Research Trends in Off-Site Construction Management : Review of Literature at the Operation Level  

Jang, JunYoung (Department of Architectural Engineering, Incheon National University)
Chen, Hao (Department of Architectural Engineering, Incheon National University)
Lee, Chansik (College of Urban Architecture epartment Engineeringof Architectural Engineering, Incheon National University)
Kim, TaeWan (College of Urban Architecture Engineering, Incheon National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.20, no.4, 2019 , pp. 114-125 More about this Journal
Abstract
Off-Site Construction (OSC) is a new construction method based on factory production. OSC (Off-Site Construction) is a new construction method based on factory production. Researches such as OSC-related design and production standardization, transport methods are actively conducted in the U.S., UK and other parts of the world as this new method has an edge over existing methods in terms of productivity, economy and quality. As the emergence of this new area requires reasonable management, an analysis of the scope of construction project management is required accordingly. Therefore, this research analyzed the study trends and relationships at the CM/PM range's "Operation level" to identify areas of study, relationship between studies and deficiencies in current research. This study carried out a comprehensive literature review of the OSC (CM/PM) research by analyzing 94 papers in Operation level as of September 3, 2018, and the analysis results are as follows. (1) Working stage level researches have been increasing rapidly since 2006. (2) Non-volumetric type is contributing most significantly at work stage level. In the building sector, it has been identified that problems such as residential: living, quality issues, non-residential: economic difficulties, factory: productivity problems have been addressed. (4) The Non-volumetric pre-assembly type dealt with the economic feasibility of residential and non-residential buildings, whereas the modular type was studied in regards to assembly quality. (5) From 2006, project management areas (e.g., quality, human resources, risks) have been expanded. It is expected that this research will help find new areas of research for OSC. If the analysis is carried out to the level of the industrial, corporate and project phases in the future, it is deemed that the overall research flow and area of the OSC industry can be identified.
Keywords
Literature review; Off-site construction; Project management; Modular method; Operation level;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Benjaoran, V., and Dawood, N. (2006). "Intelligence approach to production planning system for bespoke precast concrete products." Automation in Construction, 15(6), pp. 737-745.   DOI
2 Kamali, M., and Hewage, K. (2016). "Life cycle performance of modular buildings: A critical review." Renewable and Sustainable Energy Reviews, 62, pp. 1171-1183.   DOI
3 Kim, M.K., Wang, Q., Park, J.W., Cheng, J.C.P., Sohn, H., and Chang, C.C. (2016). "Automated dimensional quality assurance of full-scale precast concrete elements using laser scanning and BIM." Automation in Construction, 72, pp. 102-114.   DOI
4 Kim, M.K,. Brilakis, L., and An, Y.K. (2015). "A study on influencing factors and revitalization of the adoption of off-site construction." Journal of KIBIM, 5(3), pp. 33-40.   DOI
5 Kim, S., Seol, H., Ikuma, L.H., and Nussbaum, M.A. (2008). "Knowledge and opinions of designers of industrialized wall panels regarding incorporating ergonomics in design." International Journal of Industrial Ergonomics, 38(2), pp. 150-157.   DOI
6 Korea Institute of Civil Engineering and Building Technology. (1997). Construction Engineering & Management. 1rd ed, Boseonggak, Korea, pp. 25-26.
7 Korea Productivity Center (2013). "Quarterly Labor Productivity Tendency." (Nov. 1, 2018)
8 Lee, C,J., and Lim, S,H. (2015). "An Analysis on Architectural Characteristics of Domestic Modular Housing and Building Material Standardization Effect through MC Design." Journal of the Korean Housing Association, 26(6), pp. 103-113.   DOI
9 Leu, S.S., and Hwang, S.T. (2002). "GA-based resource-constrained flow-shop scheduling model for mixed precast production." Automation in Construction, 11(4), pp. 439-452.   DOI
10 Sadiq, M., Bouferguene, A., Liu, H., Al-hussein, M., and Yu, H. (2018). "Automation in Construction Integrated production planning and control system for a panelized home prefabrication facility using simulation and RFID." Automation in Construction, Elsevier, 85(August 2017), pp. 369-383.   DOI
11 Salama, T., Salah, A., Moselhi, O., and Al-Hussein, M. (2017). "Near optimum selection of module configuration for efficient modular construction." Automation in Construction, 83, pp. 316-329.   DOI
12 Samani, P., Jeremy, G., Leal, V., Mendes, A., and Correia, N. (2018). "Lifecycle Cost Analysis of Prefabricated Composite and Masonry Buildings : Comparative Study." 24(1), pp. 1-11.
13 Shaked, O., and Warszawski, A. (1992). "CONSCHED: Expert System for Scheduling of Modular Construction Projects." Journal of Construction Engineering and Management, 118(3), pp. 488-506.   DOI
14 Sutrisna, M., Ramanayaka, C.D.D., Goulding, J.S., Sutrisna, M., Ramanayaka, C.D.D., and Goulding, J.S. (2018). "Developing work breakdown structure matrix for managing offsite construction projects." 2007 (May).
15 Svajlenka, J., and Kozlovska, M. (2018). "Houses based on wood as an ecological and sustainable housing alternative-Case study." Sustainability, 10(5), p. 1502.   DOI
16 Finnie, D., Ali, N.A., and Park, K. (2018). "Enhancing off-site manufacturing through early contractor involvement (ECI) in New Zealand." Management Procurement and Law, 171(4), pp. 176-185.
17 Chen, Y., Okudan, G.E., and Riley, D.R. (2010). "Decision support for construction method selection in concrete buildings: Prefabrication adoption and optimization." Automation in Construction, 19(6), pp. 665-675.   DOI
18 Cheng, M.Y., and Chen, J.C. (2002). "Integrating barcode and GIS for monitoring construction progress." Automation in Construction, 11(1), pp. 23-33.   DOI
19 Diez, R., Padron, V.M., Abderrahim, M., and Balaguer, C. (2007). "AUTMOD3 : The Integration of Design and Planning Tools for Automatic Modular Construction." International Journal of Advanced Robotic Systems, 4(4), pp. 457-468.
20 Garg, A., and Kamat, V.R. (2012). "Virtual Prototyping for Robotic Fabrication of Rebar Cages in Manufactured Concrete Construction." Journal of Architectural Engineering, 20(1), pp. 309-318.
21 Gibb, A. (2001). "A review of recent and current industry and research initiatives on pre-assembly in construction." Construction Research & Innovation Strategy Panel Rights, pp. 5-8.
22 Gibb, A., and Isack, F. (2003). "Re-engineering through pre-assembly: Client expectations and drivers." Building Research and Information, 31(2), pp. 146-160.   DOI
23 Ha, T.H. (2011). "Structural Performance of Modular Building System." Journal of the KGBC, 12(3), pp. 26-33.
24 Hallmark, R., White, H., and Collin, P. (2012). "Prefabricated Bridge Construction across Europe and America." Practice Periodical on Structural Design and Construction, 17(3), pp. 82-92.   DOI
25 Lim, S.H., and Lee, G.K. (2011). "A Study on the Standardization of UBR (Unit Bath Room) by Utilizing Reference Plane." Journal of Architectural Institute of Korea, 27(1), pp. 81-88.
26 Li, C.Z., Xu, X., Shen, G.Q., Fan, C., Li, X., and Hong, J. (2018). "A model for simulating schedule risks in prefabrication housing production: A case study of six-day cycle assembly activities in Hong Kong." Journal of Cleaner Production, 185, pp. 366-381.   DOI
27 Taghaddos, H., Asce, A.M., Hermann, U., Asce, M., Abourizk, S., Asce, M., Mohamed, Y., and Asce, M. (2014). "Simulation-Based Multiagent Approach for Scheduling Modular Construction." 28(April), pp. 263-274.   DOI
28 Tam, V.W.Y., Tam, C.M., and Ng, W.C.Y. (2007). "On prefabrication implementation for different project types and procurement methods in Hong Kong." Journal of Engineering Design and Technology, 5(1), pp. 68-80.   DOI
29 Li, C.Z., Zhong, R.Y., Xue, F., Xu, G., Chen, K., Huang, G. G., and Shen, G.Q. (2017). "Integrating RFID and BIM technologies for mitigating risks and improving schedule performance of prefabricated house construction." Journal of Cleaner Production, 165, pp. 1048-1062.   DOI
30 Li, Z., Shen, G.Q., and Xue, X. (2014). "Critical review of the research on the management of prefabricated construction." Habitat International, 43, pp. 240-249.   DOI
31 Martinez, S., Jardon, A., Navarro, J.M., Gonzalez, P., Martinez, S., Jardon, A., and Gonzalez, P. (2015). "Building industrialization : robotized assembly of modular products." Assembly Automation, 28(2), pp. 134-142.   DOI
32 Kim, D.M., Lee, J.S., Kim, J.H., and Kim, J.J. (2014). "Marketing Strategy and Influential Factors based on the Attributes of Unit Modular System." Korean Journal of Construction Engineering and Management, KICEM, 15(1), pp. 78-86.   DOI
33 McKinsey & Company (2017). Reinventing construction through a productivity revolution, McKinsey Global Institute Report, 2017-11.
34 Melo, R.S.S. De, and Alves, T.C.L. (2010). "Investigation of the supply chain of prefabricated wooden doors." Lean Construction Journal, pp. 30-42.
35 Xu, G., Li, M., Luo, L., Chen, C., and Huang, G.Q. (2018). "Cloud-based fleet management for prefabrication transportation." Enterprise Information Systems, Taylor & Francis, 13(1), pp. 87-106.   DOI
36 Wang, Y., Yuan, Z., and Sun, C. (2018). "Research on Assembly Sequence Planning and Optimization of Precast Concrete Buildings." Journal of Civil Engineering and Management, 24(2), pp. 106-115.   DOI
37 Wang, Z., and Hu, H. (2018). "Dynamic response to demand variability for precast production rescheduling with multiple lines." International Journal of Production Research, 56(16), pp. 5386-5401.   DOI
38 Wu, P., and Low, S.P. (2014). "Barriers to achieving green precast concrete stock management - a survey of current stock management practices in Singapore." International Journal of Construction Management, 14(2), pp. 78-89.   DOI
39 Xue, H., Zhang, S., Su, Y., and Wu, Z. (2018). "Capital cost optimization for prefabrication: A factor analysis evaluation model." Sustainability, 10(1), pp. 1-22.   DOI
40 Yang, H., Chung, J.K.H., Chen, Y., Pan, Y., Mei, Z., and Sun, X. (2018). "Ordering Strategy Analysis of Prefabricated Component Manufacturer in Construction Supply Chain." Mathematical Problems in Engineering, 2018.
41 Baeza Pereyra, J., and Alvarez Romero, S. (2009). "Technical and economical simulation of two roofing construction systems in southeast Mexico." Revista Ingenieria de Construccion, 24(2), pp. 167-180.
42 Altobelli, F., Taylo, H., and Bernold, L. (1993). "The International Institute of Production Engineering Research (CIRP)." Journal of Aerospace Engineering, 6(1), pp. 19-33.   DOI
43 Arashpour, M., Wakefield, R., Abbasi, B., Lee, E.W.M., and Minas, J. (2016). "Off-site construction optimization: Sequencing multiple job classes with time constraints." Automation in Construction, 71, pp. 262-270.   DOI
44 Arashpour, M., Bai, Y., Aranda-mena, G., Babhadiashar, A., Hosseini, R., and Kalutara, P. (2017). "Optimizing decisions in advanced manufacturing of prefabricated products: Theorizing supply chain configurations in off-site construction." Automation in Construction, 84, pp. 146-153.   DOI
45 Herkommer, F., and Bley, B. (1996). "CAD/CAM for the prefabrication of brickwork." Automation in Construction, 4(4), pp. 321-329.   DOI
46 Han, S.H., Al-Hussein, M., Al-Jibouri, S., and Yu, H. (2012). "Automated post-simulation visualization of modular building production assembly line." Automation in Construction, 21, pp. 229-236.   DOI
47 Han, S.H., Hasan, S., Bouferguene, A., Al-hussein, M., Asce, M., and Kosa, J. (2015). "Utilization of 3D Visualization of Mobile Crane Operations for Modular Construction On-Site Assembly." Journal of Management in Engineering, 31(5), pp. 1-9.
48 Heravi, G., and Firoozi, M. (2017). "Production process improvement of buildings' prefabricated steel frames using value stream mapping." The International Journal of Advanced Manufacturing Technology, 89(9), pp. 3307-3321.   DOI
49 Hosseini, M.R., Martek, I., Zavadskas, E.K., Aibinu, A.A., Arashpour, M., and Chileshe, N. (2018). "Critical evaluation of off-site construction research: A Scientometric analysis." Automation in Construction, 87, pp. 235-247.   DOI
50 Jaillon, L., and Poon, C.S. (2010). "Design issues of using prefabrication in hong kong building construction." Construction Management and Economics, 28(10), pp. 1025-1042.   DOI
51 Jin, R., Gao, S., Cheshmehzangi, A., and Aboagye-Nimo, E. (2018). "A Holistic Review of off-site Construction Literature Published between 2008 and 2018." Journal of Cleaner Production, 202, pp. 1202-1219.   DOI
52 Jo, S., Lee, E., and Pyo, K. (2018). "Integrating a Procurement Management Process into Critical Chain Project Management (CCPM): A Case-Study on Oil and Gas Projects, the Piping Process." Sustainability, 10(6), p. 1817.   DOI
53 O'Neill, D., and Organ, S. (2016). "A literature review of the evolution of British prefabricated low-rise housing." Structural Survey, 34(2), pp. 191-214.   DOI
54 Moghadam, M., Al-Hussein, M., Al-Jibouri, S., and Telyas, A. (2012). "Post simulation visualization model for effective scheduling of modular building construction." Canadian Journal of Civil Engineering, 39(9), pp. 1053-1061.   DOI
55 Niu, Y., Lu, W., Liu, D., Chen, K., Anumba, C., and Huang, G.G. (2017). "An SCO-Enabled Logistics and Supply Chain-Management System in Construction." Journal of Construction Engineering and Management, 143(3).
56 Yu, H., Al-Hussein, M., Al-Jibouri, S., and Telyas, A. (2013). "Lean Transformation in a Modular Building Company: A Case for Implementation." Journal of Management in Engineering, 29(1), pp. 103-111.   DOI
57 Zakaria, S.A.S., Gajendran, T., Rose, T., and Brewer, G. (2018). "Contextual, structural and behavioural factors influencing the adoption of industrialised building systems: a review." Architectural Engineering and Design Management, 14(1-2), pp. 3-26.   DOI
58 Zhai, Y., Zhong, R.Y., Li, Z., and Huang, G. (2017). "Production lead-time hedging and coordination in prefabricated construction supply chain management." International Journal of Production Research, 55(14), pp. 3984-4002.   DOI
59 Jonsson, H., and Rudberg, M. (2017). "KPIs for measuring performance of production systems for residential building: A production strategy perspective." Construction Innovation, 17(3), pp. 381-403.   DOI
60 Nor, M., Azman, A., Ahamad, M.S.S., Hamid, Z.A., and Gomez, C.P. (2012). "The selection of IBS precast manufacturing plant in Malaysia using GIS." Malaysian Construction Research Journal, 10(1), pp. 77-90.
61 Penin, L., Balaguer, C.P., J.M, R., F.J, B., and A, Aracil, R. (1998). "Robotized Spraying of Prefabricated Panels." IEEE Robotics & Automation Magazine, 5(3) (September), pp. 18-29.   DOI
62 Pereyra, J.R.B., Romero, S.O.A., Yucatan, U.A. De, Chen, Y., Okudan, G.E., and Riley, D.R. (2010). "Automation in Construction Sustainable performance criteria for construction method selection in concrete buildings." Automation in Construction, Elsevier B.V., 24(2), pp. 235-244.
63 PMI. (2013). A Guide to the Project Management Body of Knowledge. In (5a ed.). Pennsylvania: Project Management Institute, Inc.
64 Rausch, C., Asce, S.M., Nahangi, M., Perreault, M., Haas, C. T., Asce, F., and West, J. (2017). "Optimum Assembly Planning for Modular Construction Components." 31(1), pp. 1-14.
65 Rebolj, D., and Podbreznik, P. (2014). "Computers in Industry Supply-chain transparency within industrialized construction projectsus." 65, pp. 345-353.   DOI
66 Rohani, M., Fan, M., and Yu, C. (2014). "I ndoor and Built Advanced visualization and simulation techniques for modern construction management." 23(5), pp. 665-674.   DOI
67 Retik, A., and Warszawskit, A. (1994). "Automated Design of Prefabricated Building." Building and Environment, 29(4), pp. 421-436.   DOI