A Study on the Current Status and Improvement of BIM in the Government Owner Perspective - Focus on the KEPCO Na-Ju Head Office Project -  

Sim, Gu-Sik (한국전력공사 자산개발처)
Kim, Sung-Man (한국전력공사 자산개발처)
Ahn, Jae-Hong ((주)유미드 시스템 기술연구소)
Publication Information
Journal of KIBIM / v.3, no.2, 2013 , pp. 19-27 More about this Journal
Abstract
The application of the BIM for the KEPCO' new headquarters in Naju involved alternative approaches and accompanied many trials-and-errors as the project adopted new targets and purposes that were not used in Korea before. In particular, for a large BIM-based project, clearly defining the BIM-including the objective, scope and the outcome-is critical for a project owner. For a successful implementation, project owners should improve the utilization of the BIM. Against this background, this research examines the case of the BIM application for the KEPCO' new headquarters in Naju, identifies its effects and problems, and proposes how to improve application of the BIM for public projects. The improvement in the BIM application can be divided into several stages: project order, design development, construction, and post-construction maintenance. In the initial stage, it is important to fully discuss the project planning among participants, and clarify the goal, scope, expected outcomes and role of the BIM. In the design stage, the level of detail (LOD) for the 3D model should be defined in consideration of information use in the stages of estimation and construction. In the construction stage, the scope of project that is managed based on the processing and use of the BIM data should be clearly given and understood. After construction is complete, measures should be sought to use the BIM for maintenance, and corresponding requirements and outcomes should be provided. The analysis is expected to provide basic data for successful implementation of BIM-based public projects, by assisting project owners and involved parties in enhancing work in different stages of a project.
Keywords
Government owner perspective; Building Information Modeling(BIM); 4D & 5D; Cost & Schedule integrated management;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Ahn, Jaehong (2012), "A Study on the Plan Construction Management Using BIM", Journal of the Korea Institute of Building Construction, 5(55), pp. 97-99.
2 Kim, Kyonghoon (2009), "A Study to Judge the Importance to Estimate Architectural Competition on the Apartment for Using BIM", Journal of the Architectural Institute of Korea, 25(2), pp. 59-66.   과학기술학회마을
3 Min, Byoungjik (2012), "A Study on the Evaluation Management of Public Housing Architectural Competition using BIM", Journal of Korea Institute of Building Information Modeling, 2(2), pp. 1-9.   과학기술학회마을
4 Seo, Jongchul and Kim, Inhan (2009), "A Study on the Basic Directions for Introducing and Applying Building Information modeling in thr Public Construction Project Delivery", Journal of the Architectural Institute of Korea, 25(9), pp. 21-30.