The Harmony and Moderation of Between Defect Liability and Default Liability in the Construction Contract  

Ahn, Sanghyo (Plant Contract Management Team DL E&C, Department of Construction Law, Kwangwoon University)
Sin, Manjoong (Department of Law, Kwangwoon University)
Publication Information
Korean Journal of Construction Engineering and Management / v.23, no.2, 2022 , pp. 65-75 More about this Journal
Abstract
On 11 June 2021, the Supreme Court ruled that the judgment of the lower court was justified for the subject case, that the plaintiff could assert the defendant's liability for default due to incomplete performance even though the warranty period for defects which stipulated in the particular condition of the contract has expired. In Korean civil law, the concurrent between the exclusion period for defect warranty and the extinctive prescription for default liability is conceded, since the exclusion period and the extinctive prescription have their respective purposes in law, therefore these two should be judged by harmonizing them based on that they are mutually related. If the subject judgment is generalized, there is no reason to exist for the provisions of defect liability in the construction contract any longer. This study examines the subject judgments through the general theory and precedent case studies on the defect liability and default liability, then derived any problems that may arise if the subject judgment is generalized. In addition, based on a realistic model, it was suggested for a practical improvement method that both the provisions of the warranty period shall be changed realistic and to stipulate the character of its nature as written provisions in the contract.
Keywords
Strict Liability; Defect Liability; Default Liability; Exclusion Period; Extinctive Prescription;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Kim, J.H. (2014). "The Concurrent between Exclusion Period and Extinctive Prescription." The Justice, Korean Legal Center, 2014.04, pp. 261-289.
2 Park, J.G. (2018). "Detailed Theory and Practice of Construction Contract Management." Theory of Construction Contract Management, Construction Economy, pp. 497.
3 Seo, S.K. (2016). "A Study on Liability for Warranty Against Architecture Defects." Ph.D. Dept. of Law, Graduate School, Dong Eui University.
4 Lee, J.M. (2020). "Contention between Contractor's Liability for Default of Obligation and Liability for Warranty against Defects." The Journal of Property Law, prolaw, 37(2), pp. 147-172.
5 Hong, S.G. (2018). "Suspending the Event-Based Accrual of Extinctive Prescription: The "objective discoverability." standard of Korean case law." The Journal of Comparative Private Law, KACPL, 25(4), pp. 1361-1436.   DOI
6 Kim, D.H. (2014). "Period for Exercise of Warranty and Prescription." Kookmin Law Review, Legal Research Institute Kookmin University, 26(3), pp. 35-61.   DOI
7 Choi, M.K. (2017). "A Study on the Theory of Precedents about the Starting Point of Reckoning in Extinctive Prescription and Exclusion Period." The Journal of Property Law, prolaw, 34(3), pp. 216-304.
8 Kim, C. W. (2010). "Anspruchsbegrenzende Ausschlussfristen und Verjahrung." The Journal of Property Law, prolaw, 26(3), pp. 1-40.