Relationship Between Net Penetration Rate and Thrust of Shielded TBM in Hard Rock (암반층에서 Shield TBM의 굴착속도와 추력과의 관계)

  • Park, Chul-Hwan;Park, Chan;Jeon, Yang-Soo;Park, Yeon-Jun
    • Tunnel and Underground Space
    • /
    • v.12 no.2
    • /
    • pp.115-119
    • /
    • 2002
  • Four tunnels have been planned to operate a large diameter shielded TBM in Gwangju urban subway construction site. No.1 tunnel has completely been excavated for 13 months operating. Net penetration rate and its relations with thrust farce of the shielded TBM are analysis in this report. This shallow depth tunnel of 536m length is located in soil layers at launching and in hard rocks at ending with 84 m length. The weekly net penetration rates haute dropped down as low as 20∼110 mm/hr in rock while 400∼800 mm/hr in soil. The actual penetration rates we proved to be high as the theoretical penetration rate which is analysis in consideration of conditions of machine and rock. And net penetration rate is investigated to increase linearly thrust force.

A Case Study on the Selection and Apply of Rock Excavation Method at Urban Tunnel (도심지 터널에서의 암반 굴착공법 선정 및 적용에 관한 사례연구)

  • 원연호;신일재;기경철;이무희;손영복
    • Explosives and Blasting
    • /
    • v.20 no.1
    • /
    • pp.25-34
    • /
    • 2002
  • 일반적으로 도심지에서 터널 시공을 위한 암반굴착 작업은 주변 보안물건에 대해 직접적인 피해를 유발시킬 수 있는 공해요소인 진동을 허용기준값 이하로 제어할 수 있으면서 상대적으로 시공성과 경제성이 뛰어난 공법으로 수행되어야 한다. 본 사례에서는 각내의 대표적인 문화시설인 예술의 전당 하부를 통과하는 우면산 터널 공사현장에서 암반굴착공법으로 고려한 TTM 장비를 이용한 기계굴착, 플라즈마 공법, 유압장비를 이용한 할암공법, 겔파쇄 공법, 미진동파쇄기를 이용한 공법, 진동제어발파공법에 대한 현장 적용성을 시험시공 등을 통해 평가한 내용과 결과를 제시하였다. 비록 각 도심지 터널의 현장 상황이나 주변 여건에 따라 이 현장에서의 시험시공 내용이나 적용 결과를 그대로 적용할 수는 없겠지만, 진동제어 암반굴착 공법에 대한 시험시공이나 선정 과정에 이 사례연구가 개략적인 참고자료로 활용될 수 있을 것이다.

A Study on the Development of the Rock Blastability Classification and the Methods for Minimizing Overbreak in Tunnel (터널 굴착면 여굴 최소화를 위한 발파암 분류(안) 및 공법 개발 연구)

  • 이태노;김동현;서영화
    • Explosives and Blasting
    • /
    • v.20 no.3
    • /
    • pp.25-38
    • /
    • 2002
  • 터널 굴착선 여굴(Overbreak)은 발파공법에 의한 괄착 중에 필연적으로 발생하는 현상으로서 숏크리트, 라이닝 등의 보강비 추가 발생과 버력 처리량의 증대로 공기 및 공사비를 증가시키는 주요한 요인으로 작용한다. 또한 터널 굴착선 암반의 손상으로 균열층이 형성되거나 부석이 발생하여 안전문제를 야기시키기도 한다. 이러한 여굴 발생은 천공오차, 발파패턴의 오류, 잘못된 화약선정, 불규칙한 암반 특성 등에 그 원인이 있으나, 지금까지 터널 여굴은 천공 및 발파기술에 의해 좌우된다라는 인식이 대부분이었다. 그러나 여굴 발생에 중요한 원인으로 터널 굴착선 암반의 특성과 이에 적합한 발파패턴 및 화약류를 들 수 있다. 본 연구는 여굴 발생에 영향을 미치는 암반상태를 파악하기 위해서 터널 굴착선 주변암반의 균열정도, 강도, 불연속면의 간격, 방향, 간극, 충전물 상태 등의 6가지 요소를 이용하여 암반을 분류하는 발파암 분류법(BI)을 새로 제안하였고, 이 분류에 따라 외곽 공의 간격과 장약밀도를 달리 하는 발파패턴을 정립하였다. 또한 화약의 순폭도와 Air Deck 효과를 이용하여 장약밀도를 조절할 수 있는 N.D.C(New Deck Charge) 발파공법을 개발함으로써 여굴을 최소화할 수 있었다.

Application of a Hydraulic Rock Splitting System to Bench-Cut Field Experiments (수압암반절개시스템을 이용한 벤치컷 현장 적용 사례 연구)

  • Park, Jong Oh;Woo, Ik
    • The Journal of Engineering Geology
    • /
    • v.32 no.4
    • /
    • pp.725-733
    • /
    • 2022
  • This study applied a hydraulic rock splitting system equipped with a hybrid packer to the bench-cut method. The hybrid packer system is an improvement of the packer developed in previous studies; it is designed efficiently to reduce vibration and noise during rock excavation by combining the two functions of inducing hydraulic fractures using injection pressure and then expanding and extending them using a rubber packer. Field experiments assessed the efficiency of rock excavation with respect to the injection conditions; the adjusted experimental conditions included the distance from the free surface and the test holes drilled at the top of the slope and the injection settings. Using a separation of 5 m left some unexcavated parts, but using a separation of 1 m left no unexcavated parts. The hydraulic fractures generated by the injection pressure developed generally parallel to the free surface and expanded and extended as the rubber packer expanded, thus facilitating bench-cut excavation. For hydraulic rock splitting to be broadly applicable to bench-cut rock excavation, it is important to accumulate results from many field experiments conducted under varying experimental conditions for various types of rockmass.

A study on the utilization of abrasive waterjet for mechanical excavation of hard rock in vertical shaft construction (고강도 암반에서 수직구 기계굴착을 위한 연마재 워터젯 활용에 관한 연구)

  • Seon-Ah Jo;Ju-Hwan Jung;Hee-Hwan Ryu;Jun-Sik Park;Tae-Min Oh
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.25 no.5
    • /
    • pp.357-371
    • /
    • 2023
  • In cable tunnel construction using TBM, the vertical shaft is an essential structure for entrance and exit of TBM equipment and power lines. Since a shaft penetrates the ground vertically, it often encounters rock mass. Blasting or rock splitting methods, which are mainly used to the rock excavation, cause public complaints due to the noise, vibration and road occupation. Therefore, mechanical excavation using vertical shaft excavation machine are considered as an alternative to the conventional methods. However, at the current level of technology, the vertical excavation machine has limitation in its performance when applied for high strength rock with a compressive strength of more than 120 MPa. In this study, the potential utilization of waterjet technology as an excavation assistance method was investigated to improve mechanical excavation performance in the hard rock formations. Rock cutting experiments were conducted to verify the cutting performance of the abrasive waterjet. Based on the experimental result, it was found that ensuring excavation performance with respect to changing in ground conditions can be achieved by adjusting waterjet parameters such as standoff distance, traverse speed and water pressure. In addition, based on the relationship between excavation performance, uniaxial compressive strength and RQD, it was suggested that excavation performance could be improved by artificially creating joints using the abrasive waterjet. It is expected that these research results can be utilized as fundamental data for the introduction of vertical shaft excavation machines in the future.

Hydro-mechanical Behavior of a Circular Opening Excavated in Saturated Rockmass (포화된 암반에 굴착된 원형공동의 수리-역학적 거동)

  • Lee Youn-Kyou;Shin Hee-Soon
    • Explosives and Blasting
    • /
    • v.23 no.2
    • /
    • pp.23-35
    • /
    • 2005
  • Excavation of an opening in a saturated porous rock may lead to the development of pore pressure around the opening due to the redistribution of initial rock stresses. The built-up of pore pressure, in turn, may affect the mechanical behavior of rock mass and give the different pattern of stress distribution around the opening from that of the case where the coupling is neglected. In this study, the short time response of an opening excavated in saturated ground under anisotropic initial stress conditions was investigated numerically. Not on the wall of opening but at a short distance from the wall, the tangential stresses were peak during the short period after excavation when the hydro-mechanical coupling is considered.

Estimation from Field Tests of the Excavation Efficiency of an Improved Hydraulic Rock Splitting System (현장실험을 통한 개선된 수압암반절개시스템의 굴착 효율성 평가)

  • Park, Jong Oh;Woo, Ik
    • The Journal of Engineering Geology
    • /
    • v.31 no.4
    • /
    • pp.719-730
    • /
    • 2021
  • An improved packer and injection system was developed to improve the efficiency of excavation by hydraulic rock splitting by reducing vibration and noise. Field testing of the system found hydraulic fractures limited in expansion and extension due to the loss of injection pressure by leackage from the cracks, and then the single packer applied to injection hole allowed to produce a sufficient tensile displacement for rock excavation. Numerical analysis based on the field test data could explain the development of cracks in the field experiments.

Rock Socket Roughness with Drilling Tools (굴착장비에 따른 암반근입말뚝의 공벽 거칠기)

  • Nam, Moon-S.
    • Journal of the Korean Geotechnical Society
    • /
    • v.23 no.1
    • /
    • pp.13-21
    • /
    • 2007
  • Rock socketed drilled shafts are used as foundations for bridges and other transportation structures because of their load carrying capabilities. However, only limited information is available in the literature on the effects of roughness on the unit side resistance of rock socketed drilled shafts. The objective of this study is to investigate the effect of drilling tools on the socket roughness in soft clay shale in Texas. Field study showed that the drilling tools, auger and core barrel, produced different roughness in the boreholes.

Pillar load and ground deformation in 2-arch tunnel in the jointed rock mass (절리암반에서 2-Arch 터널의 필라하중과 지반변위)

  • Lee, Sang-Duk
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.9 no.1
    • /
    • pp.91-97
    • /
    • 2007
  • Loads on the pillar and ground deformation in 2-arch tunnel, which is excavated in the rock mass with regular discontinuities, depending on the dips of discontinuities and the construction sequences were experimentally studied. Large scale model tests in the biaxial test facility were performed. Tested model (width 3.3m, height 3.0m, and length 0.45m) for 2-arch tunnel in 1/10 scale were built with various dips. Test results show that discontinuities have greate affects on the behavior of the 2-arch tunnel, especially on the pillar loads and ground deformation.

  • PDF

Rock Mass Classification and Its Use in Blast Design for Tunneling (암분류기법과 터널굴착을 위한 발파설계에의 활용)

  • Ryu Chang-Ha;SunWoo Choon;Choi Byung-Hee
    • Explosives and Blasting
    • /
    • v.24 no.1
    • /
    • pp.63-69
    • /
    • 2006
  • Building tunnels means dealing with what rock is encountered. Relocation of the site of the underground structure is rarely possible. Tunneling engineers and miners have to cope with the quality of the rock mass as it is. Different tunneling philosophies and different rock classification methods have been developed in various countries. Most of the rock classification methods are based on the response of the rock mass to the excavation. Tunnel support requirements could be assessed analytically, supplemented by rock mass classification predictions, and verified by measurements during construction. Rock mass classifications on their own should only be used for preliminary, planning purposes and not for final tunnel support. Design of blast pattern in tunneling projects in Korea is also mostly prepared according to the general rock classification methods such as RMR or Q. They, however, do not take into account the blast performance, and as a consequence, produce poor blasting results. In this paper, the methods of general rock classification and blast design for tunnel excavation in Korea are reviewed, and efforts to develop a new classification method, reflecting the blasting performance, are presented.