Integrated Project Delivery in the Pre-construction Phase : Case Study of IPD for Lean Construction  

Jang, Hanbyeol (Department of Architectural system Engineering, Hanyang University)
Lee, Joosung (Department of Architectural Engineering, Hanyang University)
Ahn, Yonghan (Department of Architectural Engineering, Hanyang University)
Publication Information
Korean Journal of Construction Engineering and Management / v.20, no.6, 2019 , pp. 11-22 More about this Journal
Abstract
Current construction project processes pose difficulties for construction management as inefficient communication between project participants seldom accurately reflects the needs of the owner. To solve this problem, lean construction-based Integrated Project Delivery (IPD), which facilitates cooperation and builds trust through the formation of horizontal relationships among participants, is becoming increasingly popular. However, although lean construction-based IPD improves productivity in the construction industry, few studies have focused specifically on developing effective methods that maximize the benefits gained from lean construction-based IPD. This study therefore analyzed success factors for lean construction-based IPD projects by analyzing prior studies to identify factors that support IPD success. Application methods were analyzed and an example of how they are actually used in the field was examined through an in-depth single case analysis. The findings of this research can be applied to support lean construction-based IPD projects in Korea, improving their efficiency and boosting owner satisfaction.
Keywords
Construction Management; Lean Construction; Integrated Delivery Method;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Ghassemi, R., and Becerik-Gerber, B. (2011). "Transitioning to Integrated Project Delivery: Potential barriers and lessons learned." Lean Construction Journal, pp. 32-52.
2 Han, J.H. (2009). "A study on constraint analysis connected with lean construction." MS thesis, Donga University.
3 Jang, M.W. (2012). "A Study on the Derivation of Priorty Item for IPD Adoption in Domestic Construction Indurstry." MS thesis, Yeungnam University.
4 Jeon, H.W., Ahn, J.H., and Park, H.S. (2011). "A Basic Study on Design Process of BIM for the Use of LEAN and IPD Methods in Domestic Industry." Korean Journal of Construction Engineering and Management, KICEM, 31(1), pp. 71-72.
5 Kang, K.H., Park, J.R., Kim, J.H., and Kim, J.J. (2010). "A Study on the Introduction of IPD by the Study of Cases in the U.S." Journal of the Architectural Institute of Korea Structure & Construction, 30(1), pp. 317-318.
6 Koo, B.S., Park, H.S., Chang, C.K., and Kim, D.Y. (2006). "Implementation of Lean Construction on London Heathrow Airport's T5 Project." Journal of the Architectural Institute of Korea Structure & Construction, 22(7), pp. 141-148.
7 KPMG. (2013). "Integrated Project Delivery: Managing risk and making it work for all parties."
8 Lean Construction Institute. (2018). "GREAT DESIGN ENABLED BY LEAN"
9 Liu, M., Griffis, F.H., and Bates, A.J. (2013). "Compensation Structure and Contingency Allocation in Integrated Project Delivery." American Society for Engineering Education conference & exposition.
10 Mesa, H.A., Moleanaar, K.R., and Alarcon, L.F. (2019). "Comparative analysis between integrated project delivery and lean project delivery." International Journal of Project Management, 37, pp. 395-409.   DOI
11 Sarhan, S. (2015). "The Concept of Waste as Understood in Lean Construction." Lean Construction Blog.
12 Wills, B. (2014) "The Advantage and Limitation of Single Case Study Analysis." E-international relations students.
13 Song, W.S., Jung, S.H., Lee, K.S., Song, Y.W., and Choi, Y.K. (2013). "Research on the Implementation of IPD for Customized Design Project Design Change." Journal of the Architectural Institute of Korea, 33(1), pp. 579-580.
14 Shin, K.C., and Ham, I.H. (2012). "A Study of Integrated Project Delivery (IPD) Methods Based on Building Information Modeling (BIM)." Journal of the Korean Digital Architecture Interior Association, 12(3), pp. 15-25.
15 University Of Minnesota. (2016). "Motivation and Means: How and why IPD and Lean lead to success." Integrated Project Delivery Alliance, Lean Construction Institute.
16 Colin, R. (2002). Real World Research. 2nd ed, Blackwell Publishers, pp. 220-223.
17 Song, K.S., Yun, J.S., and Kwon, O.C. (2011). "A Case Analysis on the Multi-Party Contract of IPD for the BIM Acquisition Process." Journal of the Architectural Institute of Korea Structure & Construction, 31(2), pp. 445-446.
18 Song, S.M., Kim, Y.S., Chin, S.Y., and Kwon, S.W. (2011). "An Analysis on the Perception of Domestic Construction Engineer to Introduce IPD." Korean Journal of Construction Engineering and Management, KICEM, 2(2), pp. 72-80.
19 Briscoe, G., and Andrew, D. (2005). "Construction supply chain integration: an elusive goal?" Supply Chain Management: An International Journal, 10(4), pp. 319-326.   DOI
20 Center for Innovation in the Design & Construction Industry (CIDCI). (2018). "Integrated project delivery: An action guide for leaders." CIDCI.
21 ConsensusDocs. Standard multi-party integrated project delivery (IPD) agreement. ConsensusDocs.
22 Darrington, J. (2011). "Using a design-build contract for Lean Integrated Project Delivery." Lean Construction Journal, pp. 85-91.
23 Eriksson, P.E. (2010). "Improving construction supply chain collaboration and performance: A lean construction pilot project." Supply Chain Management: An International Journal, 15(5), pp. 394-403.   DOI
24 Kim, Y.J., Lee, Y.M., Shin, T.H., Kim, Y.S., and Chin, S.Y. (2009). "A Preliminary Study for Adoption of IPD to Public Sector Delivery Systems in the Korean Construction Industry." Journal of the Architectural Institute of Korea Structure & Construction, 29(1), pp. 609-612.
25 Kim, D.Y. (2003). "Guidelines for Implementing Lean Construction." Journal of the Architectural Institute of Korea Structure & Construction, 19(9), pp. 121-128.
26 Kim, S.W. (2009). "The Public Project Application of Management Analysis and Management Plan Proposed Based on Lean for Government Owner." MS thesis, Kyungnam University.
27 Kim, Y.W., and Kim, K.H. (2008). "A Study on Preconstruction Process in Support of Lean Project Delivery System : Case Study of Children's Hospital at Bellevue, Wa, U.S.A." Korea Institute of Healthcare Architecture, pp. 47-54.
28 AIA National. (2012). "IPD case studies." AIA California Council.
29 Abdelhamid, T.S. (2012). All about Lean construction, Construction Employer Associated Builders exchange magazine.
30 AIA National. (2007). "Integrated project delivery: A Guide." AIA California Council.
31 Ashley, D.B., Lurie, C.S., and Jaselskis, E.J. (1987). "Determinants of construction project success." Project Management Journal, 18(2), pp. 69-79.