A Study of Improving the Reliability of VE Process  

Shin, Sung-In (Inha University)
Woo, Sungkwon (Inha University)
Jin, Sung-Ho (Inha University)
Choi, Seok-In (Construction Economy Research Institute of Korea)
Publication Information
KSCE Journal of Civil and Environmental Engineering Research / v.36, no.5, 2016 , pp. 881-889 More about this Journal
Abstract
The VE evaluation process, in which the value is composed of the cost and the function, should have a characteristic of quantitative analysis based on specific figures rather than qualitative approach. However, most of the VE evaluation performed domestically have a problem of having no systematic process of quantification of the function, even though the cost is estimated and analyzed quantitatively. Moreover, in addition to the tendency of strong practical experience, the VE evaluation has the problem of limited application of practical scientific analysis caused by declining the suggestion of creative opinions by over quantification or over objectification. This paper presents the suggestions for improvement of VE evaluation processes, which satisfies the aspects of simplification and objectification, without hindering the essence of the evaluation in the practical business point of view.
Keywords
Value engineering; Construction VE; VE process; Limitation; Improvement area;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Im, J. R. (2008). "VE/LCC Analyzing process model for the selection of mechanical system in apartment." Master's thesis, Sungkyunkwan University.
2 Kim, H. H. (2009). "A process model for effective idea creation and administration of value engineering at design phase activity." Master's thesis, Namseoul university.
3 Kim, H. Y. (2008). "A study on the improvement of function definition and assessment in the design phase VE." Master's thesis, Seoul National University Science & Technology.
4 Kim, J. H. (2009). "Function oriented VE alternatives evaluation procedure using function classification." Master's thesis, University of Seoul.
5 Kim, K. H. (2009). "A study on the optimal selection of backfill method using VE/LCC analysis for urban underground railway." Master's thesis, SEOUL National University of Science & Technology.
6 Kim, S. Y. (2006). "Analysis of main control factors for design value engineering work in construction projects." Journal of Construction Management, KSCE, Vol. 7, No. 1, pp. 128-137.
7 Korea Environment Corporation (2012). "Design VE work manual." KECO2010-RE02-12, Korea Environment Corporation.
8 Kwon, T. S. (2004). "A study on the methodology to select optimum choice for construction value engineering." Master's thesis, Yonsei University.
9 Ministry of Land, Infrastructure and Transport (2008). "1st Design VE competitive exhibition casebook." Available at: https://www.calspia.go.kr/.
10 Ministry of Land, Infrastructure and Transport (2009). "2nd Design VE Competitive Exhibition Casebook." Available at: https://www.calspia.go.kr/.
11 Ministry of Land, Infrastructure and Transport (2010). "3rd Design VE Competitive Exhibition Casebook." Available at: https://www.calspia.go.kr/.
12 Satty, T. L. (1980). "The analytic hierarchy process." McGraw-Hill.