The Application Plan for Value Engineering Redesign by Using The Simulation for The Port Facilities Construction Project  

Yoon, Moo-Hee (Head of SOC bussiness. amco)
Ahn, Kyung-Soo (School of Civil and environment system Engineering, University of Incheon)
Publication Information
Journal of Korean Society of Coastal and Ocean Engineers / v.19, no.6, 2007 , pp. 533-546 More about this Journal
Abstract
This paper studied the design VE (Value Engineering) process among the various methods to satisfy the requirement of user and cost saving in the overall redesign process for the Turn-key base construction project. This study has been estabilished the rational and practical analysis process with the stepwise by using the design VE process. The efficiency and safety were verified with the adoptian of computer simulation to cope with the problem of initial analysis and verification for design VE process in the large construction project. In the previous design VE process, there is a limitation for the analysis of design VE in the planing stage and the execution time period of the large construction project. The previous application of VE technique was only for the construction of harbor facilities, so there was no contribution of cost saving in the function and construction. However, this paper proposed the selection methodology of VE items and hence the redesign VE process can be efficiently improved. It can be also improved the process of functional analysis rationally and practically. About 4.6 billion won has been saved with applying to the harbor construction project with using the VE method proposed in this paper. The study gives the direction of VE to be accomplished efficiently in the similar project.
Keywords
value engineering(VE); computer simulation; efficiency; safety; harbor construction project;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 건설교통부 http://www.moct.go.kr
2 한충희 (1999). 건설관리 및 경영(제1편). 보성각. 483-509
3 현창택 (1999). 건설관리 및 경영(제1편). 보성각. 211-213
4 Alphonse Dell'isola (1997). Value Engineering, R. S. Means Company Inc. 56
5 건설교통부 http://www.moct.go.kr
6 삼안코퍼레이션(주) (2001). 인천항 갑문문짝(10KT) 증설공 사 설계변경 용역보고서
7 이승훈, 구교진, 현창택 (2005). 건설사업 설계초기단계 VE 적용방안. 한국건설관리학회 논문집, 156-166   과학기술학회마을
8 인천항건설사무소 (1999). 인천항 갑문문짝(10KT) 증설공사 실시설계보고서
9 김종훈, 정의균, 이도형, 한미건설기술(주) (2005). 신항만 VE 추진사례. 한국건설관리학회지. 건설관리기술동향
10 한국해양수산연구원 (2000). 인천항 갑문문짝(1만톤)증설공 사 관련 선박조종 시뮬레이션 용역 보고서. 1-107
11 장인규 (2002). 건축설비 계획시 VE 기법 적용에 관한 연구. 석사학위논문, 서울대학교
12 강대준 (1998). 설계단계에서 가치공학기법을 적용한 프로 세스 모델에 관한 연구. 석사학위논문, 성균관대학교