An Improved Ant Colony System for Parallel-Machine Scheduling Problem with Job Release Times and Sequence-Dependent Setup Times  

Joo, Cheol-Min (Dept. of System and Management Engineering, Dongseo University)
Publication Information
Journal of Korean Institute of Industrial Engineers / v.35, no.4, 2009 , pp. 218-225 More about this Journal
Abstract
This paper considers a parallel-machine scheduling problem with job release times and sequence-dependent setup times. The objective of this problem is to determine the allocation policy of jobs and the scheduling policy of machines so as to minimize the weighted sum of setup times, delay times, and tardy times. A mathematical model for optimal solution is derived and a meta heuristic algorithm based on the improved ant colony system is proposed in this paper. The performance of the meta heuristic algorithm is evaluated through compare with optimal solutions using randomly generated several examples.
Keywords
Parallel-Machine Scheduling; Ant Colony System;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Dorigo, M., Birattari, M., and Stutzle, T. (2006), Ant Colony Optimization : Artificial Ants as a Computational Intelligence Technique, TR/IRIDIA/2006-023, University Libre De Bruxelles, Belgium
2 Dorigo, M. and Blum, C. (2005), Ant colony optimization theory : Asurvey, Theoretical Computer Science, 344, 243-278   DOI   ScienceOn
3 Dorigo, M., Maniezzo, V., and Colorni, A. (1996), The Ant System : Optimization by a Colony of Cooperating Agents, IEEE Transactions on Systems, 26, 29-41
4 Mendes, A. S., Muller, F. M., Franca, P. M., and Moscato, P. (2002), Comparing metaheuristic approaches for parallel machine scheduling problems, Production Planning and Control, 13, 143-154   DOI   ScienceOn
5 Shyu, S. J., Lin, B. M. T., and Lin, P.Y. (2004), Application of ant colony optimization for no-wait flowshop scheduling problem to minimize the total completion time, Computers and Industrial Engineering, 47, 181-193   DOI   ScienceOn
6 Ying, K. and Liao, C. (2004), An ant colony system for permutation flow-shop sequencing, Computers and Operations Research, 31, 791-801   DOI   ScienceOn
7 Bell, J. E. and McMullen, P. R. (2004), An colony optimization technique for the vehicle routing problem, Advanced Engineering Informatics, 18, 41-48   DOI   ScienceOn
8 Bobrowski, P. M. and Kim, S. C. (1994), The impact of sequence dependent setup time on job shop scheduling performance, International Journal of Production Research, 32, 1503-1520   DOI   ScienceOn
9 Garey, M. and Johnson, D. (1997), Computers and intractability : A guide to the theory of NP-completeness, New York : W. H. Freeman
10 Hahn, C. K., Bragg, D. J., and Shin, D. W. (1989), Impact of the setup variable on capacity and inventory decisions, Academic Management Review, 13, 91-103
11 Flynn, B. B. (1987), The effects of setup time on output capacity in cellular manufacturing, International Journal of Production Research, 25, 1761-1772   ScienceOn
12 Behnamian, J., Zandieh M., and Ghomi, F. (2009), Parallel-machine scheduling problems with sequence-dependent setup times using an ACO, SA and VNS hybrid algorithm, Expert Systems with Applications, 36, 9637-9644   DOI   ScienceOn
13 Nessah, F., Yalaoui, F., and Chu, C. (2005), New heuristics for identical parallel machine scheduling with Sequence-dependent setup times and dates, In Proceedings of the international conference on industrial engineering and systems management, Marrakech, Morocco, 32- 41
14 Dorigo, M. and Di Caro, G. (1999), The Ant Colony Optimization Meta-heuristic, New Ideas in Optimization, McGraw-Hill
15 Dorigo, M. and Gambardella, L. M. (1997), Ant Colony System : A cooperative learning approach to the traveling salesman problem, IEEE Transactions on Evolutionary Computation I, 1, 53-66   DOI   ScienceOn
16 Frederickson, G., Hecht, M. S., and Kim, C. E. (1978), Approximation algorithm for some routing problems, SIAM Journal on Computing, 7, 178-193   DOI
17 Gharehgozli, A. H., Tavakkoli-Moghaddam, R., and Zaerpour, N. (2009), A fuzzy-mixed-integer goal programming mode for a parallel-machine scheduling problem with sequence- dependent setup times and relaeas dates, Robotics and Computer-Integrated Manufacturing, 25, 853-859   DOI   ScienceOn
18 Cheng, C. and Mao, C. (2007), A modified ant colony system for solving the traveling salesman problem with time window, Mathematical and Computer Modeling, 46, 1225-1235   DOI   ScienceOn
19 Pinedo, M. (1995), Scheduling theory, algorithms, and systems, Prentice-Hall
20 Tahar, D. N., Yalaoui, F., Chu, C., and Amodeo, L. (2006), A linear programming approach for identical parallel machine scheduling with job splitting and sequence-dependent setup times, International Journal of Production Economics, 99, 63-73   DOI   ScienceOn
21 Solimanpur, M., Vart, P., and Shankar, R. (2004), Ant colony optimization algorithm to the inner-cell layout problem in cellular manufacturing, European Journal of Operations Research, 157, 592-606   DOI   ScienceOn