수립에 관한 연구

  • 최동희;박주철
    • Proceedings of the Korean Operations and Management Science Society Conference
    • /
    • 2001.10a
    • /
    • pp.286-289
    • /
    • 2001
  • This paper deals with the procedures of effective mid-term Operation Planning establishment for painting shop in shipbuilding. and develop prototype system. In general, the block painting process consists of two stages such as blasting operation for surface preparation and painting operation for paint application for blocks. Weather condition is a potent Influence on those operations. The procedures consists of four steps, Load analysis, Generate alternative simulation plan. Implementation of Allocation automation module and Compare result of each simulation plan. Explain of each step. as follows, 1.step, Load analysis measure amount of assigned workload and manhour. 2.step, simulation scheme include alterable control variable such as overtime, weather. Auto allocating module carry out feasibility of simulation plan. 3.step, Allocation automation module are composed of three algorithms, as followings: - the block allocation algorithm that determines the number of blocks to be processed each day, - the team allocation algorithm that allocates blocks to worker groups. - the block arrangement algorithm that arrange blocks in blasting and painting cells. Since the block arrangement algorithm is conducted simultaneously with the team allocation algorithm, the total structure of the operating algorithms is considered to have two phases: first, daily load balancing with capacity limit and second, team allocation considering arrangement each day 4 step, Comparing result of each simulation plan. and select best simulation plan.

  • PDF

Effect of Retained Pre-construction Primer on the Corrosion Protection Properties of Epoxy Coatings

  • Lee, Chul-Hwan;Shin, Chil-Seok;Lee, Ho-Il;Chung, Mong-Kyu;Baek, Kwang-Ki
    • Corrosion Science and Technology
    • /
    • v.6 no.5
    • /
    • pp.219-226
    • /
    • 2007
  • Pre-construction primer (PCP), or shopprimer, have been applied to steel plates to control temporary corrosion during ship fabrication. For surface preparation at ship block stage, in common shipyard practices, welding beads, burnt and rusted areas shall be blasted or power tool cleaned and the contamination such as zinc salt shall be removed with blasting or power tool. Whereas, the sound film of PCP needs not to be removed or roughened as the paint having good compatibility with PCP is used for the first coat. In many cases, however, full blasting or sweep blasting on the sound PCP treated block assemblies was requested. There still has been argument about the legitimacy of this practice, thus, it is critical to evaluate the quality of the coating system applied on the sound PCP retained condition, comparing with the one applied on the full blasted or sweep blasted condition. In this study, two different epoxy systems for water ballast tank were applied on the surfaces with sound PCP condition, full blasted condition, and sweep blasted condition. Coating performances such as durability, anti-corrosion, cathodic disbondment resistance were evaluated. The test results clearly indicated that the sound film of PCP needed not to be removed or roughened as the paint having good compatibility with PCP based on inorganic zinc silicate.