Environmental impact assessment(EIA) on the construction and operation of thermal power plant(TPP) is aimed at promoting sustainable coastal development by clearly identifying the marine physics and organisms effects of the project on the surrounding marine environment and minimizing its impact. The primary purpose of this study is to establish EIA guidelines for TPP in order to assess how TPP construction projects influence marine environment and to establish the mitigaion plans of environmental impacts. Through this study, scientific and efficient EIA guidelines for the marine environments were established by a specialist forum consisted of officials from the Ministry of Environment and the Ministry of Trade, Industry and Energy, personnel from five public corporations in charge of TPPs and marine environment experts. In the study, fifteen EIA reports (2009~2015) on TPPs submitted were analyzed to identify the shortcomings of current assessment items on marine environment and to collect a wide range of information including EIA report formulation regulations, domestic and overseas environmental survey guidelines and EIA review comments on TPPs. Based on the findings, a specialist forum put together EIA guidelines for TPP construction projects.
Keywords
hermal power plant(TPP); Environmental impact assessment(EIA); Marine physics; Marine organisms; Guideline;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Dongbu-Power Dangjin. 2015. Dongbu green Power generation Construction project EIA.
2 Environmental Impact Assessment Support System(EIASS): http://www.eiass.go.kr/
3 EWP. 2009. Dangjin Thermal power plant 9,10 Construction project EIA.
4 Gangneungecopower. 2015. Gangneunganin Thermal power plant 1, 2 Construction project EIA.
5 General Industrial Complex Development Project EIA.
6 GS EPS. 2014. GS Dangjin Power plant 5 Construction project EIA.
7 HG-Power. 2011. HyundaiGreenPower 5,6 power plant Construction Project EIA.
8 KEI. 2002. A study on reasonable estimation and assessment method of environmental impact.
9 Kim MW, Cho KW, Maeng JH, Kang TS, Kim JK. 2014. Improvement Plan of Ocean Physics Assessment Technique for Power Plant Thermal Effluent, Journal of Ocean Engineering and Technology. 28(3): 245-253. [Korean Literature]   DOI
10 KOEN. 2011. Yeosu Thermal power plant 1 Construction project EIA.
11 KOSPO. 2010. Samcheok comprehensive power generation
12 KOSPO. 2015. Yeungnam Combined Cycle power plant Construction project EIA.
13 KOWEPO. 2010. Taean IGCC Power plant Construction project EIA.
14 KOWEPO. 2012. Taean Thermal power plant 9, 10 Construction project EIA.
15 Maeng JH, Kim TY, Suh DH. 2014. Minimizing Environmental Impact in Accordance with the Thermal Power Plant Ash Management (I). Korea Environment Institute. 24(5): 472-486. [Korean Literature]
16 Meiya Power Company. 2012. MPC Yulchon LNG Combined Cycle power plan(2) EIA.
17 Ministry of Trade, Industry & Energy. 2015. 2014 Yearbook of Energy Statistics.
18 SKEC. 2015. Goseong high Thermal power project EIA.
19 Ministry of Trade, Industry & Energy. 2015. the 7th Basic Plan for Long-term Electricity Supply and Demand.
20 POSCO Energy. 2011. POSCOPower LNG Combined Cycle power plant 1, 2 Construction project EIA
21 STX Corporation. 2012. Bukpyeong Thermal power plant Construction project EIA.
22 KOWEPO. 2012. Pyeongtaek Combined Cycle power plant Phase 2 Construction project EIA.