Risk Influencing Factors in Performance of River Disaster Prevention Project  

Cho, Jin-Ho (Kyungpook National University)
Kim, Byung-Soo (Kyungpook National University)
Publication Information
KSCE Journal of Civil and Environmental Engineering Research / v.40, no.4, 2020 , pp. 417-428 More about this Journal
Abstract
The characteristics of the construction project involved various stakeholders' involvement from the planning stage until completion of the object, which caused the uncertainty to increase. Successful construction projects require risk analysis and appropriate responses. Therefore, this study aimed to confirm the influence of risk management factors on the success of river disaster prevention construction in construction projects and the effect of moderating communication between stakeholders involved in the construction process. The Delphi method was used to derive the risk management factors of the construction process. The survey used a snow ball sampling method. For analysis, SPSS Statistic 20 and SmartPLS 2.0 were used. As a result of the study, the impact of risk management factors on project performance was found to be large in the order of time risk, quality risk, cost risk, safety risk, and construction environment risk. In addition, the impact of the communication moderating effect was large in the order of cost risk, quality risk, construction environment risk, time risk, and safety risk. In this study, it was confirmed that communication between stakeholders related to river disaster prevention work has a moderating effect that changes the ranking of impacts on project performance. This shows the importance of communication in the construction process of river disaster prevention works. This study has important significance in that it identifies the importance of risk management factors and communication in river disaster prevention works.
Keywords
River disaster prevention project; Risk management factors; Communication; Project performance;
Citations & Related Records
Times Cited By KSCI : 10  (Citation Analysis)
연도 인용수 순위
1 Kaplan, R. S. and Norton, D. P. (2001). "Transforming the balanced scorecard from performance measurement to strategic management: Part I." Accounting Horizons, Vol. 15, No. 1, pp. 87-104.   DOI
2 Kim, H. Y., Kang, S. B. and Lee, J. H. (2013). "Wiki-based expert knowledge collaboration effects on performance of project members." Journal of Information Technology Services, Vol. 12, No. 1, pp. 173-187 (in Korean).   DOI
3 Kwon, D. S. and Kim, J. H. (2011). "The effects of self-determination theory on reality, flow in online community." The Journal of Information Systems, Vol. 20, No. 2, pp. 177-206 (in Korean).   DOI
4 Lee, S. K., Lee, H. L. and Yu, J. H. (2010). "The effect of PMIS quality on project management success." Journal of the Korea Institute of Building Construction, Vol. 10, No. 6, pp. 117-126 (in Korean).   DOI
5 Lee, T. W., Park, N. S. and Kim, S. C. (2014). "A study on the effect of risk management factors on project performance in construction projects." Korea Project Management Research, Vol. 4, No. 1, pp. 1-11 (in Korean).
6 Seo, J. W., Yoon, J. H., Kim, J. H. and Jee, S. H. (2010). "Development of risk analysis structure for large-scale underground construction in urban areas." Journal of the Korean Geotechnical Society, Vol. 26, No. 3, pp. 59-68 (in Korean).
7 Zhi, H. (1995). "Risk management for overseas construction projects." International Journal of Project Management, Vol. 13, No. 4, pp. 231-237.   DOI
8 Chapman, R. J. (2001). "The controlling influences on effective risk identification and assessment for construction design management." International Journal of Project Management, Vol. 19, No. 3, pp. 147-160.   DOI
9 Ahn, S. H. (2015). "Case study on risk identification in construction projects." Korean Institute of Construction Engineering and Management, Vol. 16, No. 1, pp. 15-23 (in Korean).   DOI
10 Ahn, S. S. and Chung, J. M. (2018). "A study on the influential factors to power plant construction project quality control: Focused on collective civil complaints of nuclear power plant construction." Journal of the Korean Society for Quality Management, KSQM, Vol. 46, No. 2, pp. 351-374 (in Korean).   DOI
11 Chin, W. W. (1998). "The partial least squares approach to structural equation modeling." Modern Methods for Business Research, Vol. 295, No. 2, pp. 295-336.
12 Cho, J. H. (2017). "An empirical study on top management's leadership in construction quality management activities and construction quality management performance." Journal of the Korean Society for Quality Management, KSQM, Vol. 45, No. 3, pp. 403-426 (in Korean).   DOI
13 Choi, J. H., Sohn, H. W. and Kim, S. K. (2011). "Key performance indicators of building project." Journal of the Korea Institute of Building Construction, Vol. 11, No. 1, pp. 61-72 (in Korean).   DOI
14 Cohen, S. and Brand, R. (1990). "Total quality management in the us environmental protection agency." Public Productivity & Management Review, Vol. 14, No. 1, pp. 99-114.   DOI
15 Jung, W. J. (2016). "A study on PR communication strategies for enhancing governance effect of public conflict in energy facilities business; focusing on milyang transmission line construction project." Public Relations Studies, Vol. 20, No. 3, pp. 84-112 (in Korean).   DOI
16 Fornell, C. and Larcker, D. F. (1981). "Structural equation models with unobservable variables and measurement error: Algebra and statistics." Journal of Marketing Research, Vol. 18, No. 3, pp. 382-388.   DOI
17 Hair Jr, J. F., Hult, G. T. M., Ringle, C. and Sarstedt, M. (2016). A primer on partial least squares structural equation modeling (PLS-SEM), SAGE Publications, California, USA.
18 Han, S. H., Lee, Y., Kim, H. J. and Ock, J. H. (2001). "A study on the corporate portfolio risk management for multinational construction company." Korean Journal of Construction Engineering and Management, KJCEM, Vol. 2, No. 2, pp. 68-80 (in Korean).
19 Hong, S. W., Kim, H. I. and Ahn, Y. S. (2003). "A study on the actual condition analysis and improvement direction of risk management in Korean construction companies." Korean Institute of Architectural Studies-Structure, Vol. 19, No. 5, pp. 153-160 (in Korean).
20 Jung, T. S. (2005). "The research and correspondence of schedule risk management at the pre-construction phase of curtain-wall." Korean Journal of Construction Engineering and Management, KJCEM, Vol. 6, No. 4, pp. 71-79 (in Korean).
21 Kang, S. J. and Hong, J. P. (2014). "A study on economic evaluation of SNG project using real option valuation model." Transactions of the Korean Hydrogen and New Energy Society, Vol. 25, No. 3, pp. 319-335 (in Korean).   DOI