An Analysis of Effect and Limitation when Adapting Earned Schedule Method for Schedule Management and Estimation in Korean Defense Research & Development Projects  

Cho, Jungho (R&D Programming Directorate, Agency for Defense Development)
Lim, Jaesung (Department of NCW Engineering, Graduate School, Ajou University)
Publication Information
Journal of the Korea Institute of Military Science and Technology / v.21, no.3, 2018 , pp. 396-402 More about this Journal
Abstract
Earned Value Management(EVM) has been used to manage and forecast defense project schedule and cost over the last two decades in the world. However to support the lacking ability of schedule analysis in traditional EVM, earned schedule(ES) has been introduced as a tool to more accurately estimate schedule performance. This paper compares which method EVM or ES, provides more accurate schedule predictors in 32 Korean defense research and development projects. As a result of comparison, the ES method can predict the future schedule more reliably than the EVM method. We also analyze early warning function of schedule performance index considering project duration extension point. Through the analysis results, we confirm that both the EVM and the ES method lack the ability of the early warning in terms of the current schedule management criterion.
Keywords
Earned Value Management; Earned Schedule; Schedule Performance Index; Schedule Estimate at Completion;
Citations & Related Records
연도 인용수 순위
  • Reference
1 "A Guide to the Project Management Body of Knowledge(PMBOK$^{(R)}$ Guide) - 5th edition," Project Management Institute Inc. USA, 2013.
2 Q. W. Fleming and J. M. Koppelman, "Earned Value Project Management - 3rd edition," Project Management Institute Inc. USA, 2005.
3 "Scientific Project Management Execution Guidance," Regulation No. 367, Defense Acquisition Program Administration, Korea, March, 2017.
4 Walt Lipke, "Schedule is different," The Measurable News, pp. 31-34, Summer, 2003.
5 Jordy Batselier and Mario Vanhoucke, “Empirical Evaluation of Earned Value Management Forecasting Accuracy for Time and Cost,” Journal of Construction Engineering and Management, Vol. 141, No. 11, pp. 05015010, 2015.   DOI
6 William J. Bruchey, "A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs," Master thesis, Naval Postgraduate School, September, 2012.
7 K. T. Crumrine and J. D. Ritschel, "A Comparison of Earned Value Management and Earned Schedule as Schedule Predictors on DoD ACAT I Programs," The Measurable News, pp. 37-44, February, 2013.
8 Chan Yang, "Comparison Research of Schedule Management between EVM and Earned Schedule," Defense & Technology, The Korea Defense Industry Association, Vol. 464, pp. 156-163, October, 2017.
9 Jeong Gu Lee, "Project Management at 21st Century," Booknamu, Inc. Korea, 2013.