Abstract
The subsea pipeline pre-commissioning stage consists of the following processes: Flooding, Venting, Hydrotesting, Dewatering, Drying, and N2 Purging. Among these processes, drying and nitrogen purging processes are stipulated to reduce and maintain the relative humidity below dew point to prevent the generation of hydrate and the risk of gas explosion in the pipeline during operation. The purpose of this study is to develop an analysis method for the air drying and nitrogen purging process during pre-commissioning of the subsea pipeline, and to evaluate the applicability of the analysis method through comparison with on-site measurement results. An analysis method using Computational Fluid Dynamics (CFD) was introduced and applied as a method for evaluating the relative humidity inside a subsea pipeline, and it was confirmed that analysis results were in good agreement with the on-site measurement results for the air drying and nitrogen purging process of the offshore pipeline. If the developed air drying and nitrogen purging analysis method are used as pre-engineering tools for pre-commissioning of subsea pipelines in the future, it is expected to have a significant impact on the improvement of work productivity.
Keywords
Subsea pipeline; Pre-commissioning; Air drying; Nitrogen purging; Relative humidity; Dew point;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Cho, C. H. and M. K. Park(1997), [Feature: Drying Technology] Air drying with PSA. Chemical Industry and Technology, Vol. 15, No. 5, pp. 417-423.
2 Chung, H.(2001), Brief Introduction to the Design and Construction Method of Submarine Pipeline. Journal of the Korean Professional Engineers Association, Vol 34, No.6, pp. 55-59.
3 Hong, S. Y., W. J. Gang, Y. J. Kim, J. U. Kim, G. P. Jang, T. H. Kim, and Y. H. Choe(2010), Offshore Energy/Resources Plant Source Technology Securing Strategy. Bulletin of the Society of Naval Architects of Korea, Vol. 47, No. 2, pp. 26-35.
4 Huh, C., S. G. Kang, S. Hong, J. S. Choi, and J. H. Baek(2008), Thermal-Hydraulic Analysis of Pipeline Transport System for Marine Geological Storage of Carbon Dioxide, Journal of Ocean Engineering and Technology, Vol. 22, No. 6, pp. 88-94.
5 Kim, Y. P.(2014), Subsea Pipeline Design and Construction Technology Trend, Journal of KSME, Vol. 54, No. 1, pp. 48-52.
6 Kim, Y. T.(2016), Introduction of the design of the subsea pipeline. Magazine of the Korean Society of Steel Construction, Vol. 28, No. 2, pp. 32-37.
7 Palmer, A. C.(2008), Subsea pipeline engineering, pp. 298-300.
8 Bai, Y. and Q. Bai(2005), Subsea Pipelines and Risers, Elsevier, pp. 11-21.
9 Barletta, A., S. Lazzari, E. Zanchini, and A. Terenzi(2008), Transient Heat Transfer from an Offshore Buried Pipeline during Start-up Working Conditions, International Journal of Heat Transfer Engineering, Vol. 29, No. 11, pp. 942-949.   DOI
10 Barrera Escobedo, J. J., A. O. Nieckele, and L. F. A. Azevedo(2006), Analysis of the Transient Cooldown of Sub-Sea Pipelines. In International Pipeline Conference, Vol. 42614, pp. 845-853.
11 DNV-GL(2016), DNVGL-RP-F115: Pre-commissioning of Submarine Pipelines, DNV-GL AS.
12 Yang, S. H., Jung, J. J., Kim, Y. H., Lee, W. S., and Kim, J. B.(2010), Global Buckling Assessment of High Pressure and High Temperature (HP/HT) Offshore Pipeline, 8th International Pipeline Conference, Calgary, Alberta, Canada, American Society of Mechanical Engineers, Vol. 3, pp. 657-663.
13 Shin, K. H, Y. S. Jang, S. Y. Kim, and P. S. Jung(1998), The Characteristics of the Hot Air Drying of Sizing Yarn with Heat and Mass Transfer. The Society of Air-Conditioning and Refregerating Engineers of Korea, pp. 27-32.
14 Son, S. H., J. B. Park, and J. H. Lee(2015), Experimental Investigation of Flow Assurance due to Heating Method in Offshore Pipeline, Vol. 3, No.1, pp. 45-53.   DOI
15 Yang, S. H.(2019), Effects of Ambient Temperature Change on the Internal Pressure Change of Multi-Layered Subsea Pipeline, Journal of the Korean Society of Marine Environment and Safety, Vol. 25, No. 6, pp. 772-779.   DOI
16 Sensirion(2006), Application Note Dew Point Calculation, Retrieved from https://www.sensirion.com/.
17 ANSYS(2013a), ANSYS Fluent Theory Guide.
18 ANSYS(2013b), ANSYS Fluent User Guide.