A study on the estimation of the optimal number of monitoring points in single-track tunnel lining with the inverse analysis program  

Woo, Jong-Tae (Dept. of Construction and Environmental Design, Kyungbok University)
Publication Information
Journal of Korean Tunnelling and Underground Space Association / v.16, no.1, 2014 , pp. 1-11 More about this Journal
Abstract
In order to determine the optimal number of monitoring points in single-track tunnel lining, this thesis compares and evaluates the results of two cases: when the tunnel lining is modeled into a simple beam form and then is applied to 1) the tunnel lining inverse analysis program, and to 2) the commercially-used program. The displacement and stress of specific tunnel lining cross-sections are determined by entering the load conditions into the commercially-used program for tunnel interpretations. In doing so, two cases were assumed: where a symmetrically-distributed load was acting upon the tunnel lining of a single-track tunnel and where an asymmetrically-distributed load was in action. By comparing the computed displacement with the stress and displacement determined by entering side numbers 3, 5, and 7 into the tunnel lining inverse analysis program, the optimal number of monitoring points is determined. From the results of the research, it can be inferred that the number of monitoring points needs to be at least 5 points, considering the efficiency of monitoring in practice and the loss-and-damage rate of tunnel monitoring.
Keywords
Single-track tunnel lining; Inverse analysis method; Inverse analysis program; Optimal number of monitoring points;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 Lee, D.H., Han, I.Y., Kim, G.S., Jin, S.W. (2000), "Case studies on applications of convergence measurement system at the stages of tunnel construction and maintenance", Journal of Korean Tunnelling and Underground Space Association, Vol. 2, No. 3, pp. 59-69.
2 Back, K.H., Oh, Y.S., Kim, Y.J., Kim, Y.G. (2002), "A study on efficiency of tunnel maintenance monitoring", Journal of Korean Tunnelling and Underground Space Association, Vol. 4, No. 4, pp. 355-369.
3 Hinton, E., Owen, D.R.J. (1977), "Finite element programming", Academic Press, pp. 1-305.
4 Hisatake, M., Ito, T. (1983), "Back analysis methods to tunnel linings", International Symposium on Field Measurements in Geomechanics, pp. 1047-1056.
5 Sakurai, S. (1981), "Direct strain evaluation technique in construction of underground openings", In Proceedings 22nd U.S. Symposium Rock Mechanics, pp. 278-282.
6 Sakurai, S., Takeuchi, K. (1983), "Back analysis of measured displacements of tunnels", Rock Mechanics & Rock Engineering, pp. 173-180.
7 Woo, J.T. (2006), "Theory and practice of tunnel monitoring", Goomi Publishing Co., pp. 91-95.
8 Woo, J.T. (2009), "A study on comparison of a ground water influx quantity in Seoul subway tunnel", Journal of Korean Tunnelling and Underground Space Association, Vol. 11, No. 4, pp. 353-359.   과학기술학회마을
9 Woo, J.T. (2010), "A study of the present state analysis and development plans about construction monitoring and monitoring industry", Journal of Korean Society of Civil Engineers, Vol. 30, No. 2D, pp. 163-169.   과학기술학회마을
10 Woo, J.T. (2013), "A study on estimation of the total loss and damage ratio of maintenance monitoring sensor of subway tunnel", Journal of Korean Tunnelling and Underground Space Association, Vol. 15, No. 1, pp. 25-31.   과학기술학회마을   DOI