A Study on the Noise and Vibration Characteristics during Construction of Screw Concrete Pile for Reduction of Noise and Vibration  

Kim, Dongchul (Dept. of Civil Engineering, Kyungsung University)
Choi, Yongkyu (Dept. of Civil Engineering, Kyungsung University)
Publication Information
Journal of the Korean GEO-environmental Society / v.14, no.9, 2013 , pp. 21-30 More about this Journal
Abstract
Because the noise and vibration regulations in domestic areas are being tightened more and more, a more environmentfriendly method than the current low-noise & low-vibration methods is needed. In this study, the characteristics of screw concrete piles for reduction of noise and vibration were explained, and during pilot tests the noise and vibration were measured. The measured vibration value is satisfied with the vibration regulations at 7.5m distance from the source. The measured noise value is exceeded over about 2dB(A) at the 15.0m distance from the source but these values are about 5~20dB(A) less than the measured values of the current low-noise & low-vibration method.
Keywords
The noise and vibration regulations; Low-noise & low-vibration method; Reduction of noise & vibration; A screw concrete pile method;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Kim, T. H.(2010), Measurement report of screw PHC pile construction noise and vibration, Department of Environmental Engineering Changwon National University, pp. 14-21 (in Korean).
2 Choi, Y., Kim, D. C., Kim, S. S. and Nam, M. S.(2009), Development and test construction plan of a noise & vibration - free PHC screw pile, 2009 Workshop of Korea Geotechnical Society of Foundation Technical Committee, KGS, pp. 18-33 (in Korean).
3 Kim, D. C.(2011), A study on the construction method and behavior of axial resistances of noise and vibration free screw concrete piles method, Ph D. Dissertation, Kyungsung University, pp. 56-82 (in Korean).
4 Kim, D. C. and Choi, Y.(2013), An analysis on the vertical load bearing behavior according to construction methods of a environment-friendly screw concrete pile for the noise and vibration-free method, Journal of Korean Geotecnincal Engineering Soiciety, Vol. 14, No. 6, pp. 5-11 (in Korean).
5 KSA(2006), Pretensioned spun concrete piles, KS F 4303, pp. 2-4 (in Korean).
6 KSA(2008), Pretensioned spun high strength concrete piles, KS F 4306, pp. 7-8 (in Korean).
7 Ministry of Environmental(2006), Guidance of noise & vibration control under construction, Ministry of Environment, pp. 14-68 (in Korean).
8 National Environmental Dispute Resolution Commission(2009), Environmental dispute resolution statistics as of the end of December 2009, (in Korean).
9 Sun, H. S., Park, Y. M. and Jo, Y. H.(2008), Investigation study on noise and vibration condition in construction site, Proceedings of the Korean Society for Noise and Vibration Engineering Conference, pp. 1-3 (in Korean).