Comparative Analysis of Conventional Tact and Compositive Tact in Apartment House Finishing Construction  

Hwang, SuHyeon (Department of Architectural Engineering, Hanyang University)
Sim, JeaHyung (Department of Architectural Engineering, Hanyang University)
Ham, NamHyuk (Department of Digital Architectural and Urban Engineering, Hanyang Cyber University)
Kim, JaeJun (Department of Architectural Engineering, Hanyang University)
Publication Information
Korean Journal of Construction Engineering and Management / v.23, no.4, 2022 , pp. 47-56 More about this Journal
Abstract
In a construction project, process planning is an important factor in determining the success or failure of a project. In particular, it is necessary to systematically establish a process plan in the early stage because the finishing work of an apartment house involves more interference than the foundation work or the frame work. First, in this study the problems of Tact process management were identified, Based on the data from the case project, conventional Tact process management and compositive Tact process management were compared and analyzed. Second, cost analysis was performed on applicable plastering work to suggest the necessity and direction of compositive Tact process management. Third, the appropriateness of manpower according to the number of construction households is analyzed through cost analysis. Through this, the validity and effectiveness of compositive Tact process management were verified based on the results derived from this study.
Keywords
Tact; Tact Process Management; Apartment House; Finish Work; Plaster Work;
Citations & Related Records
Times Cited By KSCI : 5  (Citation Analysis)
연도 인용수 순위
1 Yoon, Y.S., and Suh, S.W. (2003). "A Study on the Application of Tact Planning & Scheduling in Finish Work of Apartment Houses." Journal of the Korea Institute of Construction Engineering and Management Conference, pp. 422-425.
2 Keskiniva, K., Saari, A., and Junnonen, J.M. (2020). "Takt planning in apartment building renovation projects. Buildings." Journal of the Buildings, 10(12), p. 226.   DOI
3 Kim, B.S. (2012). "Tact Process Reengineering for Improving the Usability in Construction Sites." MS Thesis, Chungbuk University.
4 Kim, S.K., Son, K.Y., Joo, J.K., Lee, D.H., and Lee, S.H. (2011). "An Enhanced TACT Technique for Finish Work of High-rise Residential Buildings." Journal of the Korea Institute of Building Construction, 11(4), pp. 396-406.   DOI
5 Kim, S.H., Yeom, D.J., Shin, N.R., Seo, H.M., and Kim, Y.S. (2016). "A Non-working Period Estimation Model Reflecting the Characteristics of the Construction Trades." Journal of the Architectural Institute of Korea Structure & Construction, 32(2), pp. 41-50.   DOI
6 Kim, S.T. (2012). "Current Status of Using D-Tact." Journal of the Korea Institute of Construction Engineering and Management, 13(5), pp. 40-44.
7 Lee, J.S. (2001). "Analyzing Method of Schedule Delay Using Bar Chart in Construction." Journal of the Architectural Institute of Korea Structure & Construction, 17(1), pp. 121-128.
8 Kim, J.H., Yoon, Y.S., Jang, M.H., and Suh, S.W. (2007). "Work flow-based Tact Planning & Scheduling Process: Focused on the Finish Work of Apartment Building." Journal of the Architectural Institute of Korea Structure & Construction, 23(6), pp. 153-162.
9 Baek, T.Y. (2017). "Process Planning for Finishing Works of High-rise Residential Buildings Project." Journal of the Korea Academia-Industrialcooperation Society, 18(11), pp. 110-117.
10 Byun, H.B. (2015). "Deriving Problems of a Domestic Schedule Management and Solution by BDM Technique." MS Thesis, Kangwon National University.
11 Jeon, M.C., Woo, J.J.O., Yoon, D.E., and Kim, D.Y. (2015). "A Study on the Main Factors for Improving Tact Process Management." Journal of the Korean Society of Civil Engineers, pp. 27-28.   DOI
12 Joo, S.U., Park, M,S., Lee, H.S., and Lee, K.P. (2015). "Tact Productivity Management for Finish Works of Residential Buildings using Productivity Achievement Ratio (PAR)." Journal of Construction Engineering and Management, 16(3), pp. 36-48.
13 Park, Y.N., Lee, D.D., and Kim, J.J. (2019). "A Study on the Task Variation and Social Network Analysis in the Construction Process." Journal of the Korea Institute of Construction Engineering and Management, 20(1), pp. 105-113.
14 Hwang, J.W. (2009). "Business Process Model for Applying Tact Methodology to Finish Work in Apartment House." MS Thesis, Soonsil University.
15 Lee, S.R., Lee, H.S., Park, M.S., and Roh, S. (2007). "A Study on Ideal Scheduling Method for High-rise Building Finishing Work." Journal of the Architectural Institute of Korea Structure & Construction, 27(1), pp. 793-796.
16 Lee, W.S. (2011). "The Application of the Tact Method for Finish Works of Apartment Buildings." MS Thesis, Kyung Hee University.
17 Sim, J.H. (2017). "Reengineering of Tact Process Management for Finishing Work in Apartment Construction Project." MS Thesis, Hanyang University.
18 Jeon, M.C., and Kim, D.Y. (2016). "Improving the process of finishing work according to the size of construction companies." Journal of the Korean housing association, 14(1), pp. 195-204.
19 Vatne, M.E., and Drevland, F. (2016). "Practical Benefits of Using Takt time planning: A case study." In Proceedings of the 24th Annual Conference of the International Group for Lean Construction (IGLC 24), Boston, MA, USA, (173), pp. 173-182.
20 Lee, J. (2001). "A Work Interference Management Model for Apartment Building Finish Works." MS Thesis, Chung-Ang University.
21 Lee, S.H., Lee, S.H., Kim, J.H., and Kim, J.J. (2010). "Delay Factors Based on the Importance of Finish Work in Apartment Construction Project." Journal of the Proceedings of the Korean Institute of Building Construction Conference, pp. 125-129.
22 Lee, S.H., Kim, Y.M., Kim, J.H., and Kim, J.J. (2011). "Analysis of Delay Factors Based on Importance of Construction Subject-classified in Apartment Finishing Works." Journal of the Korea Institute of Building Construction, 11(1), pp. 73-81.   DOI
23 Kim, S.G., Byun, H.B., Kim, J.H., and Jung, W. (2014). "Integration of LOB and Tact Techniques by BDM Technique." Journal of the Architectural Institute of Korea Structure & Construction, 30(9), pp. 61-68.   DOI
24 Shin, D.H., Park, H.S., Yun, S.H., and Koo, K.J. (2010). "Application plan of Tact process for finish works in apartment housing projects." Journal of Architectural Institute of Korea, 26(1), pp. 129-136.