Integrated Management of Process Schedule and Quantity Take-Off for Steel Structures using BIM Information  

Kim, Jin-Uk ((주)빔파트너스)
Shin, Tae-Song (동명대학교 건축공학과)
Publication Information
Journal of KIBIM / v.8, no.2, 2018 , pp. 10-18 More about this Journal
Abstract
BIM technologies store, share and integrate the information produced in each sector of the construction industry. From this point on, it increases the efficiency of the work. Currently, quantity take-off and process schedule are derived separately based on BIM technology. When calculating the quantity by process, relevant information shall be collected, reinterpreted, and reevaluated as required by the practice. The purpose of this study is to develop an integrated process and quantity management system through BIM collaboration and to build prototypes for steel structures. The main research is to build a construction BIM model for steel structures and a process BIM model through BIM collaboration. Furthermore, necessary information was selected and processed according to the user's needs for integrated management. Relevant integration outcomes are visualized graphically to maximize utilization. Through these studies, a system for integrated control of processes and supplies is provided, and the results are expected to contribute to the improvement of working efficiency and are easily and quickly reflected in design change and process change. In this study, we intended to enhance the usability of information by linking process schedules with quantity calculations based on BIM. Thus, the process for integrated control of the quantity of structural components by process unit and the BIM based schedule information was established. In addition, the efficiency of the information link of the integrated management system was considered for design changes and process schedule changes.
Keywords
BIM; quantity take-off; process schedule; integrated management; steel structures;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Brad Hardin (2009). BIM and Construction Management: Proven Tools, Methods, and Workflows, Sybex.
2 Eom, B. H., Kim, Y. H., Lee, Y. C., Min, D. S., R, J. H. (2017). Proposal of Material Takeoff Method Using the Object Concept of general 3D Modeling Tool, KIBIM annual conference, pp. 71-72.
3 Eom, J. U. (2010). A Study on the Automation System of Structural Detail Design and Modeling Process based on BIM for Steel Structures, Master thesis, The graduate school, Tongmyong University.
4 Jo, D. G., (2015). Hidden Values in BIM, Korean Journal of Construction Engineering and Management, Vol.16 No.5.
5 Kim, J. U. (2016). A Study on the Quantity Take-Off the Structural Members related to the Schedule by utilizing OpenBIM, Master thesis, The graduate school, Tongmyong University.
6 Kim, J. U., Shin, T. S. (2015). Feasibility of application of OpenBIM between structural analysis and architectural design, KIBIM annual conference, Vol.5, No.1.
7 Kim, J. U., Shin, T. S. (2015). Process planning and quantity take-off related to the schedule by utilizing the Open BIM, Proceedings of the 2015 Annual Conference of the Busan- Ulsan- Gyeongnam Chapter of Architecture Institute of Korea.
8 Lee, J. G., Lee, H. S., Park, M., Jung, M. (2013). A Framework Integrating Cost and Schedule based on BIM using IFC, Korean Journal of Construction Engineering and Management, Vol. 14 No. 3.
9 Lee, J. H. (2017). BIM based Reinforced Concrete Work Quanti ty and Cost Est imate Method, KIBIM annual conference, pp. 69-70.
10 Lee, K. (2010). Social network analysis of BIM collaboration, Master thesis, The graduate school, Yonsei University.
11 Moon, Y. N., Kwon, B. R. (2017). Schedule(4D) and Cost(5D) implementation using BIM integrated data, KIBIM annual conference, pp. 59-60.
12 Navisworks, http://www.autodesk.co.kr/Products/navisworks/overview, 2017.12.28.
13 Tekla Structures, http://www.tekla.com/, 2017.12.28.