Extension plate attached PHC piles and bolts spliced PHC piles were installed in field test site. Pile integrities were checked during installation with dynamic pile test and the actual pile conditions after installation were compared with integrity index (${\beta}$ index) by PDA test. Theoretically the break in near pile end or pile end (especially extension plate itself) was very difficult to access by integrity index (${\beta}$ index) and also require a high level of knowledge and field experience on PDA test. First actual wave equation of bolts spliced PHC piles due to bolts spliced equipment can be different with welding spliced. Second wave length of the stress wave from installing can be longer than the height of bolts spliced equipment (about 100 mm). Third Beta processing in PDA analysis function is very difficult to access without a high level of knowledge and field experience on wave equation. Above-mentioned three reasons can make conclusion that traditional PDA test in domestic site can not access the integrity of bolts spliced equipment in bolts spliced PHC piles.
Keywords
Extension plate attached PHC pile; Bolts spliced PHC pile; Pile integrity during installation; Dynamic pile load test; Integrity index (${\beta}$ Index); Wave equation; Access pile integrity; Bolts spliced equipment;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Likins, G. and Rausche, F. (2014), Pile Damage Prevention and Assessment Using Dynamic Monitoring and the Beta Method, Soil Behavior Fundamentals to Innovations in Geotechnical Engineering, ASCE Geo-Institute Geotechnical Special Publication No.233, pp. 428-442.
2 Pile Test Corp. (2018), Dynamic pile load test report for second open PHC pile field test to check pile performance, Report No. KJ1805R01, 2018. 8, pp.1-32. (In Korean)
3 Choi, Y. and Kim, M. H. (2018), Axial bearing characteristics of tip-transformed PHC piles through field tests, Journal of KGS, Vol.34, No.11, Nov. 2018, pp.107-119. (In Korean)
4 Kim, M. H. (2018a), Safe installation method development project for extension plate attached PHC piles and bolt spliced PHC piles(Final report), Inje University industry academic cooperation foundation, pp.1-341. (In Korean)
5 Kim, M. H. (2018b), Safe installation method deveropement project for extension plate attached PHC piles and bolt spliced PHC piles (Final report) - supplement, Inje University industry academic cooperation foundation, pp.A-1-1-A-13-48. (In Korean)
6 Kim, M. H. and Choi, Y. (2018), Comparison of splices between bolts and welding spliced PHC piles, Journal of KGS, Vol.34, No.12, Nov. 2018. (In Korean) (in process)