• Title/Summary/Keyword: 월굴진율

Search Result 4, Processing Time 0.017 seconds

A Study on Efficiency Improvement through Productivity Analysis Based on TBM Operation Data (TBM공법 적용 현장별 생산성 분석을 통한 효율성 개선 방안)

  • Park, Hong Tae;Song, Young Sun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.30 no.1D
    • /
    • pp.71-77
    • /
    • 2010
  • This study presented the operation method through of productivity on eight analysis work items (TBM boring, cutter check and exchange, TBM maintenance, succeeding facilities, reinforcement in tunnel, operation alternation, a tram car) which have developed equipment at WRITH with TBM a waterway tunnel works. It was inquired lose time with analyzed result by work items and removed lose time. It was analyzed TBM boring length, TBM boring length percentage and TBM boring length time. This study analyzed TBM operation utility factor of a foreign work with TBM operation boring length percentage, a monthly average boring length, pure boring length percentage etc. and assumed a monthly average boring length and a monthly average boring length of rise forecast. Based on analyzed Data, TBM boring has been forecasted propriety pure boring length at compressive strength $675{\sim}1662kgf/cm^2$.

Analysis on Downtime element of Gripper TBM based on field data (현장 데이터 분석을 통한 Gripper TBM의 Downtime 요소 분석)

  • Park, Jinsoo;Song, Ki-Il
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.23 no.6
    • /
    • pp.393-402
    • /
    • 2021
  • The first TBM introduced in Korea was the gripper TBM, which was applied to the Gudeok Waterway Tunnel in 1985. In the initial stage of the introduction of the gripper TBM, many applications were mainly focused on waterway tunnels (Tunnel Mechanized Construction Design, 2008). Currently, the construction range of gripper TBM in Korea is widely applied to not only waterway tunnels, but also subways, railway tunnels, and TBM+NATM expansion. Overseas, gripper TBM is generally applied, and even when NATM tunnel is applied, it is applied as an exploration tunnel because of the excellent advance rate of gripper TBM and used as an evacuation tunnel after completion. Due to the fast excavation speed, the application of the gripper TBM in the rock section of weathered rock or higher can minimize the environmental and civil complaints caused by creating a large number of work areas when planning long tunnels or mountain tunnels. In this study, the work process of the general gripper TBM was analyzed by analyzing the construction cycle and the gripper TBM with a diameter of 2.6~5.0 m, which was applied the most in Korea. Downtime was investigated and analyzed.

Case Study of Shield Tunnel Construction : Incheon Metro Line 1 Geomdan Extension Phase 1 Project (쉴드TBM 터널 시공 사례 : 인천도시철도1호선 검단연장선 1공구)

  • Byungkwan Park;Chaeman Joo;Dohak Huh;Hyunsup Song;Gwangsu Joo;Dohoon Kim;Minsang Lee
    • Tunnel and Underground Space
    • /
    • v.34 no.3
    • /
    • pp.185-195
    • /
    • 2024
  • The Incheon Metro Line 1 Geomdan Extension Phase 1 is the first project in South Korea where both a roadheader and TBM (Tunnel Boring Machine) are being used together. The shield TBM tunnel section is 1,057 m long, and is mostly composed of rock, including the section beneath the Airport Railroad and the Gyeongin Ara Waterway. A 7.8 m earth pressure balance shield TBM was used for tunnel excavation. The average monthly advance rate for both the North and South tracks is 239.1 m, with a maximum monthly advance rate of 334.5 m. This technical article comprehensively evaluates the productivity of the shield TBM, focusing on the TBM excavation performance. Above all, it aims to provide useful reference material for the successful execution of shield TBM tunnel construction.

A Case Study on the Application of the Electronic Detonator System in Tunnel Blasting (전자기폭시스템을 활용한 터널 시공사례)

  • 이상헌;윤지선;조영곤;안봉도
    • Explosives and Blasting
    • /
    • v.22 no.1
    • /
    • pp.23-32
    • /
    • 2004
  • 터널 발파를 원활히 수행하기 위해서는 암반조건에 적합한 합리적인 설계와 정밀한 천공, 정확한 기폭초시가 기본요소로서 이는 현재 국내 터널 설계.시공 기술 및 기자재의 발달로 만족할 만한 성과를 얻을 수 있다. 특히. 터널발파에서 정확한 기폭초시 부여는 굴진율 및 버럭 파쇄율, 굴착예정선 미려도, 잔여 암반 손상도 등의 시공성에서 뿐만 아니라 소음 및 진동 발생율을 좌우하는 환경적인 측면에서 매우 중요한 요소이다. 기폭요소는 최초 도화선을 활용한 공업뇌관에서 전기뇌관, 비전기식뇌관의 순으로 기폭안전성과 정밀성 면에서 눈부신 성장을 이룩하여 왔으며 특히, 90년대 초에 개발되어 전 세계적으로 최근까지 지속적으로 사용량이 급증하고 있는 전자뇌관은 기폭방식에 일대혁신을 이루었다. 전자기폭 시스템은 기존뇌관의 초시를 결정하는 화약성분의 지연요소 대신에 IC board(전자회로)에 의한 Digital timer로 신호를 발생하여 초시를 결정하는 방식이다. 본 논문에서는 국내 최초로 전자기폭시스템을 활용하여 2003년 9원 23일에서 동년 11월 2일까지 강원도 양구 지역의 $\bigcirc\bigcirc$터널에 전자뇌관을 이용한 시험발파를 실시하였고, 발파에 의한 진동 등을 조사하여 그 효율성을 검토하였다. 이를 위해 전자뇌관의 특성과 장점을 최대한 샅리기 위하여 각공을 발파하는 방식, 즉 1지발에 1공을 발파하는 방식을 채택하고 일반 뇌관과 전자뇌관으로 설계를 하여 각각의 발파효율을 비교하여 보았다. 그 결과 발파진동의 경우 기존뇌관을 이용하여 1공씩을 1지발로 발파를 한 경우에는 18~56%의 진동저감 효과가 있었고. 본선 설계에 의해 진행된 발파에 비하여는 최대 70% 이상의 진동저감 효과가 있는 것으로 나타났다.