Development of Determination System for Optimal Combination of Earthwork Equipments  

Park, Jae-Woo (Construction Policy Institute, Korea Institute of Civil Engineering and Building Technology)
Yeom, Dong-Jun (Construction Policy Institute, Korea Institute of Civil Engineering and Building Technology)
Publication Information
Journal of the Korean Society of Industry Convergence / v.23, no.6_2, 2020 , pp. 957-969 More about this Journal
Abstract
The primary objective of this study is to develop a determination system for an optimal combination of earthwork equipment that improves the traditional way in convenience, prediction accuracy, and productivity. For this, the following research works are conducted sequentially; 1)literature review, 2)technology development trend analysis, 3)develop a determination system for the optimal combination of earthwork equipment, 4)simulation of a developed system. As a result, core considerations are deducted for the development of a determination system. Furthermore, site simulation is performed using a developed system. Site simulation result, Cluster 1(R1200LC 7㎥, CAT 775G 65ton×2) was selected from 6 clusters because of its production cost (₩491/㎥). It is expected that the application range and impact on the construction industry will be enormous due to the availability of the developed system.
Keywords
Civil Engineering; Construction Equipment; Earthwork; Combination; System;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Korea Specialty Contractors Association (KOSCA), "2018 Contract Performance of Industrial Classification", Statistical Yearbook, (2019).
2 S.K. Won, S. K. Kim and C. H. Han, "A Combination Model of Earthwork Equipment using System Dynimics", Korean Journal of Construction Engineering and Management, KICEM, 8(2), pp. 194-202, (2007).
3 J. H. Kim, J. W. Seo, "BIM based Intelligent Excavation System", Journal of KIBIM, 1(1), pp. 1-5, (2011).   DOI
4 S. S. Lee, J. H. Jang, C. W. Yoon, J. W. Seo, "Development of the Local Area Design Module for Planning Automated Excavator Work at Operation Level", Journal of the Korean Society of Civil Engineers, 33(1), pp. 363-375, (2013).   DOI
5 H. J. Kim, H. J. Song, N. H. Kang, J. H. Choi, "Optimized Construction Equipment Combination to Reduce Carbon Emission in Earthwork", 2014 Proceeding of Korean Journal of Construction Engineering and Management, pp.155-156, (2014).
6 J. H. Hwang, H. W. Hwang, B. S. Kim, "Conceptual Design of Optimization Model for Earthwork Equipment Combination using Multiobjective Optimization Method", 2009 Proceeding of Korean Journal of Construction Engineering and Management, pp.205-210, (2009).
7 B. I. Yu, J. S. Ahn, S. W. Oh, S. W. Han, Y. S. Kim, "A Study on Selection of Key Enabling Technologies for Automation of Realtime Ground Shape Recognition and Soil Volume Estimation", 2007 Proceeding of Korean Journal of Construction Engineering and Management, pp.347-352, (2007).
8 C. Y. Yi, H. C. Lee, J. W. Seo, D. E. Lee, "Construction Equipment Fleet Optimization for Energy Saving in Earthmoving Operation", Journal of the Architectural Institute of Korea Structure & Construction, 31(4), pp.137-144, (2015).   DOI
9 J. H. Choi, D. H. Lee, S. H. Kim, S. K. Kim, "Factors Affecting Selection & Combination of Earthwork Equipment", Proceeding of Spring Annual Conference of the Korea Institute of Building Construction, 10(1), pp.201-205, (2010).
10 H. Kim, R. Jeon, C. Lee, "The Deduction of CO2 Emission Influence Factors for Earthwork Equipment", 2012 Proceeding of Korean Journal of Construction Engineering and Management, pp.11-14, (2012).
11 Doosan Infracore, "Estimating System of Doosan Infracore", Doosan Infracore Construction Equipment Website, , (Oct. 2020).
12 Caterpillar, "Caterpillar Performance Handbook", Caterpillar Website, , (Oct, 2020).
13 Volvo, "Volvo Construction Equipment Site Simulation", , (Oct, 2020).