Analysis on Downtime element of Gripper TBM based on field data  

Park, Jinsoo (Dept. of Civil Engineering, Inha University, TBM-Part, Civil Construction Team, HoBan Group)
Song, Ki-Il (Dept. of Civil Engineering, Inha University)
Publication Information
Journal of Korean Tunnelling and Underground Space Association / v.23, no.6, 2021 , pp. 393-402 More about this Journal
Abstract
The first TBM introduced in Korea was the gripper TBM, which was applied to the Gudeok Waterway Tunnel in 1985. In the initial stage of the introduction of the gripper TBM, many applications were mainly focused on waterway tunnels (Tunnel Mechanized Construction Design, 2008). Currently, the construction range of gripper TBM in Korea is widely applied to not only waterway tunnels, but also subways, railway tunnels, and TBM+NATM expansion. Overseas, gripper TBM is generally applied, and even when NATM tunnel is applied, it is applied as an exploration tunnel because of the excellent advance rate of gripper TBM and used as an evacuation tunnel after completion. Due to the fast excavation speed, the application of the gripper TBM in the rock section of weathered rock or higher can minimize the environmental and civil complaints caused by creating a large number of work areas when planning long tunnels or mountain tunnels. In this study, the work process of the general gripper TBM was analyzed by analyzing the construction cycle and the gripper TBM with a diameter of 2.6~5.0 m, which was applied the most in Korea. Downtime was investigated and analyzed.
Keywords
Gripper TBM; Advance rate; Downtime;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Farrokh, E. (2018), "Introducing hard rock TBMs' downtime analysis model with reference to past case histories' data", Journal of Mining and Environment, Vol. 9, No. 2, pp. 457-472.
2 Lee, H.L. (2020), Real-time prediction of penetration rate of shield TBM based on machine learning, Doctor of Philosophy, Inha University, pp. 6-23.
3 Jing, L.J., Li, J.B., Zhang, N., Chen, S., Yang, C., Cao, H.B. (2021), "A TBM advance rate prediction method considering the effects of operating factors", Tunnelling and Underground Space Technology, Vol. 107, 103620.   DOI
4 Ko, T.Y., Kim, T.K., Lee, D.H. (2019), "Statistical characteristics and rational estimation of rock TBM utilization", Tunnel and Underground Space, Vol. 29, No. 5, pp. 356-366.
5 Tunnel Mechanized Construction Design (2008), Korean Tunnelling and Underground Space Association, CIR, Seoul, pp. 7.