Towards a Transportation Support System for Off-site Construction : Identifying Key Functions and Diagramming Functional Blocks  

Lee, Gangho (Department of Architectural Engineering, Graduate School, Incheon National University)
Kim, Minguk (Department of Architectural Engineering, Incheon National University)
Lee, Chansik (Division of Architecture and Urban Design, Incheon National University)
Koo, Choongwan (Division of Architecture and Urban Design, Incheon National University)
Kim, Taewan (Division of Architecture and Urban Design, Incheon National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.22, no.2, 2021 , pp. 21-30 More about this Journal
Abstract
The existing construction industry is classified into industries with low productivity compared to other industries. In order to solve the decline in productivity in the construction industry, the world is focusing on off-site construction (OSC), which is about 40% more productive than existing construction methods. This high productivity is possible because the three stages of production, transport to the site, and site assembly are consistently maintained in a continuous flow. This study conducted a functional survey through literature review, preliminary field survey, questionnaire, and expert interview. The surveyed function were classified into five categories: convenience, flexibility, manageability, communication, and safety, and the functional characteristics of flexibility, manageability, and communication were high. Because of the change according to the construction progress, the production schedule of the factory, and the variety of transportation time required. Finally, A functional block diagram was developed based on the 15 functions corresponding with an average score of 4 or more in the surveyed function score result. If the OSC transport system is established through this study, It can contribute to a successful construction OSC project and increase productivity.
Keywords
Off-Site-Construction; Transportation; System Development View; Functional Block Diagram;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Boyd, N., Khalfan, M.M., and Maqsood, T. (2013). "Off-site construction of apartment buildings." Journal of architectural engineering, 19(1), pp. 51-57.   DOI
2 Cho, Y.J., Oh, S.R., Park, J.M., Choy, I., Kim, K.B., and Lim, J. (1993). "Function Block Diagram Approach for Manufacturing Process Control Programming." IFAC Proceedings Volumes, 26(2), pp. 461-464.
3 Dawood, N.N., and Neale, R.H. (1990). "A survey of current production planning practices in the precast concrete industry." Construction Management and Economics, 8(4), pp. 365-383.   DOI
4 Gary Sullivan, Stephen Barthorpe, Stephen Robbins (2010). "Managing Construction Logistics" Wiley-Blackwell, pp. 17.
5 Jang, J., Chen, H., Lee, C., and Kim, T. (2019). "Research Trends in Off-Site Construction Management: Review of Literature at the Operation Level." Korean Journal of Construction Engineering and Management, KICEM, 20(4), pp. 114-125.   DOI
6 Kwahk, G.J., Sohn, J.R., Kim, K.R., Sohn, C.B., and Kim, J.J. (1998). "A Logistics Information Management System for the Prefabricated Precast Concrete Panels." Journal Architectural Institute of Korea Structure and Construction, 14, pp. 87-94.
7 Morabito, R., Morales, S.R., and Widmer, J.A. (2000). "Loading optimization of palletized products on trucks." Transportation Research Part E: Logistics and Transportation Review, 36(4), pp. 285-296.   DOI
8 London, K., and Singh, V. (2013). "Integrated construction supply chain design and delivery solutions." Architectural Engineering and Design Management, 9(3), pp. 135-157.   DOI
9 Liu, D., Li, X., Chen, J., and Jin, R. (2020). "Real-Time Optimization of Precast Concrete Component Transportation and Storage." Advances in Civil Engineering. pp. 18
10 Lee, J. W., and Lee, K.H. (1999). "Microprocessor FBD Visualization." Communications of the Korean Institute of Information Scientists and Engineers, 26(2), pp. 36-38.
11 Markhauser, C.P. (1996). "A cost effective software for TV engineers, based on a block diagram simulation language." IEEE transactions on consumer electronics, 42(3), pp. 705-709.   DOI
12 Ng, S.T., Shi, J., and Fang, Y. (2009). "Enhancing the logistics of construction materials through activity-based simulation approach." Engineering, Construction and Architectural Management, 22(1): pp. 91-107.   DOI
13 Olsson, J., Larsson, T., and Quttineh, N.H. (2020). "Automating the planning of container loading for Atlas Copco: Coping with real-life stacking and stability constraints." European Journal of Operational Research, 280(3), pp. 1018-1034.   DOI
14 Pheng, L.S., and Chuan, C.J. (2001). "Just-in-time management of precast concrete components." Journal of construction engineering and management, 127(6), pp. 494-501.   DOI
15 Yoon, Y.S., Lee, H.S., and Suh, S.W. (2002). "The flow of Temporary Facility Planning Information in High-rise Building Construction." Korean Journal of Construction Engineering and Management, KICEM, 3(1), pp. 91-96.
16 Pheng, L.S., and Chuan, C.J. (2001). "Just-in-time management of precast concrete components." Journal of construction engineering and management, 127(6), pp. 494-501.   DOI
17 Park, Y.S., Yeom, D.J., and Kim, Y.S. (2018). "Development of Material Management System for Construction on the Downtown Area." Korean Journal of Construction Engineering and Management, KICEM,19(6), pp.135-136.   DOI
18 Woo, H.C., Kim, J.C., Kim, Y.M., Lee, J.C., Lee, W.D., and Chung, J.D. (2011). "A Study on the Utilization of Functional Models in the Project Design Reviews." The Korean Society for Railway, In Proceedings of the KSR Conference, pp. 1591-1598.
19 Polat, G. (2010). "Precast concrete systems in developing vs. industrialized countries." Journal of Civil Engineering and Management, 16(1), pp. 85-94.   DOI