Improvement Plan Through Analysis of the Current Status of Construction Period Calculation of Public Construction Projects  

Lee, Jong-Tae (Department of Architectural Engineering, Chungnam National University)
Yun, Hyun-Do (Department of Architectural Engineering, Chungnam National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.22, no.3, 2021 , pp. 12-20 More about this Journal
Abstract
In order to secure construction quality and safety and prevent cost disputes, the importance of calculating 'the appropriate construction period' has recently emerged. It is necessary to analyze a considerable amount of historical data to establish the standard for calculating the construction period. However, many experts are raising questions about the use of past data due to changes in the construction business environment, such as shortening working hours, reinforcing quality regulations, and changing climate conditions. In addition, the possibility of errors increases when calculating a uniform construction period using historical statistics because the work order and productivity are very diverse according to construction conditions. Therefore, through this study, a new solution to change from the method of analyzing past data to the method of reviewing current production data through an active 'transformation of thoughts' was proposed through this study. In other words, the process of reviewing and calculating 'the appropriate construction period' was institutionalized by introducing 'process management experts' and 'construction experts by type of construction' in the design stage.
Keywords
Public Construction Work; Appropriate Construction Period; Quality; Safety;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Hwang, H.S. (2002)0 "Analysis of Actual Duration by Effecting Elements to Duration Estimate - Focused on Standard Duration of the Office Building Construction." Korean Journal of Construction Engineering and Management, KICEM, 3(3), pp. 84-93.
2 Ministry of Land, Infrastructure and Transport Ordinance No. 1140 (Jan. 1, 2019). "Standards for Calculating Construction Period for Public Construction Works"
3 Han, T.G., and Kim, Y.S. (2000). "An Estimation Method of Activity Duration Using Fuzzy Set Theory." Journal of the Regional Association of Architectural Institute of Korea, 16(3), pp. 93-102.
4 Hong, S.H. (2018). "The Current Status and Implications of the Construction Period Calculation System for Overseas Public Construction Projects." Construction Management, Korea Construction Management Association, 19(6), p. 50.
5 Lee, B.S., Kim, K.N., and Lee, M.J. (2015). "A Study on Normal Project Duration for Water Resource Project." Journal of the Korea Construction Management Association, Korea Construction Management Association, 16(1), pp. 37-38.
6 Lee, H.S. (1996). "A Method of Estimating the Construction Duration based on Repetitive Work Modules for Reinforced Concrete Buildings." Journal of the Architectural Institute of Korea, Architectural Institute of Korea, 12(5), pp. 266.
7 Ministry of Employment and Labor Act No. 15513 (Mar. 20, 2018). "Labor Standards Act"
8 Park, M.S., Kim, S., and Sin, E.Y. (2019). "Analysis of the Critical Path for Calculating the Proper Construction Period of Construction Project." Proceedings of the Korea Construction Management Association Conference, Korea Construction Management Association, p. 127.
9 Ministry of Land, Infrastructure and Transport Notification No. 2020-15 (Jan. 13, 2020). "Guidelines for design competition, implementation of basic design, etc. and review of economic feasibility of design"
10 Ministry of Strategy and Finance Ordinance No. 386 (Jul. 12, 2018), "Guidelines for managing total project costs"