Abstract
The use of TBM (tunnel boring machine) gradually increases in worldwide tunneling projects. TBM machine are often applied to more difficult and complex geological conditions in urban area, and many problems and difficulties have been reported due to these geological conditions. However, in Korea, there is a lack of research on difficult grounds so far. This paper discussed general aspects of investigation method, and problems of TBM tunneling in difficult grounds. Construction cases that passed through the difficult grounds in worldwide were analyzed and the typical difficult grounds were classified into 11 cases. For each case, the definition and general problems were summarized. Particularly, for mixed ground and boulder ground, and fault zone, which are frequent geological conditions in urban area with shallow depth, classification system, investigation methods and major considerations were discussed, and proposed the direction of future research. This paper is a basic study for the development of TBM construction technology in difficult ground, and it is expected that it will be useful for related research and construction of TBM in difficult ground in the future.
Keywords
TBM; difficult grounds; mixed grounds; boulder condition; fault zone; classification system;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 Kim, Y.K., 2017, Key issue and technical dilemma of selection of TBM type - EPB vs. Slurry, Magazine of Korean Tunnelling and Underground Space Association, Vol. 19, No. 2, 39-51.
2 Kovari, K., Ramoni, M., 2006, Urban tunnelling in soft ground using TBMs, International Conference and Exhibition on Tunnelling and Trenchless Technology: Tunnelling and trenchless technology in the 21st century, Subang Jaya-Selangor, Malaysia, 17-31.
3 Lee, S.D., Jeong, H.Y, Jeon, S., 2012, Determination of rock abrasiveness using Cerchar abrasiveness test, Tunnel and Underground Space, Vol. 22, No. 4, 284-295.   DOI
4 Lee, K.H., Seo, H.J., Park, J.J., Park, J.H., Lee, I.M., 2016, A probabilistic assessment of ground condition prediction ahead of TBM tunnels combining each geophysical prediction method, J. of Korean Tunn Undergr Sp Assoc, 18(3), 257-272.   DOI
5 Li, S.C., Liu, B., Xu, X.J., Nie, L.C., Liu, Z.Y., Song, J., Sun, H.F., Chen, L., Fan, K.R., 2017, An overview of ahead geological prospecting in tunneling, Tunnelling and Underground Space Technology, Vol. 63, 69-94.
6 McFeat-Smith, I., 2016, TBM tunnelling in extreme geological conditions: from mixed ground conditions in Asia's urban areas to challenges in the Himalayas, International Conference on Tunnel Boring Machines in Difficult Grounds (TBM DiGs 2016), Istanbul, Turkey.
7 Paltrinieri, E., Sandrone, F., Zhao, J., 2016, Analysis and estimation of gripper TBM performances in highly fractured and faulted rocks, Tunnelling and Underground Space Technology, Vol. 52, 44-61.
8 Poot, S., Boone, S.J., Westland, J., Pennington, B., 2000, Predicted Boulder Frequency Compared to Field Observations during Construction of Toronto's Sheppard Subway, In: Proceedings of Tunneling Association of Canada 2000 Conference, 47-54.
9 Ringen, A., 2016, Compaction and Jet. Grouting, Breakthroughs in Tunneling Short Course, University of Colorado, September 14, Colorado, USA.
10 Sandell, T., 2017, Rondout West Branch Bypass Tunnel Advancements in Mechanized Excavation A TBM Boring in hard rock against high water pressure and high water inflows beneath the Hudson River in New York, Proceedings of ITA-AITES World Tunnel Congress 2013 (WTC 2013), Bergen, Norway.
11 Santi, P.M., 2006, Field Methods for Characterizing Weak Rock for Engineering, Environmental and Engineering Geoscience, Vol. 12, No. 1, 1-11.   DOI
12 Shirlaw, J.N., 2015, Pressurized TBM Tunnelling in mixed face conditions resulting from tropical weathering of igneous Rock, International Conference on Tunnel Boring Machines in Difficult Grounds (TBM DiGs 2015), Singapore.
13 Toth, A., Gong, Q.M, Zhao, J., 2013, Case studies of TBM tunneling performance in rock-soil interface mixed ground", Tunnelling and Underground Space Technology, Vol. 38, 140-150.
14 Shirlaw, J.N., 2016, Pressurised TBM tunnelling in mixed face conditions resulting from tropical weathering of igneous rock, Tunnelling and Underground Space Technology, Vol. 57, pp. 225-240.
15 Steingrimsson, J.H., GrOv, E., Nilsen, B., 2002, The significance of mixed-face conditions for TBM performance, World Tunnelling, 15, 435-441.
16 Terzaghi, K., 1950, Chapter 11: Geologic aspects of soft ground tunneling. Applied sedimentation. Wiley, New York.
17 Thewes, M., 2004, Schildvortrieb mit Flussigkeits-oder Erddruckstützung in Bereichen mit Gemischter Ortsbrust aus Fels und Lockergestein, Geotechnik, Vol. 27, No. 2, pp. 214-219.
18 Thewes, M., Hollmann, F., 2015, Clogging of TBMs in clay soils and clay-rich rock, International Conference on Tunnel Boring Machines in Difficult Grounds (TBM DiGs 2015), Singapore.
19 Tunnel Business Magazine, 2016, TBM Tunneling the Chengdu Metro, Benjamin Media, Inc. http://tunnelingonline.com/tbm-tunneling-chengdu-metro/
20 Vergara, I.M., Saroglou, C., 2017, Prediction of TBM performance in mixed-face ground conditions, Tunnelling and Underground Space Technology, Vol. 69, 116-124.
21 Yagiz, S., 2006, TBM performance prediction based on rock properties", Proceedings of Multiphysics Coupling and Long Term Behavior in Rock Mechanics, EUROCK, Vol. 6, 663-670.
22 Zhao, J., Gong, Q.M., 2006, Rock Mechanics and Excavation by Tunnel Boring Machine - issues and challenges, Proceedings of the ISRM International Symposium 2006 and the 4th Asian Rock Mechanics Symposium, Singapore.
23 Yagiz, S., 2008, Utilizing rock mass properties for predicting TBM performance in hard rock condition, Tunnelling and Underground Space Technology, Vol. 23, No. 3, 326-339.
24 Yagiz, S., Karahan, H., 2011, Prediction of hard rock TBM penetration rate using particle swarm optimization, Rock Mechanics and Mining Science, Vol. 48, No. 3, 427-433.
25 Zarei, H.R, Sharifzadeh, M., Uromyehic, A., 2011, Gas ground risks and geological investigations for TBM tunneling in Iran, First Asian and 9th Iranian Tunneling symposium, Tehran, Iran.
26 Zhao, J., Gong, Q.M., Eisensten, Z., 2007, Tunnelling through a frequently changing and mixed ground: A case history in Singapore, Tunnelling and Underground Space Technology, Vol. 22, 388-400.
27 Zhao, J., Gong, Q.M., 2015, TBM tunneling under adverse geological conditions - An overview, Keynote lecture, International Conference on Tunnel Boring Machines in Difficult Grounds (TBM DiGs 2015), Singapore.
28 Zhang, C.S., Liu, N., Chu, W.J., 2016, Key technologies and risk management of deep tunnel construction at Jinping II hydropower station, Journal of Rock Mechanics and Geotechnical Engineering, Vol. 8, No. 4, 499-512.
29 American Association of State Highway and Transportation Officials (AASHTO), 1988, Manual on Subsurface Investigations, Washington, D.C.
30 Amoun, S., Sharifzadeh, M., Shahriar, K., Rostami, J., 2015, Soil abrasiveness for EPB-TBM along Tehran metro tunnel line 7, Iran, World Tunnelling Congress, ITA WTC, Dubrovnik, Croatia, May.
31 ASTM, 2011, Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System) (D2487-11)
32 Barla, G., S. Pelizza, S., 2000, TBM tunnelling in difficult ground conditions, GeoEng2000 - An International Conference on Geotechnical & Geological Engineering, Melbourne, Australia.
33 Barla, G., 2001, Tunnelling Under Squeezing Rock Conditions, Eurosummer-School in Tunnel Mechanics, Innsbruck, Logos Verlag, Berlin, 169-268.
34 Barton, N., 2000, TBM Tunnelling in Jointed and Faulted Rock, Rotterdam: Balkema.
35 Barton, N.R., Lien, R., Lunde, J., 1974, Engineering classification of rock masses for the design of tunnel support. Rock Mechanics and Rock Engineering, 6, 189-236.
36 Barzegari, G., Uromeihy, A., Zhao, J., 2014, EPB tunneling challenges in bouldery ground: a new experience on the Tabriz metro line 1, Bulletin of Engineering Geology and the Environment, 73, 429-440.
37 Bilgin, N., Ates, U., 2016, Probe Drilling Ahead of Two TBMs in Difficult Ground Conditions in Turkey, Rock Mechanics and Rock Engineering, Vol. 49, No. 7, 2763-2772.
38 Bayati, M., Hamidi, K.J., 2017, A case study on TBM tunnelling in fault zones and lessons learned from ground improvement, Tunnelling and Underground Space Technology, Vol. 63, 162-170.
39 Bieniawski, Z.T., 1976, Rock mass classifications in rock engineering. Proceedings Symposium on Exploration for Rock Engineering, Rotterdam, 97-106.
40 Bilgin, N., Algan, M., 2012, The performance of a TBM in a squeezing ground at Uluabat, Turkey, Tunnelling and Underground Space Technology, Vol. 32, 58-65.
41 Boone, S.J., Westland, J., Busbridge, J.R., Garrod, B., 1998, Prediction of Boulder Obstructions, In: Tunnels & Metropolises, Proceedings of World Tunnelling Congress 1998, 817-822.
42 Broere, W., 2016, Urban underground space: Solving the problems of today's cities, Tunnelling and Underground Space Technology, Vol. 55, 4-17.
43 Delisio, A., Zhao, J., 2014, A new model for TBM performance prediction in blocky rock conditions, Tunnelling and Underground Space Technology, Vol. 43, 440-452.
44 Delisio, A., Zhao, J., Einstein, H.H., 2013, Analysis and prediction of TBM performance in blocky rock conditions at the Lötschberg Base Tunnel, Tunnelling and Underground Space Technology, Vol. 33, 131-142.
45 Diponio M.A., Chapman D., Bournes C., 2007, EPB Tunnel Boring Machine Design for Boulder Conditions, In: Proceedings of 2007 Rapid Excavation and Tunneling Conference, Traylor M.T. & Townsend J.W. (Eds), SME, Littleton, Colorado, R2007.20, 215-228.
46 Diponio, M.A., 2016, Personal communication.
47 Gharahbagh, E.A., Rostami, J., Palomino, A.M., 2011, New soil abrasion testing method for soft ground tunneling applications, Tunnelling and Underground Space Technology, 26, 604-613.
48 Dong, A., Ma, G., Gong, Q.M., Zhao, J., 2006, Numerical simulation on rock cutter performance in mixed ground, Geoshanghai 2006, 199-204.
49 Fang, Y., Deng, R.Y., Walton, G., Wang, S.M., 2017, Performance of slurry TBM tunnelling in sandy cobble ground - A case study in Lanzhou, International Conference on Tunnel Boring Machines in Difficult Grounds (TBM DiGs 2017), Wuhan, China.
50 Filba, M., Salvany, J.M., Jubany, J., Carrasco, L., 2016, Tunnel boring machine collision with an ancient boulder beach during the excavation of the Barcelona city subway L10 line: A case of adverse geology and resulting engineering solutions, Engineering Geology, Vol. 200, 31-46.
51 Goss, C.M., 2002, Predicting Boulder Cutting in Soft Ground Tunneling, Proceedings of North American Tunneling 2002, Rotterdam: Balkema, 37-46.
52 Guglielmetti, V., Grasso, P., Mahtab, A., Xu, S., 2007, Mechanized Tunnelling in Urban Areas: Design methodology and construction control, Taylor & Francis Group, London.
53 Gong, Q. M., Yin, L. J., She, Q. R., 2013, TBM tunneling in marble rock masses with high in situ stress and large groundwater inflow: A case study in China. Bulletin of Engineering Geology and the Environment, Vol. 72, No. 2, 163-172.   DOI
54 Gong, Q.M., Liu, Q.S., Zhang, Q.B., 2016, Tunnel boring machines (TBMs) in difficult grounds, Tunnelling and Underground Space Technology, Vol. 57, 1-3.
55 Habimana, J., Labiouse, V., Descoeudres, F., 2002, Geomechanical characterisation of cataclastic rocks: experience from the Cleuson-Dixence project, International Journal of Rock Mechanics and Mining Sciences, Vol. 39, 677-693.
56 Heuer, R.E., 1974, Important parameters in soft ground tunneling, proceedings of specialty conference on subsurface exploration for underground excavation and heavy construction. ASCE, New York.
57 Hamidi, J.K., Shahriar, K., Rezai, B., Rostami, J., 2010, Performance prediction of hard rok TBM using Rock Mass Rating (RMR) system, Tunnelling and Underground Space Technology, Vol. 25, No. 4, 333-345.
58 Hassanpour, J., Rostami, J., Khamehchiyan, M., Bruland, A., 2009, Developing new equations for TBM performance prediction in carbonateargillaceous rocks: a case history of Nowsood Water conveyance tunnel, Geomechanics and Geoengineering, Vol. 4, No. 4, 287-297.   DOI
59 Hassanpour, J., Rostami, J., Khamehchiyan, M., Bruland, A., Tavakoli, H.R., 2010, TBM performance Analysis in Pyroclastic Rocks: A Case History of Karaj Water Conveyance Tunnel, Geomechanics and Geoengineering, Vol. 43, No. 4, 427-445.
60 Hassanpour, J., Rostami, J., Zhao, J., 2011, A new hard rock TBM performance prediction model for project planning, Vol. 25, No. 5, 595-603.
61 Hoek, E., Brown, E.T., 1998, Practical estimates of rock mass strength, International Journal of Rock Mechanics and Mining Sciences, 34, 1165-1186.
62 Hunt, S.W., 2002, Compensation for Boulder Obstructions. L. Ozdemir (ED), In: Proceedings of The North American Tunneling 2002, Ozdemer L., (Ed), Rotterdam: Balkema, 23-36.
63 Hunt, S.W., 2017, Tunneling in cobbles and boulders, Breakthroughs in Tunneling, Short Course, Colorado School of Mines, August 14-16, Chicago, USA.
64 Hunt, S.W., Del Nero, D.E., 2011, Tunneling in cobbles and boulders, Breakthroughs in Tunneling, Short Course, Colorado School of Mines, September 19-21, Colorado, USA.
65 Jee, W.W., Ha, S.G., 2007, Feasible Boulder treatment methods for soft ground shielded TBM, Proceedings of World Tunneling Congress 2007, Taylor & Francis Group, London, 217-222.
66 Kieffer, D.S., Leelasukseree, C., Mustoe, G.G.W., 2008, Disc cutter performance in boulder laden ground, Proceedings of North American Tunneling 2008, 129-136.
67 Kang, Y.K., Choi, I.C., 2015, Economic Feasibility of Common Utility Tunnel based on Cost-Benefit Analysis, Journal of Korean Society of Safety. Vol. 30, No. 5, 29-36.   DOI
68 KICT, 2010, TBM Technology Development for Mechanized and Automated Tunnel Construction, Research Report, Korea Institute of Construction Technology.