A Study on the Perceptions and Current Practices in Estimating Risk Cost of Contractor's Construction Budget - Focused on Building Projects -  

Choi, Jeong Won (Department of Architecture, Sejong University)
Kim, Han Soo (Department of Architecture, Sejong University)
Publication Information
Korean Journal of Construction Engineering and Management / v.23, no.3, 2022 , pp. 13-24 More about this Journal
Abstract
Construction projects are exposed to various types of risks, which tend to increase. The increasing risks call for contractors' more attentions to forecasting and dealing with these risks. One of the measures to deal with contractors' risks is to forecast or estimate risk cost and include it in the construction budget. Although various researches in relation to risk cost have been observed, little attention has been paid to general contractors' perceptions and current practices in estimating risk cost of construction budget. The objective of the study is to identify and discuss key characteristics and implications based on the survey and analysis of general contractors' perceptions and current practices in estimating risk cost of construction budget. The study shows that there is a gap between the perception and the practice of estimating risk cost, that is, high perception of the importance of risk cost and a relatively low level of practice. It suggests that historical cost data, guidelines and corporate-level standard procedures are required to improve the current practice in addition to sufficient time allocations for risk cost estimating. It discusses that there is a need for using sophisticated estimating techniques including bid data analytics despite a low level of the current adoption, and also proposes that research and development in the field of the sophisticated estimating techniques should be further implemented in order to increase their practicality.
Keywords
Risk Cost; Estimating; Contractor's Construction Budget; General Contractors' Perception and Practice; Big Data;
Citations & Related Records
Times Cited By KSCI : 8  (Citation Analysis)
연도 인용수 순위
1 Hamid, R.A., and Kehinde F.J. (2017). "Choosing an appropriate contingency sum estimating methods for highway construction projects in nigeria: a literature review." The Journal of the Malaysia Institute of Planners, PLANNING MALAYSIA, 15(1), pp. 13-21.
2 Ebrat, M., and Ghodsi, R. (2014). "Construction project risk assessment by using adaptive-network-based fuzzy inference system: An empirical study." KSCE Journal of Civil Engineering, KSCE, 18(5), pp. 1213-1227.   DOI
3 El-Kholy, A.M., Tahwia, A.M., and Elsayed, M.M. (2020). "Prediction of simulated cost contingency for steel reinforcement in building projects: ANN versus regression-based models." International Journal of Construction Management, pp. 1-15.
4 Jung, Y.S., and Joo, M.H. (2011). "Patterns and Trends in Cost Control Practive of Korean General Contractors." Korean Journal of Construction Engineering and Management, KICEM, 12(4), pp. 79-87.   DOI
5 Kang, H.W., Kim J.W., and Kim, Y.S. (2018). "Risk Assessment and Contingency Prediction considering Work Characteristics for Modular Plant Construction Projects." Korean Journal of Construction Engineering and Management, KICEM, 19(5), pp. 81-89.   DOI
6 Karunarathne, B.V.G., and Kim, B.S. (2018). "A Study on the Allocation and Prediction of Contingency Reserves Using Monte Carlo Simulation." Proceedings of the National University Student Conference, KICEM, pp. 106-107.
7 An, S.H., and Lee, W.H. (2012). "Case-based Reasoning Model for Building Construction Cost Management by using Risk Analysis." Journal of Korean Society of Industrial and Systems Engineering, KSISE, 28(10), pp. 157-164.
8 An, S.H., Suk, S.J., and Lee, M.H. (2011). "Weighting of Key Factors Influencing the Cost Budgeting in Building Construction Projects." Journal of Korean Society of Industrial and Systems Engineering, KSISE, 27(5), pp. 119-126.
9 Diab, M.F., Varma, A., and Panthi, K. (2017). "Modeling the construction risk ratings to estimate the contingency in highway projects." Journal of Construction Engineering and Management, ASCE, 143(8), pp. 04017041-1-04017041-9.   DOI
10 Salah, A., and Moselhi, O. (2015). "Contingency modelling for construction projects using fuzzy-set theory." Engineering, Construction and Architectural Management, emerald PUBLISHING, 22(2), pp. 214-241.   DOI
11 Yoo, J.K., Kim, D.H., Moon, D.S., and Lee, H.S. (2019). "Study on Introduction of Probabilistic Contingency using Stochastic Cost-Risk Assessment Model.: Journal of the Korean Society for Railway, The Korean Society For Railway, 22(2), pp. 178-187.   DOI
12 Kim, D.Y. (2016). "Risk-based Decision Model for Contingency Estimation of Large Construction Projects." Journal of Decision Science, The Korea Society of Decision Sciences, 24(2), pp. 11-26.
13 Kermanshachi, S., and Rouhanizadeh, B. (2018). "Feasibility analysis of post disaster reconstruction alternatives using automated BIM-based construction cost estimation tool." Proceeding of CSCE 6th International Disaster Mitigation Specialty Conference, Montreal: Canadian Society of Civil Engineering, Canadian Society of Civil Engineering.
14 Rani, H.A. (2017). "The Analysis of Importance Index to the Dominant Category Causing Contractor Contingency Cost in Aceh Province." University Of Muhammadiyah Aceh, Academia.edu, pp. 1-5.
15 Howell G. (2012). "Uncertainty and contingency: implications for managing projects." Proceedings of the 20th Annual Conference of the International Group for Lean Construction, The International Group For Lean Construction.
16 Kim, Y.W., and Park, H.S. (2012). "Analysis of Construction Management Market Using System Thinking." Journal of the Korean Society of Civil Engineers D, KSCE, 32(3), pp. 239-245.   DOI
17 Kang, H.W., Min, B.J., and Kim, Y.S. (2010). "A Study on the Costs Variation Range through the Risk Factors for Overseas Plant Projects." Journal of the Architectural Institute of Korea Structure & Construction, Architectural Institute Of Korea, 26(7), pp. 139-146.
18 Lee, D.G., and Cha, H.S. (2016). "A Probabilistic Risk-based Cost Estimation Model for Initial-Stage Decision Making on Apartment Remolding Projects." Korean Journal of Construction Engineering and Management, KICEM, 17(2), pp. 70-79.   DOI
19 Koo, K.Y., and Kim, H.S. (2016). "A Study on the Investigation into Obstacles in Construction Budget Estimating." Korean Journal of Construction Engineering and Management, KICEM, 17(3), pp. 81-89.   DOI
20 Kwon, H.C., and Kang, C.W. (2016). "Contingency and Management Reserves Estimation Method for Project Budget." Journal of Korean Society of Industrial and Systems Engineering, KSISE, 39(1), pp. 17-24.   DOI
21 Lee, H.J., and Suhr, M.S. (2011). "A Study on the Analysis of Cost Management System and the Awareness for large and small Construction Company." Proceedings of the National University Student Conference, KICEM, pp. 39-42.
22 Lee, J.Y. (2010). "Analysis of the Schedule Risk Importance using PROMETHEE in Building Construction Management." MS thesis, Kyungwon Univ., Gyeonggi-do.
23 Lhee, S.C., Flood, I., and Issa R.R.A. (2014). "Development of a two-step neural network-based model to predict construction cost contingency." Journal of Information Technology in Construction, Kungliga Tenkniska Hoegskolan/Royal Institute of technology, 19(24), pp. 399-411.
24 Love, P.E.D., Wang, X., Sing, C.P., and Tiong, R.L.K. (2013). "Determining the probability of project cost overruns." Journal of Construction Engineering and Management, ASCE, 139(3), pp. 321-330.   DOI
25 Nieto-Morote, A., and Ruz-Vila, F. (2011). "A fuzzy approach to construction project risk assessment." International Journal of Project Management, 29(2), pp. 220-231.   DOI
26 Lee, M.H. (2011). "A Study to Establish Measures to Manage costs through an Analysis of Factors that Affect a construction projects of a Construction Work." MS thesis, Deagu Univ., Gyeongsangbuk-do.
27 Seo, J.P., Lee, S.H., Song, Y.W., and Choi, Y.K. (2012). "A Study of Analysis for Impact Assessment of the Cost Risk-Factor on the Design-Build Projects based on Business Process." Korean Journal of Construction Engineering and Management, KICEM, 13(3), pp. 14-24.   DOI
28 Taroun, A. (2014). "Towards a better modelling and assessment of construction risk: Insights from a literature review." International Journal of Project management, Association for Project Management (APM) and the International Project Management Association (IPMA), 32(1), pp. 101-115.   DOI
29 Yoon, W.S., and Go, S.S. (2011). "A Study on the Construction Cost Risk through Analyzing the Actual Cost of Public Apartment." Korean Journal of Construction Engineering and Management, KICEM, 12(6), pp. 65-78.   DOI
30 Yun, G.C., and Kim, H.S. (2003). "Systematization of Core Knowledge for Construction Project Budget." Journal of Korean Society of Industrial and Systems Engineering, KSISE, 19(3), pp. 147-154.