A Comparison of Operation Time between the Standard of Estimate and Actual Operations in Tunnel Blasting  

Kim, Yang-Kyun (세종대학교 에너지자원공학과)
Kim, Hyung-Mok (세종대학교 에너지자원공학과)
Publication Information
Explosives and Blasting / v.33, no.3, 2015 , pp. 14-20 More about this Journal
Abstract
Tunnel blasting that plays the most important role in the construction of a drill & blast tunnel, shows a big difference in operation time according to various factors such as rock mass quality, tunnel dimension, machine performance, and the skill level of tunnel crews. This paper analyzes the differences between the time calculated by the standard of estimate and actual operation time based upon field investigations on blasting operation time in three tunnels of Korea. The result shows that actual blasting time is generally about 8%~16% less than the standard of estimate in cases that normal operations are performed. If the time delayed by unforeseen situations is included, however, it is presumed that the number of cases that actual operation time exceeds the standard of estimate are considerable. This study aims to help make a judgement over the appropriacy of the standard of estimate through continuous investigations on actual operation time, as well as improve the productivity of tunnel excavation.
Keywords
Tunnel blasting; Blasting operation time; Cycle time; Standard of estimate;
Citations & Related Records
연도 인용수 순위
  • Reference
1 국토교통부, 2014, 건설공사 표준품셈, pp. 448-451.
2 이효, 윤영재, 1998, 건설현장에서 적용되고 있는 암발파 방법 및 일위대가에 대한 고찰, 터널과 지하공간, Vol. 8, pp. 171-177.
3 Kim, Y., Bruland, A., 2015, Comparison of tunnel excavation cycle time for Norwegian and Korean tunnels, ITA WTC 2015, May 22-28, Dubrovnik, Croatia, 9-16.