A Study on Considering Non-Working Days for Determination Normal Project Duration in the Railway Bridgework Construction  

Chae, Su Min (WESTERN Metro CO., Ltd)
Lee, Sang Hyuck (Chungbuk National University)
Park, Hyung Keun (Chungbuk National University)
Publication Information
KSCE Journal of Civil and Environmental Engineering Research / v.41, no.5, 2021 , pp. 601-608 More about this Journal
Abstract
Recently, despite a decrease in the number of working days and an increase in the number of non-working days due to an increase in the abnormal climate and the revision of the Labor Standards Act, a standard construction period reflecting this has not been established. For this reason, even if the appropriate construction period is calculated at the site, there is a situation where delays occur due to unexpected circumstances. Therefore, this study proposes a method of calculating the number of non-working days for railway bridgework construction that reflects changes in construction conditions and climate change and reflects this to railway bridgework construction, and the number of working days was calculated. As a result, the number of non-working days by region and month in Korea was derived, and through this, the necessity of regulations and standards for appropriate construction periods reflecting regional characteristics and characteristics of each construction type was presented.
Keywords
Abnormal climate; Appropriate construction duration; Railroad bridgework; Non-working day;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Ko, K. J. (2015). A study on the change of non-working days through BCP analysis, Master Dissertation, Incheon National University (in Korean).
2 Lee, S. H. (2021). An effective method considering non-working days for determination of normal project duration in the railroad roadbed construction, Master Dissertation, Chungbuk National University (in Korean).
3 Ministry of Land, Infrastructure and Transport (MOLIT) (2019). Construction period calculation standard for public construction works (in Korean).
4 Park, I. B. (2010). A study on the estimation of non-working days due to climate condition, Master Dissertation, University of Cheongju (in Korean).
5 Kwon, S. B. (2007). Study on the influence of the weather factors on productivity and number of working days in marine construction, Master Dissertation, Seoul National University of Science and Technology (in Korean).
6 Ministry of Employment and Labor (MOEL) (2019). Rules on occupational safety and health standards (in Korean).
7 Jeong, S. N. and Lee, H. K. (2000). "A preliminary study on the effective decision-making support model for duration by the hypothetical weather simulation." Journal of The Architectural Institute of Korea, Vol. 20, No. 2, pp. 587-590 (in Korean).
8 Land and Housing Research Institute (LH) (2014). A study on the method of estimating the construction duration for apartment to assure quality (in Korean).
9 Lee, G. H. (2005). Improvement of non non-working day estimation affected by weather conditions in the construction projects, Master Dissertation, University of Ajou (in Korean).
10 Ministry of Environment (MOE) (2019). High concentration of fine dust Guidelines for implementing emergency reduction measures (in Korean).
11 Yoon, J. S. (2020). Development of method for quantifying and applying non-working day to planning and scheduling to calculate normal project duration, Ph.D. Dissertation, University of Ajou (in Korean).
12 Bang, J. D., Song, S. H., Cho, G. H., Sohn, J. R. and Kim, J. W. (2015). "A study on non-working day calculation standards and days of non-working for estimation of optimum duration in the frame work of apartment building." Journal of the Architectural Institute of Korea Structure & Construction, Vol. 31, No. 10, pp. 21-28 (in Korean).   DOI