A Generating Cost Evaluation of APR+ Standard Design  

Ha, Gag-Hyeon (KHNP Central Research Institute)
Kim, Sung-Hwan (KHNP Central Research Institute)
Lee, Jae-Ho (KHNP Central Research Institute)
Publication Information
Abstract
KHNP CRI has been developing APR+ nuclear power plant since 2007, which is GEN III+ model with 1500 MWe capacity. To develop safer and more economical nuclear power plant than APR1400, we investigated advanced design features of ALWR(advanced light water reactor) being constructed in Korea and being developed/constructed in foreign countries. We applied the advanced design features and lessons learned from Fukushima accident to develop APR+ standard design suitable for both domestic construction and overseas construction business. Three economic assessments have performed during standard design phase of APR+. The result of the 3th(final) economic analysis for APR+ standard design showed that APR+ N-th plant was about 23% more economical than coal-fired 1,000MW power plant.
Keywords
APR+; Total Capital Cost; O&M cost; Fuel Cost; Generating Cost;
Citations & Related Records
연도 인용수 순위
  • Reference
1 EPRI, Technical Assessment Guide, Volume 1, Rev.7, 1993
2 EPRI, Technical Assessment Guide, Volume 3, Rev.7, 1997
3 EPRI, ALWR Cost Estimating Groudrules, 1995
4 한수원 중앙연구원, APR+ 2단계 표준상세설계 개발 세부3과제 경제성평가보고서(3차), Nov. 2012
5 지식경제부, 제 5차 전력수급기본계획(2010-2024), 2010
6 지식경제부, 피동안전설비 적용 기술개발, APR+1단계 세부 2과제, 2010
7 한국전력공사, 차세대원자로기술개발(II) 경제성 평가 최종보고서, Feb. 1999
8 지식경제부고시 제2011-197호, Oct. 2011