Performance Analysis of Pre-Construction Phase of CM at Risk Project in Public Sector  

Park, Bo-sung (Department of Architectural Engineering, Chungbuk National University)
Kim, Ok-kyue (Department of Architectural Engineering, Chungbuk National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.22, no.2, 2021 , pp. 97-105 More about this Journal
Abstract
The CM at Risk project, which started with the aim of strengthening the global competitiveness of the domestic construction industry through innovation of ordering system, is being implemented in the form of pilot projects in the public sector. However, it seems that it is necessary to enact related laws and regulations to move to the formal ordering system, and the performance analysis of the project is still insufficient. In this paper, the effectiveness and reliability of the project were verified through the performance analysis of the Pre-Construction Service of the four pilot projects currently being implemented. The results of the study were analyzed in five areas including Team Building, Design Book, Construction Period, VE, and BIM. Through the interview survey, the problems were confirmed and improvement plans were presented. The results of this study are expected to be used as basic data for the legalization of ordering system to be implemented in the future.
Keywords
CM at Risk; Public Secter; Pilot Project; Pre-Construction Service;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Byambadorj, T. (2012). "A Study of Factors that Caused 'CM at Risk's Inactivity and Proposal for the System Improvement." M.S. Dissertation, Department of Architecture, Soongsil University, pp. 1-44.
2 Cho, H.K. (2011). "Construction Management Services during Pre-Construction Stages." M.S. Dissertation, Department of Architectural Engineering, Sejong University, pp. 37-60.
3 Han, J.H. (2019). "Risk Factors to Implement CM at Risk Pilot Project." M.S. Dissertation, Department of Construction Management, Hanyang University, pp. 19-47.
4 Han, J.H., Kim, K.T., and Ahn, Y.H. (2018). "Major Risk Factors to Implement CM at Risk Pilot Project on the Public Sector." Korean Journal of Construction Engineering and Management, KICEM, 19(3), pp. 61-69.   DOI
5 Han, T.H. (2018). "Innovation of Pre-Construction Service Based Construction Production Method." Korean Journal of Construction Engineering and Management, KICEM, 19(5), pp. 41-45.
6 Han, T.H., and Park, J.H. (2017). "A Possibility of Pre-Construction Service and its Core Technologies in Domestic Construction Market." 建築, AIK, 61(5), pp. 39-46.
7 Kim, J.G. (2008). "The Strategy of the General Contractor Under the Circumstances of CM at Risk." M.S. Dissertation, Department of Architectural Engineering, Dong-A University, pp. 35-50.
8 Kim, J.H. (2020). "PRECON." MID, pp. 113-234.
9 Koh, S.H. (2018). "Comparison Analysis of BIM Use and Levelin the Domestic and Overseas BIM Projects according to Project Delivery System." M.S. Dissertation, Department of Construction Management, Hanyang University, pp. 5-28.
10 Kim, J.H. (2010). "An Analysis about Factors Affecting Inactiveness of CM at Risk at Korean Construction Industry." M.S. Dissertation, Department of Construction Management, Hanyang University, pp. 13-39.
11 Koo, S.K. (2017). "Risk Factor Assessment for Guaranteed Maximum Price Contract in CM at Risk." M.S. Dissertation, Department of Construction Management, University of Seoul, pp. 38-94.
12 Lee, C.J., Lee, S.H., and Ahn, Y.H. (2017). "Benchmarking of US General Contractor's Pre -construction Services for a CM at Risk Project to Improve Contractor's Competitiveness." Journal of the Korea Institute for Structural Maintenance and Inspection, JKSMI, 21(5), pp. 9-18.
13 Lee, K.D. (2015). "A Study on the Analysis of main Barriers for the Activation of CM at Risk in the Domestic Construction Industry." M.S. Dissertation, Department of Architectural Engineering, Kyungpook National University, pp. 47-58.
14 Son, K.N. (2018). "Importance Analysis of Obstacle Factors on the CM at Risk Projects using AHP Method." M.S. Dissertation, Department of Construction Management, Hanyang University, pp. 15-67.
15 Park, H.K. (2011). "A Study on the Effect of Pre-Detecting Errors Using BIM in the Pre- Construction Phase." M.S. Dissertation, Department of Architectural Engineering, Yonsei University, pp. 50-75.
16 Park, K.M., and Kim, C.D. (2016). "Improvement through Analysis of Current Open Book Policy for the Korean CM at Risk." Korean Journal of Construction Engineering and Management, KICEM, 17(2), pp. 3-11.   DOI
17 Park, S.J. (2020). "Improving the Performance of Construction Projects Introducing CM at Risk." M.S. Dissertation, Department of Construction Management, Hanyang University, pp. 29-40.
18 Shin, S.H. (2004). "A Plan for Application of CM at Risk to the Public Construction Sector in Korea." M.S. Dissertation, Department of Construction Management, University of Seoul, pp. 35-107.