Application of Linear Schedule Chart by Linking Location Information of Construction Project with Horizontal Work Space  

Han, Seon Ju (Gyeongsang National University ERI)
Kim, Hyeon Seung (GeoNT)
Park, Sang Mi (Gyeongsang National University)
Kang, Leen Seok (Gyeongsang National University, ERI)
Publication Information
KSCE Journal of Civil and Environmental Engineering Research / v.38, no.4, 2018 , pp. 601-610 More about this Journal
Abstract
Since the building construction works are repeated vertically in a limited space, there is not a great need for the location information of each activity in the schedule management. On the other hand, civil engineering works such as road and railway projects consist of a large number of earthworks, long bridges, and long tunnels. These types of work should be controlled in a horizontal space according to the linear axis of several tens of kilometers. In other words, since most of the activities are managed in the unit of distance from the start point to the end point, it is possible to improve the efficiency of the schedule management by linking the location information of the activity with the schedule data in the schedule management system. This study presents a methodology for creating a linear schedule chart specific to a project with horizontal work space and compares the convenience with the existing Gantt chart. In addition, the methodology of linking linear schedule chart to the 4D CAD system, which is a typical BIM technology in the construction phase, is presented to improve the usability of BIM. The practical applicability of the proposed methodology was verified statistically.
Keywords
Linear schedule chart; Schedule management; Horizontal work space; 4D CAD;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Agrama, F. A. E.-M. (2011). "Linear projects scheduling using spreadsheets features." Alexandria Engineering Journal, Vol. 50, No. 2. pp. 179-185.   DOI
2 Biruk, S. and Jaskowski, P. (2017). "Scheduling linear construction projects with constraints on resource availability." Archives of Civil Engineering, Vol. 63, No. 1, pp. 3-15.
3 Go, H. J. (2011). "A study on improvement method of construction schedule management techniques by linear scheduling model." Master Thesis, Hongik University (in Korean).
4 Kim, W. J. (2012). "Effectiveness of linear scheduling methods in nuclear power plant construction." Master Thesis, Myongji University (in Korean).
5 Lee, G. S. and Park, H. S. (2011). "Implementation of time management; based on road construction projects." Journal of the Korean Society of Civil Engineers, KSCE, Vol. 31, No. 3. pp. 451-456 (in Korean).
6 Liu, L., Liu, Y. and Tang, Y. (2016). "Production rate determination for linear construction projects based on linear scheduling method." International Journal of Smart Home, Vol. 10, No. 4, pp. 143-152.
7 Tilos, Available at: https://www.tilos.org (accessed Dec. 2016).