Analysis of Major Management Factors Affecting Crew Productivity in Road Bridge Construction Site Using IPA  

Huh, Young-Ki (Department of Architectural Engineering, Pusan National University)
Lee, Sang-Ho (Department of Architectural Engineering, Pusan National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.20, no.3, 2019 , pp. 39-45 More about this Journal
Abstract
Crew productivity in the construction industry is an important indicator of soundness and efficiency of work process, since all works in a site are conducted as groups of people. A survey was conducted in order to reveal importance and performance of major management factors affecting crew productivity in road bridge construction site using IPA. As a result of the analysis, it was found that 'Construction equipment' and 'Human resource related' factors among five major-categories are most important but with low performance. Furthermore, from another analysis with 27 factors of sub-categories, it is revealed that factors needed sustained attention are four, namely 'Just-in-time machinery delivery', 'Formation of a crew members', 'Skill of workers', and 'Site control and management', whereas those needed much more improvement are five, such as 'Machinery performance', 'Clearity of Design', 'Clearity of shop drawing', 'Timing of work instruction and approval', and 'Clearity of work instruction'. Findings from this study will enable road agencies as well as road construction experts to enhance crew productivity in a site.
Keywords
Road Bridge Construction; Crew Productivity; Productivity; Management Factor; IPA;
Citations & Related Records
Times Cited By KSCI : 6  (Citation Analysis)
연도 인용수 순위
1 Ahn, S.H., and Yu, J.H. (2009). "Management of work efficiency and work condition in construction site." Journal of Excellent Graduation Thesis of the Architectural Institute of Korea, AIK, 5, pp. 381-384.
2 Baek, K.G., Kang, S.H., Baek H.G., and Seo J.W. (2009). "A Study on the factors of haul routes planning for earthmoving." Journal of Conference Korea Institute of Construction Engineering and Management, KICEM. pp. 899-903.
3 H. Randolph Thomas (1991). "Labor productivity and work sampling: the bottom line." Journal of Construction Engineering and Management, ASCE, 117(3), pp. 423-444.   DOI
4 Kim, B.S., and Kwon, S.H. (2009). "The conceptual cost estimate model on preliminary design phase for RC rahmen bridge." Korean Journal of Construction Engineering and Management, KICEM, 10(2), pp. 111-120.
5 Kim, J.W., Kim, Y.S., Kim, Y.S., and Kim, S.B. (2008). "WBS development for acquisition and analysis of public housing productivity data." Korean Journal of Construction Engineering and Management, KICEM, 9(5), pp. 86-94.
6 Lee, D.W., Cho, H.J., Lee, K.J., and Kim, N.S. (2011). "Productivity analysis on the standard quantity-per-unit costing method and work crew combination method : focused on non-vibration mass excavation method." Journal of Korean Society of Civil Engineers, KSCE, 31(3), pp. 457-468.
7 Lee, K.J., and Kim, Y.S. (2010). "An importance analysis for the major schedule management factors classified by construction participants in high-rise building reinforced concrete work." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 26(12), pp. 185-192.
8 Kim, J.Y., Choi, J.H., and Lee, S.H. (2011). "Factors affecting the losses of domestic construction productivity and strategies for avoiding them." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 27(2), pp. 113-124.
9 Lee, S.B., and Pyo, Y.M. (2007). "A study on the analysis of factors decreasing construction labor-productivity using AHP method." Journal of the Architectural Institute of Korea Structure & Construction, AIKRA, 9(1), pp. 179-187.
10 Lee, S.H. (2004). "The measurement and analysis techniques of total project productivity on transportation projects." Journal of Conference Korea Institute of Construction Engineering and Management, KICEM. pp. 95-100.
11 Lee, S.H., and Hong, S.H. (2005). "An evaluation method for the impact of disruptive events on road construction projects using total project productivity." Journal of Korean Society of Civil Engineers, KSCE, 25(5), pp. 747-756.
12 O'Connor, James T., and Huh, Y.K. (2005). "Crew production rates for contract time estimation: bent footing, column, and cap of highway bridges." Journal of Construction Engineering and Management, ASCE, 131(9), pp. 1013-1020.   DOI
13 O'Connor, James T., and Huh, Y.K. (2006). "Crew production rates for contract time estimation: beam, erection, deck, and rail of highway bridges." Journal of Construction Engineering and Management, ASCE, 132(4), pp. 408-415.   DOI
14 Ohn, S.W., Woo, S.K., and Kim, O.K. (2007). "An application of simulation method to planning of road pavement operation." Korean Journal of Construction Engineering and Management, KICEM, 8(1), pp. 124-131.
15 Park, S. M., Park, T. E., and Kim, H. K. (2013). "Checklist for the application of concurrent engineering in bridge construction." Korean Journal of Construction Engineering and Management, KICEM, 14(1), pp. 3-11.   DOI
16 Seo, J.H., and Park, H.K. (2011). "A study on the development of standard of estimate of representative construction type of road project." Journal of Conference Korea Institute of Construction Engineering and Management. KICEM. pp. 97-98.
17 Son, C.B., and Lee, D.C. (2002). "An analysis on the factors decreasing productivity of building construction." Journal of the Architectural Institute of Korea Structure & Construction, AIK, 18(12), pp. 125-132.
18 Yoo, D.Y., Park, H.K., and Lim, H.M. (2013). "A study on the development of work-crew based daily-productivity for representative B.O.Q item in river conservation project." Journal of the Korean Society of Civil Engineers, KSCE, 33(6), pp. 2519-2528.   DOI
19 Yoon, B.S., Yu, J.H., and Kim, C.D. (2010). "An analysis on the influence of work management type on work condition." Korean Journal of Construction Engineering and Management, KICEM, 11(5), pp. 76-84.