Process Planning for Finishing Works of High-rise Residential Buildings Project  

Baek, Tae-Yong (Department of Architecture, Bucheon University)
Publication Information
Journal of the Korea Academia-Industrial cooperation Society / v.18, no.11, 2017 , pp. 110-117 More about this Journal
Abstract
In the construction of high-rise residential buildings in which the finishing works are done repetitively in each housing unit, the construction period and cost can be reduced, while maintaining the quality, if the work process is properly managed in order for the resources to be input continuously. Time management methods such as the Bar Chart, CPM and LOB are not appropriate, due to the difficulties involved in the diagraming of repetitive works and applying them to the project. The Tact method also has difficulties in maintaining a constant work flow and needs significant effort and cooperation from the subcontractors to allocate the resources consistently. Partitioning, base works for finishing, floor mortar plastering and the final finishing work are done sequentially in residential buildings projects, and there are many repetitive activities which differ in terms of the work method, work area and productivity. If these repetitive activities are synchronized or converged toward the last work area, the goal of process management can be achieved effectively. Therefore, a process planning method for the finishing works of residential building projects is proposed, which takes into consideration elements, such as the sequential relation between the activities in each housing unit and classification of repetitive works in terms of their management method, work area and production rate, for the continuous input of resources into the housing units.
Keywords
Finish work; Process management; Repetitive activity; Residential project; Tact method;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Y. Kim, J. Han, D. Shin, K. Kim, C. Kim, S. Seo, "A Tact Planning and Scheduling Process Model for Reduction of Finishing Work Duration in Building Construction Projects", Journal of the Architectural Institute of Korea Structure & Construction, vol. 19, no. 1, pp. 161-168, 2003.
2 S. Seo, G. Lee, "Construction Management and Engineering", p. 240, Kimundang, 1999.
3 D. Shin, "Application Plan of TACT Process for Finish Works in Apartment Housing Projects", MS Thesis, Graduate School of Urban Science, University of Seoul, 2009.
4 K. Kim, "A Study on Improvement of Repetition Process Management for Finish Works Quality of Construction -Focused on Apartment Housing Projects-", MS Thesis, Graduate School of Architectural Engineering, Yonsei University, 2014.
5 T. Kim, "Improvement of TACT Scheduling Process in Finishing Works of the Residential Housing", MS Thesis, Graduate School of Architecture, Aju University, 2008.
6 Y. Yoon, Y. Joung, S. Seo, D. Shin, C. Kim, K. Kim, "Improvement of Construction Process management dividing the work area reasonably in Building Construction", Korean Journal of Construction Engineering and Management, KICEM, vol. 4, no. 2, pp 059-065, 2005.
7 H. Ryu, T. Kim, "Analysis of Boundary Conditions for Activities' Relationships in Linear Scheduling Model", Korean Journal of Construction Engineering and Management, KICEM, vol. 12, no. 1, pp. 023-032, 2011. DOI: https://doi.org/10.6106/KJCEM.2011.12.1.23   DOI