Development of shield-TBM scale model system for excavation of curved section  

Kong, Min-Teak (Dept. of Civil Engineering, Hoseo University)
Kim, Yeon-Deok (Dept. of Civil Engineering, Hoseo University)
Lee, Kyung-Heon (Dept. of Civil Engineering, Hoseo University)
Hwang, Beoung-Hyeon (Dept. of Civil Engineering, Hoseo University)
An, Jun-Kyu (Dept. of Civil Engineering, Hoseo University)
Kim, Sang-Hwan (Dept. of Civil Engineering, Hoseo University)
Publication Information
Journal of Korean Tunnelling and Underground Space Association / v.21, no.6, 2019 , pp. 849-860 More about this Journal
Abstract
This paper is a study on the development of equipment system to obtain data on stability in excavation of sharp curve section of Shield TBM. Shield TBM equipment is being used a lot recently for tunnel excavation. Excavation may result in inevitable detours by buildings above the ground or existing underground structures. Preconstruction simulation is required to verify the stability of the construction in case of this. Therefore, it is necessary to establish an automated control system through the development of this equipment system and conduct simulation through simulation of excavation model in the sharp curve section. A system shall be developed to control the left and right angles and thrust of the equipment, and to view data on the earth pressure and propulsion pressure of the equipment in real time during excavation. With this system, the necessary data can be collected for field testing through excavation method and excavation simulation by angle. It is expected that it will be very useful in assessing the actual Shield TBM by conducting a scale-down model experiment.
Keywords
Shield TBM; Excavation simulation; Control system;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 Chang, S.H., Choi, S.W., Park, Y.T., Lee, G.P., Bae, G.J. (2013), "Experimental evaluation of the effects of cutting ring shape on cutter acting forces in a hard rock", Journal of Korean Tunnelling and Underground Space Association, Vol. 15, No. 3, pp. 225-235.   DOI
2 Cho, J.W., Yu, S.H., Jeon, S.W., Chang, S.H. (2008), "Numerical study on rock fragmentation by TBM disc cutter", Journal of Korean Tunnelling and Underground Space Association, Vol. 10, No. 2, pp. 139-152.
3 Kang, E.M., Kim, Y.M., Hwang, I.J., Kim, S.H. (2015), "A study on the damage of cutter bit due to the rotation speed of shield TBM cutter head in mixed ground", Journal of Korean Tunnelling and Underground Space Association, Vol. 17, No. 3, pp. 403-413.   DOI
4 Kang, S.O., Kim, H., Kim, Y.M., Kim, S.H. (2017), "Application technique on thrust jacking pressure of shield TBM in the sharp curved tunnel alignment by model tests", Journal of Korean Tunnelling and Underground Space Association, Vol. 19, No. 2, pp. 335-353.   DOI
5 Kim, J.D. (2011), A study on ground behavior of model test shield TBM during excavation, Engineering Structures, Hoseo University of Graduate School, Master's Degree, pp. 1-77.
6 Oh, T.S., Kim, B.S, Shin, H.C, Kim, S.H. (2011), "A study on ground behavior of shield TBM lunching area during excavation", Proceedings of the Korean Society for Railway Conference, Vol. 2011, No. 10, Jeju, pp. 353-364.
7 Sugimoto, M., Sramoon, A., Konishi, S., Sato, Y., (2007), "Simulation of shield tunneling behavior along a curved alignment in a multilayered ground", Journal of Geotechnical and Geoenvironmental Engineering, Vol. 133, No. 6, pp. 684-694.   DOI