A Case Study on the Construction of Concrete Structures in Parallel with Tunnel Blasting  

류창하 (한국지질자원연구원)
최병희 (한국지질자원연구원)
김양균 (코오롱건설 주식회사)
유정훈 (코오롱건설 주식회사)
Publication Information
Explosives and Blasting / v.21, no.4, 2003 , pp. 11-21 More about this Journal
Abstract
An experimental study was carried out in order to reduce the period and cost of construction of Missiryung tunnel, which is a relatively long one 3.6 km long. An allowable vibration level for curing concrete was established based on the extensive case studies done over the world. and assessment was performed on the possibility of constructing concrete structures like lining during tunnel blasting. Attenuation relationships were obtained by processing more than 130 measurement data from a series of tunnel blasting in the site. A Guideline for safe construction work was suggested. To verification, low small concrete blocks with a constant standoff distance were installed in the floor of the tunnel After the blocks were exposed to blast vibrations for 28 days, compressive strength tests were performed on 20 specimens taken from the blocks. It was shown that the suggested guideline was appropriate for the safe construction work at the site.
Keywords
tunnel blasting curing concrete; parallel construction; vibration effect; safe distance;
Citations & Related Records
연도 인용수 순위
  • Reference