An Evaluation of Operator's Action Time for Core Cooling Recovery Operation in Nuclear Power Plant  

Bae, Yeon-Kyoung (Central Research Institute of Korea Hydro & Nuclear Power Co.)
Publication Information
Journal of the Korean Society of Safety / v.27, no.5, 2012 , pp. 229-234 More about this Journal
Abstract
Operator's action time is evaluated from MAAP4 analysis used in conventional probabilistic safety assessment(PSA) of a nuclear power plant. MAAP4 code which was developed for severe accident analysis is too conservative to perform a realistic PSA. A best-estimate code such as RELAP5/MOD3, MARS has been used to reduce the conservatism of thermal hydraulic analysis. In this study, operator's action time of core cooling recovery operation is evaluated by using the MARS code, which its Fussell-Vessely(F-V) value was evaluated as highly important in a small break loss of coolant(SBLOCA) event and loss of component cooling water(LOCCW) event in previous PSA. The main conclusions were elicited : (1) MARS analysis provides larger time window for operator's action time than MAAP4 analysis and gives the more realistic time window in PSA (2) Sufficient operator's action time can reduce human error probability and core damage frequency in PSA.
Keywords
PSA; success criteria; MARS; MAAP4; operator's action time;
Citations & Related Records
연도 인용수 순위
  • Reference
1 KHNP, "Probabilistic Safety Assessment for Kori Unit 3&4", 2008.
2 U.S. EPR, "FSAR Tier 2 Section 19.1", Rev.0 pp.16
3 KHNP, "Human Relaiability Analysis Report for Kori Unit 3&4", 2008.
4 KHNP, "Success Criteria Analysis Report for Kori Unit 3&4", 2008.
5 NEI 00-02, "Probabilistic Risk Assessment Peer Review Process Guidance Rev. A3", March, 2000.
6 F. Rahn, "MAAP4 Application Guidance", EPRI, 2008.
7 ASME, ASME/ANS RA-Sa-2009, "Addenda to ASME/ANS RA-S-2008 Standard for Level I/ Large Early Release Frequency Probabilitsitc Risk Assessment for Nuclear Power Plant", 2009.
8 Han S.J., Lim H.G., Yang J.E., "An Estimation of an Operator's Action Time by using the MARS code in a Small Break LOCA without a HPSI for a PWR", Nucl. Eng. and Design, Vol. 237 pp. 750, 2007.
9 KHNP, "Emergency Operating Procedure ER-C.1 Response to Degraded Core Cooling", Rev. 6. Nov. 21, 2006.
10 Westinghouse Electric Company, "WOG 2000 Reactor Coolant Pump Seal Leakage Model for Westinghouse PWRs", WCAP-15603, Rev. 1, 2002.
11 KHNP, "Emergency Operating Procedure Supplement-1.3 Switch to Cold Leg Recirculation", Rev. No. 21, 2006.
12 Jung. W.D., Kang D.I., Kim J.H., "Development of a Standard Method for Human Reliability Analysis (HRA) of Nuclear Power Plants-Level 1 PSA Full Power Internal HRA", KAERI/TR-2961 /2005, 2005.
13 KHNP, "Emergency Operating Procedure ER-C.2 Response to Inadequate Core Cooling", Rev. 6. Nov. 21, 2006.