Strut as a Permanent System using Composite Beams  

Hong, Won-Kee (경희대학교 건축공학과)
Park, Seon-Chee (경희대학교 대학원)
Kim, Jin-Min (경희대학교 대학원)
Lee, Ho-Chan ((주) MCS Tech.)
Publication Information
KIEAE Journal / v.8, no.1, 2008 , pp. 87-92 More about this Journal
Abstract
Sheathing work used for excavation in a crowded downtown is generally a temporary strut method using H-piles and sheathing wall includes lagging, CIP, SCW or slurry wall. A temporary strut serving the support for sheathing wall acts to resist the earth pressure, but it shall be removed when installing the underground structure members. A traditional temporary strut might cause the stress imbalance of the sheathing wall when it is demolished, resulting in time extension and the risk of collapse. A traditional temporary strut method thus needs to be improved for schedule and cost reduction, risk mitigation and for preparation for potential civic complaint. A permanent strut method doesn't require installing and demolishing the temporary structure that will lead to reducing the time and cost and the structural risk during the demolition process. And given the girder, the part of the underground structure, serves the role of strut, it can secure the wider interval compared to the traditional method, which enables to secure the wider space for the convenience of excavation as well as enhance the constructability and efficient site management. The thesis was intended to study the composite girder designed to use the strut as permanent structure so as to reduce the excavation and floor height.
Keywords
earth retaining wall; strut; excavation; construction cost; construction period;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Ali, M.A., White, R.N., "Consideration of compression stress bulging and strut degradation in truss modeling of ductile and brittle corbels", Engineering structures, v.23 no.3, 2001, pp.240-249   DOI   ScienceOn
2 Brian Uy, and Mark Andrew Bradford. (1995). "Ductility of profiled Composite beams. Part II : Analytical study." Journal of Structural Engineering, ASCE, 121(5), 883-889   DOI   ScienceOn
3 Clough, G.W., O'Rourke, T.D., "Construction Induced Movements of Institute Walls", Design and Performance of Earth Retaining Strudtures. Geotechnical Special publication, No. 25, ASCE, pp.439-470, 1990
4 최재원, 윤지언, 김광희, 강경인, "PS 띠장을 이용한 버팀대식 흙막이 공법의 적용 사례분석", 대한 건축학회 논문집, 20권 8호, pp.115-122, 2004
5 Ali Mirza, S., Ville hyttinen, and Esko Hyttinen. (1996). "Physical tests and analyses of composite steel-concrete beam-columns." Journal of Structural Engineering, ASCE, 122(11), 1317-1326   DOI   ScienceOn
6 Brian Uy, and Mark Andrew Bradford. (1995). "Ductility of profiled Composite beams. Part I : Experimental study. "Journal of Structural Engineering, ASCE, 121(5), 876-882   DOI   ScienceOn
7 홍원기, 김선국, 김희철, "구조물 겸용 흙막이 스트러트 공법", 한국 건설관리 학회 논문집, 5권 3호, pp. 71-78, 2004