Causes of Delay in Khuzestan Steel Company Construction Projects  

Saeb, Sajjad (Department of Civil Engineering, Ahvaz Branch, Islamic Azad University)
Khayat, Navid (Department of Civil Engineering, Ahvaz Branch, Islamic Azad University)
Telvari, Abdulrasoul (Department of Civil Engineering, Ahvaz Branch, Islamic Azad University)
Publication Information
Industrial Engineering and Management Systems / v.15, no.4, 2016 , pp. 335-344 More about this Journal
Abstract
Construction project is a competitive business with high risk especially in developing countries like Iran which faces with many problems such as delay and time and costs increases. Thus, the first priority here is to determine the causes of prolongation of construction projects and to evaluate their importance. Khuzestan Steel Company (KSC) has made important contribution to the projects in Iran and in turn is required to finish them on time. In this study, an attempt was made to investigate the causes of delay in implementation of construction projects held by this company. Data was collected through questionnaire distributed among the sample including 10 owners, 10 consultants and 15 con-tractors. Accordingly, participants rated the causes in the questionnaire so the most important priorities of each area were specified using TOPSIS method. The results showed that according to the employers, consultants and contractors' viewpoints, the most important reason for delays in construction projects of KSC is related to the financial matters. Hence, according to the results obtained, causes for delays in the company's projects are largely related to the drilling permits and long administrative cycle to renew them. Besides, continuous production of steel in this company is another reason to delays of construction projects.
Keywords
Construction Projects; Delay; Khuzestan Steel Company; Prolongation;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Aziz, R. F. and Abedel-Hakam, A. A. (2016), Exploring delay causes of road construction projects in Egypt, Alexandria Engineering Journal, In Press.
2 Chan, D. W. M. and Kumaraswamy, M. M. (2002), Compressing construction duration: lessons learned from Hong Kong building projects, International Journal of Project Management, 20(8), 23-35.   DOI
3 Ezeldin, A. and Abdel-Ghany, M. (2013), Causes of construction delays for engineering projects: an Egyptian perspective, AEI, 54-63.
4 Frimpong, Y., Oluwoye, J., and Crawford, L. (2003), Causes of delay and cost overruns in construction of groundwater projects in a developing countries: Ghana as a case study, International Journal of Project Management, 21, 321-326.   DOI
5 Golenko-Ginzburg, D., Gonik, A., and Laslo, Z. (2003), Resource constrained scheduling simulation model for alternative stochastic network Projects, Mathematics and Computers in Simulation, 63(2), 105-117.   DOI
6 Habibi, A., Izadyar, S., and Sarafrazi, A. (2014), Fuzzy Multi-Criteria Decision Making, Published by the inscription Gill. (In Persian).
7 Hamzah, N., Khoiry, M. A., Arshad, I., Badaruzzaman, W. H. W., and Tawil, N. M. (2012), Identification of the causes of construction delay in Malaysia, World Acad. Sci., Eng. Technol., WASET. Int. Journal of Civ.Sci. Eng., 6(12), 578-583.
8 Hasseb, M., Xinhai-Lu, A., Bibi, M., and Dyian, W. R. (2011), Problems of projects and effects of delays in the construction industry of Pakistan, Austr. Journal of Bus. Manage. Res., 1(5), 41-50.
9 James, G. and Zack, J. R. (2004), Schedule analysis is there agreement?, Presentation, 5-6.
10 Kaliba, C., Muya, M., and Mumba, K. (2009), Cost escalation and schedule delays in road construction projects in Zambia, International Journal of Project Management, 27(3), 522-531.   DOI
11 Marzouk, M., El-Dokhmasey, A., and El-Said, M. (2008), Assessing construction engineering-related delays: Egyptian perspective, Journal of Professional Issues in Engineering Education and Practice, 134(2), 315-326.   DOI
12 Kamikg, P. F., Olomolaiye, P. O., Gray, D., Holt, F., and Harris, C. (1997), Factors influencing construction time and cost overruns on high-rise projects in Indonesia, Construction management and economics, 83-94.
13 Khanzadi, M., Afandizadeh Zargari, S. H., and Abrishamchi, I. (2011), Estimated delay in the construction of road construction projects due to weather conditions using analyzing fuzzy-probability, Transportation Journal, 8(3), 211-224.
14 Mansfield, N., Ugwu, O., and Doran, T. (1994), Causes of delay and cost overruns in Nigerian construction projects, International Journal of Project Management, 12(1), 254-260.   DOI
15 Menesi, W. (2007), Construction delay analysis under multiple baseline updates, A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of Applied Science in Civil Engineering.
16 Ogunlana, S. O., Promkuntong, K., and Jearkjirm, V. (1996), Construction delays in a fast-growing economy: comparing Thailand with other economies. Int. J. Project Manage, 14(1), 37-45.   DOI
17 Mola'ie, F. and Ghazanfari Nia, J. (2009), Investigating of delay causes in construction projects, Management publication. 6th ed., 314(7).
18 Ndekugri, I., Braimah, N., and Gameson, R. (2008), Delay analysis within construction contracting organizations, The Journal of Construction Engineering and Management, ASCE, 134(9), 692-700.   DOI
19 Odeh, A. and Battaineh, H. (2002), Causes of construction delay: traditional Contracts, International Project Management, 20(1), 67-73.   DOI
20 Ruqaishi, M. and Bashir, H. (2015), Causes of delay in construction projects in the oil and gas industry in the Gulf Cooperation Council countries: a case study, Journal of Manage. Eng., 31(3).
21 Sambasivan, M. and Soon, Y. (2007), Causes and effects of delays in Malaysian construction industry, International Project Management, 25(2), 517-526.   DOI
22 Schumacher, L. (1995), Quantifying and apportioning delay on construction projects, J. Cost Eng, 37, 11-13.
23 Thomas Ng, S. and Tang, Z. (2010), Labour-intensive construction sub-contractors: Their critical success factors, International Journal of Project Management, 28, 732-740.   DOI
24 Aziz, R. (2013), Ranking of delay factors in construction projects after Egyptian revolution, Alexandria Eng. J., 52(3), 387-406.   DOI
25 Aibinu, A. and Odeyinka, H. (2006), Construction delays and their causative factors in Nigeria, J. Constr. Eng. Manage, 132(7), 667-677.   DOI
26 Al-Kharashi, A. and Skitmore, M. (2009), Causes of delays in Saudi Arabian public sector construction projects, Construction Management and Economics, 27(1), 3-23.   DOI
27 Assaf, S. A. and Al-Hejji, S. (2006), Causes of delay in large construction projects, International Journal of Project Management, 24, 349-357.   DOI
28 Yang, J. B. and Wei, P. R. (2010), Causes of delay in the planning and design phases for construction projects, Journal of Architectural Engineering, 16(3), 80-83.   DOI
29 Trohid, S. A. (2004), Setting methodology to determine the activities portion in creating projects delay for separate administrators, Master dissertation, Industry Engineering course, Amir-Kabir Industrial Uniersity, 160.
30 Williams, T. (2003), Assessing extension of time delays on major projects, International Project Management, 21(1), 19-26.   DOI