Development of Construction Benchmarking for Oversea Industrial Projects  

Park, Hee-Sung (Hanbat National Univ.)
Publication Information
KSCE Journal of Civil and Environmental Engineering Research / v.33, no.3, 2013 , pp. 1165-1171 More about this Journal
Abstract
The oversea construction contract amount has sharply increased since 2003. The contractor's capability for EPC and project management is a key factor for a successful industrial construction project. Construction performance measurement and evaluation is needed to improve contractor's project management capability. Therefore, this paper proposes the construction performance benchmarking program for oversea industrial projects. Performance metrics consists of project cost, schedule, quality, and safety. Data from 10 oversea industrial projects were collected and analyzed. Also, this paper describes the process for development of the benchmarking program and lessons learned from industry are summarized. Finally, this paper recommends how sustainable benchmarking program should be established and implemented.
Keywords
Industrial Project; Benchmarking; Performance Analysis;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Ko, Y. S., Yoon, H. S., and Lee, J. H. (2004). Performance management in the public sector, KDI.
2 Park, H. S. (2007). "Public infrastructure practitioner's recognition on project performance." Construction Management, Vol. 8, No. 2, pp. 93-100 (in Korean).
3 Lee, K. S., and Moon, H. P. (1995). National budget and policy goals: Government Innovation, KDI (in Korean).
4 ICAK and HNU (2010). Development of a performance framework for oversea plant projects, MLTM (in Korean).
5 Atkinson, R. (1999). "Project management: Cost, Time, and Quality, Two Best Guesses and a Phenomenon, It's Time to Accept Other Success Criteria." International Journal of Project Management, Vol. 17, No. 6, pp. 337-342.   DOI   ScienceOn
6 Brown, A., and Adams, J. (2000). "Measuring the effect of project management on construction outputs: a new approach." International Journal of Project Management, Vol. 18, No. 5, pp. 327-335.   DOI   ScienceOn
7 Bubshait, A. A., and Almohawis, S. A. (1994). "Evaluating the general conditions of a construction contract." International Journal of Project Management, Vol. 12, No. 3, pp. 133-135.   DOI   ScienceOn
8 Chan, A. P. C. (1996). Determinants of project success in the construction industry of Hong Kong. Ph.D thesis, Univ. of South Australia.
9 Chan, A. P. C. (2000). "Evaluation of enhanced design and build system-A case study of hospital project." Construction Management and Economics, Vol. 18, No. 8, pp. 863-871.   DOI
10 Chan, M., Nizette, M., La Rance, L., Broughton, C., and Russel, D. (2002). "Australia." OECD Journal on budgeting, Vol. 1, No. 4, pp. 35-69.   DOI
11 Costa, D. B., Formoso, C. T., Kagioglou, M., Alarcon, L. F., and Caldas, C. H. (2006). "Benchmarking initiatives in the construction industry: Lessons learned and improvement opportunities." Journal of Management in Engineering, ASCE, Vol. 22, No. 4, pp. 158-167.   DOI   ScienceOn
12 Cox, R., Issa, R. A., and Ahrens, D. (2003). "Management's perception of key performance indicators for construction." Journal of Construction Engineering and Management, ASCE, 1292: 142-151.
13 Fisher, D., Minertschin, S., and Pollock, D. R., (1995). "Benchmarking in construction industry." Journal of Management in Engineering, ASCE, Vol. 11, No. 1, pp. 50-57.   DOI   ScienceOn
14 Hatush, Z., and Skitmore, M. (1997). "Criteria for contractor selection." Construction Management and Economics, Vol. 15, No. 1, pp. 19-38.   DOI
15 Meade, G., Rankin, J., and Manseau, A. (2006). "Performance of the canadian construction industry - a benchmarking pilot." Canadian Civil Engineer, Vol. 23, No. 4, pp. 8-11.
16 Naoum, S. G. (1994). "Critical analysis of time and cost of management and traditional contracts." Journal of Construction Engineering and Management, ASCE, Vol. 120, No. 4, pp. 687-705.   DOI   ScienceOn
17 Newcombe, R. (2000). "The anatomy of two projects: A Comparative Analysis Approach." International Journal of Project Management, Vol. 18, No. 3, pp. 189-199.   DOI   ScienceOn
18 OECD (1999). Improving evaluation practices: Best Practice Guidelines for Evaluation and Background Paper, PUMA/PAC (99)1.
19 Park, H. S. (2002). Development of construction productivity metrics system, Ph.D dissertation, Univ. of Texas, Austin, Tex.
20 Park, H. S., Thomas, S. R., and Tucker, R. L. (2005). "Benchmarking of construction productivity." Journal of Construction Engineering and Management, ASCE, Vol. 131, No. 7, pp. 772-778.   DOI   ScienceOn
21 Shenhar, A. J., Levy, O., and Dvir, D. (1997). "Mapping the dimensions of project success." Project Management Journal, Vol. 28, No. 2, pp. 5-13.
22 Songer, A. D., and Molenaar, K. R. (1997). "Project characteristics for successful public-sector design-build." Journal of Construction Engineering and Management, ASCE, Vol. 123, No. 1, pp. 34-40.   DOI   ScienceOn