Study on mechanical behaviors of large diameter shield tunnel during assembling  

Feng, Kun (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
Peng, Zuzhao (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
Wang, Chuang (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
He, Chuan (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
Wang, Qianshen (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
Wang, Wei (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
Cao, Songyu (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
Wang, Shimin (Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University)
Zhang, Haihua (Technical Research & Development Institute, Kumagai Gumi Co., Ltd.)
Publication Information
Smart Structures and Systems / v.21, no.5, 2018 , pp. 623-635 More about this Journal
Abstract
In order to study the mechanical behavior of shield tunnel segments during assembly stage, the in-situ tests and FDM numerical simulation were conducted based on the Foguan Shiziyang Tunnel with large cross-section. Analysis for the load state of the assembling segments in different assembly steps as well as the investigation for the changing of inner forces and longitudinal stress of segments with assembling steps were carried out in this paper. By comparing the tested results with the simulated results, the conclusions and suggestions could be drawn as follows: (1) It is the most significant for the effects on axial force and bending moment caused by the assembly of adjacent segment, followed by the insertion of key segment while the effects in the other assembly steps are relative smaller. With the increasing value of axial force, the negative bending moment turns into positive and remains increasing in most monitored sections, while the bending moment of segment B1and B6 are negative and keeping increasing; (2) The closer the monitored section to the adjacent segments or the key segment, the more significant the internal forces response, and the monitored effects of key segment insertion are more obvious than that of calculation; (3) The axial forces are all in compression during assembling and the monitored values are about 1.5~1.75 times larger than the calculated values, and the monitored values of bending moment are about 2 times the numerical calculation. The bending moment is more sensitive to the segments assembly process compared with axial force, and it will result in the large bending moment of segments during assembling when the construction parameters are not suitable or the assembly error is too large. However, the internal forces in assembly stage are less than those in normal service stage; (4) The distribution of longitudinal stress has strong influence on the changing of the internal forces. The segment side surface and intrados in the middle of two adjacent jacks are the crack-sensitive positions in the early assembly stage, and subsequently segment corners far away from the jacks become the crack-sensitive parts either.
Keywords
shield tunnel; assembling segments; mechanical behavior; in-situ tests; FDM numerical simulation;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Itasca Consulting Group (2005), 'Fast Lagrangian Analysis of Continua in 3 Dimensions', Minneapolis: Itasca Consulting Group.
2 Liao, S.M., Men, Y.Q., Zhang, D., et al. (2014), "In-situ tests on mechanical behaviors during assembly of segmental linings of Qianjiang tunnel", Chinese J. Geotech. Eng., 37(1), 156-164. (in Chinese)
3 Liao, S.M., Xu, J. and Jiao Q.Z. (2013), "Mechanical behaviors of tunnel lining during segment assembly", China Civil Eng. J., 46(3), 127-135. (in Chinese)
4 Mo, H.H. and Chen, J.S. (2008), "Study on internal force and dislocation of segments caused by shield machine attitude", Tunn. Undergr. Sp. Tech., 23, 281-291.   DOI
5 Oliveira, E.R.DE, A. and Chen, Y.T. (1985), "The difference and similarity between finite element and finite difference", China Water Sci. Technol. Inform., (4), 91-98. (in Chinese)
6 Sugimoto, M. (2006), "Causes of shield segment damages during construction", International Symposium on Underground Excavation and Tunnelling. Bangkok, Thailand.
7 The Professional Standards Compilation Group of People's Republic of China, (2015), TB10003-2005 Code for Design of Concrete Structures, Beijing: China Architecture& Building Press. (in Chinese)
8 Wu, H.M., Shu, Y.M. and Zhu, J.G. (2011), "Implementation and verification of interface constitutive model in FLAC3D", Water Sci. Eng., 4(3), 305-316.   DOI
9 Wu, M.Q. (2004), "Study on the application of steel fiber reinforced concrete shield tube in Subway Tunnel Engineering", Guangdong Build. Mater., (3), 6-8. (in Chinese)
10 Xu, J. (2013), "Mechanical behaviors of tunnel linning induced by segments assembly", Shanghai: Tongji University. (in Chinese)
11 Cavalaro, S.H.P., Blom, C.B.M., Walraven, J.C., et al. (2011), "Structural analysis of contact deficiencies in segmented lining", Tunn. Undergr. Sp. Tech., 26(6), 734-749.   DOI
12 Ye X.W., Ni Y.Q., Wai T.T., et al., 2013, 'A vision-based system for dynamic displacement measurement of long-span bridges: algorithm and verification', Smart Struct. Syst., 12(3-4), 363-379.   DOI
13 Ye, X.W., Xi, P.S., Su, Y.H., et al. (2018), "Stochastic characterization of wind field characteristics of an arch bridge instrumented with structural health monitoring system", Struct. Saf., 71, 47-56.   DOI
14 Zhao W.S., Chen W.Z., Yang F. (2015), 'Study of the interface mechanical properties of concrete segments in shield tunnels', Modern Tunnel. Technol., 52(3), 119-126. (in Chinese)
15 Blom, C.B.M., Van der Horst, E.J. and Jovanovic, P.S. (1999), "Three-dimensional structural analyses of the shield-driven "Green Heart" tunnel of the high-speed line south", Tunn. Undergr. Sp. Tech., 14(2), 217-224.   DOI
16 Cavalaro, S.H.P., Blom, C.B.M., Aguado, A., et al. (2012), "New design method for the production tolerances of concrete tunnel segments", J. Perform. Constr. Fac., 26, 824-834.   DOI
17 Chen, J.S. and Mo, H.H. (2009), "Numerical study on crack problems in segments of shield tunnel using finite element method", Tunn. Undergr. Sp. Tech., 24, 91-102.   DOI
18 Chen, J.S., Mo, H.H. and Liang Z.Y. (2006), "Study on local cracking of segments in shield tunnel during construction", Chinese J. Rock Mech. Eng., (5), 906-910. (in Chinese)
19 Feng, K., He, C., Fang, Y., et al. (2013), "Study on the mechanical behavior of lining structure for underwater shield tunnel of high-speed railway", Adv. Struct. Eng., 16(8), 1381-1399.   DOI
20 Feng, K., He, C., Qiu, Y., et al. (2018), "Full-scale tests on bending behavior of segmental joints for large underwater shield tunnels", Tunn. Undergr. Sp. Tech., 75, 100-116.   DOI
21 Guo, R., He, C., Su, Z.X., et al. (2011), "Study of shearing mechanical properties of segment joints of shield tunnels", Modern Tunn. Technol., 48(4), 72-77. (in Chinese)
22 Ishimura, K., Mashimo, H. and Ishimura, T. (2003), "How to evaluate the section force at the time of assembling of the segment", Study Tunnel Eng., 13(1), 395-400.