Cost-Schedule Tradeoff in Software Project  

Lee, Sang-Un (Dept. of Multimedia Engineering, Gangnung-Wonju National University)
Choi, Myeong-Bok (Dept. of Multimedia Engineering, Gangnung-Wonju National University)
Publication Information
The Journal of the Institute of Internet, Broadcasting and Communication / v.13, no.4, 2013 , pp. 99-106 More about this Journal
Abstract
Generally, software development schedule compression is decided within 75% of nominal schedule. However, there are some difficulties when we judge the possibility of development schedule compression because a nominal schedule has not been definitely. Therefore, this paper investigates various nominal schedule estimation models and decides the optimum range. Basing on the performance of ISBSG Release 8,614 projects are extracted from the actual 1,595 projects. We presented development effort estimation model from those data. Also, we derived the development schedule model from the development effort. When you apply the proposed model, you will be able to estimate development effort and schedule required for the development more actually.
Keywords
Impossible Region; Practical Region; Optimal Region; Impractical Region; Cost-Schedule Trade-off;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 G. Sifri, "Accurate Estimates Critical for Software Development Projects," ESI International, Inc., 2001
2 R. Mukcher, "Business Case for A Common Services Based Architecture," OMG Document #3-300, 2000.
3 M. Holtsinger, "CIS 4251/CIS 5930 Software Development," 1999.
4 D. R. Jones, "Project Scheduling," Augsburg College, 1999.
5 C. Carbno, "Optimal Resource Allocation for Projects," Project Management Journal, 1999.
6 B. W. Boehm, "Software Engineering Economics," Prentice Hall, 1981.
7 L. H. Putnam and W. Myers, "Familiar Metric Management - Time-to-Market, http://www.qsm.com/fmm_08.pdf
8 D, L, Hallowell, "Software Project Management Meets Six Sigma," http://software.isixsigma.com/ library/content/c030813a.asp, iSixSigma Magazine, 2003.
9 Construx, "10 Deadly Sins of Software Estimation," Construx Software Builders, Inc., 2002.
10 Y. Yang, Z. Chen, R. Valerd, and B. Boehm, "Effect of Schedule Compression on Project Effort," 5th Joint International Conference & Educational Workshop, the 15th International Annual Conference for the Society of Cost Estimating and Analysis and 27th Annual Conference of the International Society of Parametric Analysis, Denver, Colorado, USA., 2005.
11 L. H. Putnam and W. Myers, "Measures of Excellence: Reliable Software on Time, Withen Budget," Yourdon Press, 1992.
12 C. Jones, "Assessment and Control of Software Risks," Yourdon Press, 1994.
13 L. H. Putnam and W. Myers, "Five Core Metrics: The Intelligence Behind Successful Software Management," Dorset House Publishing, 2003.
14 L. H. Putnam and W. Myers, "What We Have Learned," The Journal of Defense Software Engineering, 2000.
15 C. Simons, "Software Sizing and Estimating: MK II," John Wiley & Sons, 1991.
16 M. Ardis, "Estimation: CSSE 372, Software Project Management," Rose-Hulman Institute, 2004.
17 C. W. Cook and J. Stubbendieck, "Range Research: Basic Problems and Techniques," Society for Range Management, Denvor, Co., pp. 232-241, 1986.
18 J. B. Park, H. S. Yang, "Quality Evaluation Method of Open Source Software," Journal of the Korea Academia-Industrial, Cooperation Society, Vol. 13, No. 5 pp. 2353-2359, 2012.   DOI   ScienceOn
19 D. S. Kim, H. C. Kim, "The Study of Software Reliability Model from the Perspective of Learning Effects for Burr Distribution," Journal of the Korea Academia-Industrial Cooperation Society, Vol. 12, No. 10 pp. 4543-4549, 2011.   과학기술학회마을   DOI   ScienceOn
20 C. Fakharzadeh, "CORADMO in 2001: A RAD Odyssey," 16th International Forum on COCOMO and Software Cost Modeling, USC-CSE, 2001.
21 B. Boehm, B. Clark, E. Horowitz, R. Modachy, R. Shelby, and C. Westland, "The COCOMO 2.0 Software Cost Estimation Model," USC Center for Software Engineering, 1995.
22 J. A. Ward, "Productivity Through Project Management: Controlling the Project Variables," Information Management, 1994.
23 M. Mah, "Controlling Software Development," SPIN Newsletter, 1997.
24 S. U. Lee, M. B. Choi, "A Definition and Evaluation Criteria for Software Development Success," Journal of The Institute of Internet, Broadcasting and Communication (IIBC), pp.233-241, vol. 12, no.2, April 2012.   과학기술학회마을   DOI   ScienceOn
25 R. Pressman, C. Jones, V. Basilli, and L. Putnam, "16 Critical Software Practices, Estimate Cost and Schedule Empirically," http://www.iceinusa.com/ 16CSP/content/ 2-cost/anmetrgt.html
26 A. J. Shenher, "Improving PM: Linking Success Criteria to Project Type," Project Management Institude, Creating Canadian Advantage through Project Management Symposium, Calgory, 1996.
27 L. K. Richard, "Staff IT," http://www.gantthead.com, 2005.
28 M. Holtsinger, "CIS 4251/CIS 5930 Software Development," 1999.
29 C. Abts, A. W. Brown, S. Chulani, B. K. Clark, E. Horowitz, R. Madachy, D. Reifer, and B. Steece, "Software Cost Estimation with COCOMO II," Prentice-Hall, 2000.
30 C. Jones, "Applied Software Measurements," McGraw Hill, 1996.
31 Marin Consultancy, "Estimation, Marin Solutions Technical Paper, 2001.
32 S. McConnell, "Rapid Development: Taming Wild Software Schedules," Microsoft Press, 1996.
33 C. E. Walston and C. P. Felix, "A Method of Programming Measurement and Estimation," IBM Systems Journal, Vol. 16, No. 1, pp. 54-73, 1977.   DOI   ScienceOn
34 G. Booker, "Info 638 Software Project Management: Estimation, WBS, and Scheduling, "2000.
35 ISBSG, "Worldwide Software Development - The Benchmark Release 8," Victoria, Australia International Software Benchmarking Standards Group, 2004.