Behavior of Building Lower Part Passage Tunnel due to Adjacent Ground Excavation  

Lee, Jong-Min (주식회사 솔토)
Lee, Sang-Duk (아주대학교 환경건설교통공학부)
Publication Information
Tunnel and Underground Space / v.20, no.5, 2010 , pp. 369-377 More about this Journal
Abstract
Applied to the braced wall in order to stabilize the adjacent tunnel. A pre-load of bracing was imposed to prevent the horizontal displacement of the braced wall during the ground excavation. For this purpose, real scale model tests were conducted, without and with pre-load on braced wall. Real scale model tests were conducted, without and with building load (0 m, 1D, 2D) on ground surface. As a result, it was found that the stability of the existing tunnel adjacent to the braced wall could be greatly enhanced when the horizontal displacement of the braced wall was reduced by applying a pre-load, which was larger than the designated axial force of bracing. In this paper, the behaviors of braced wall and adjacent tunnel was studied. Model tests in 1:10 scale were performed in real construction sequences. Adjacent tunnel was 12 m in diameter and the size of test pit was 2.0 m (width) ${\times}$ 6.0 m (height) ${\times}$ 4.0 m (length) in dimension.
Keywords
Braced wall; Pre-loading; Adjacent tunnel;
Citations & Related Records
연도 인용수 순위
  • Reference
1 김일(2008), 근접굴착 시 흙막이벽체에 가하는 선행하중에 따른 터널의 거동, 공학박사학위 논문, 아주대학교.
2 Soliman E., Duddeck, H. and Ahrens, H.(1993), "Twoand three-dimensional analyis of closely spaced double-tube tunnels", Tunnelling and Underground Space Technology, Vol. 8, No. 1, pp. 13-18.   DOI   ScienceOn
3 이상덕(1998), "토질 역학 제 2판", 도서출판 새론, pp. 353, 354, 388-396.
4 이상덕(1999), "기초 공학", 도서출판 새론, pp. 252-254.
5 이상덕(2003), 최신터널 기술의 이해, 아주대 지반공학 연구실, pp. 1-22.