A Basic Study on Effective Adjustment Method for Construction Escalation/De-Escalation Price  

Sung, Ju-yong (Public Procurement Service)
Kim, Dong-jin (Department of Civil Engineering, Chungnam National University)
Lee, Min-jae (Department of Civil Engineering, Chungnam University)
Publication Information
Korean Journal of Construction Engineering and Management / v.20, no.3, 2019 , pp. 3-11 More about this Journal
Abstract
The construction of a facility is an act whereby infrastructure such as roads and railways and other facilities such as housing and office spaces are constructed, and due to the characteristics of the relevant industry where such construction is carried out in a custom order method, it requires a long period of time mostly. While the construction is carried out over a long period of time, fluctuations in the price of raw materials required for the construction occur. Therefore, the cost of the construction also fluctuates inevitably. The fluctuation of the construction cost meshes closely with the profit of a constructor and the efficiency of government spending. Therefore, it is necessary to maintain the construction cost at a reasonable level by adjusting the construction cost rationally in order to secure the required construction quality and spend the budget efficiently. The buffer system for solving such problem is the contract amount adjustment system by fluctuations in prices (Escalation/De-Escalation). In this study, the method combining the escalation method based on the item adjustment method was suggested for an efficient contract amount adjustment method. In addition, it is proposed that there be an investigation and codification of matters not applied to government acts and regulations on contracts related to the adjustment of fluctuations in prices legally.
Keywords
Contract Amount Adjustment System; Escalation; Item Adjustment Method; Index Adjustment Method;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Jang, H.G. (2015). "Explanation of the latest public contract system." Sam-il Book.
2 Ministry of Strategy and Finance (2018). "Act on Contracts to Which the state is a Party."
3 Lee, J.S., and Shin, Y.C. (2011). "Improvement on the Managerial Method of Price Fluctuation System." Korean Journal of Construction Engineering and Management, KICEM, 12(2), pp. 3-11.   DOI
4 Na, S.H. (2005). "A Study on Improvement of Escalation Criteria based on Subcontract Dispute Cases." Chung-Ang University.
5 Choi, M. S. (2014). "A Study on the Policies to improve the Escalating Regulations of Construction Price : With a Focus on Results of a Delphi Survey" Korean Journal of Construction Engineering and Management. 5(6). pp.203-211.
6 Kim, S.H. (2011). "The Rationalization of Contract Sum Adjustment through Case Study of Price Fluctuation Adjustment based on Index Adjustment Method." Korean Journal of Construction Engineering and Management, KICEM, 12(4), pp. 70-79.   DOI
7 Cho, H. H. and Doe, G. Y. (2005). "Improvement of contract sum adjustment method caused by price fluctuation using construction cost index" Korean Journal of Construction Engineering and Management. 6(1). pp.162-168.
8 Ministry of Strategy and Finance (2018). "State Conctract Act"
9 Kim, W.Y., and Kim, Y.J. (2008). "Improved contract amount adjustment based on price fluctuation-Focusing on the main item index adjustment (plan)." The Construction & Economy Research Institute of Korea (CERIK).
10 Ji, Y.I. (2012). "Problem Analysis and Improvement Schemes to the Application of Producer Price Index for Construction Price Fluctuations." Chung-Ang University.
11 Procurement Agency (2017). "Escalation Price Review Practice and Q/A."