Risk Assessment and Contingency Prediction considering Work Characteristics for Modular Plant Construction Projects  

Kang, Hyunwook (The Chartered Research Institute of Construction Costs)
Kim, Jongwook (Corporation of Moo-Young Construction Management)
Kim, Yongsu (Faculty, Department of Architectural Engineering, Chung-Ang University)
Publication Information
Korean Journal of Construction Engineering and Management / v.19, no.5, 2018 , pp. 81-89 More about this Journal
Abstract
The purpose of this study is to assess the risk and predict the contingency for modular plant construction projects. Considering the work characteristics of the modular plant, The adapted research method is that suggest models for assessment impact of risk and predict the contingency considering risk. Based on the proposed models, It is selected one modular plant construction project and assessment impact of risk factors and predicted the contingency. The results of this study are as follows: Assessment the probability of occurrence of risk factors and intensity of impact, and extract 15 important risk factors. These are classified as Engineering, Procurement, Fabrication, Transportation, Construction phases to consider the work characteristics of the modular plant. The predicted contingency is that 6.739%(Engineering 2.850%, Procurement 6.225%, Fabrication 6.211%, Transportation 4.165%, Construction 8.168%) to prepare the basic business expense. The model is used as a way to derive quantitative results in the decision-making process for risk management in construction projects.
Keywords
Modular Plant; Risk Assessment; Contingency Prediction;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 AACE (2009). Cost Engineer's Notebook Vol. I&II(Estimation Contingency). American Association of Cost Engineering.
2 California (2012). Project Risk Management Handbook. California Department of Transportation.
3 Construction Industry Institute (CII). (2013). "SPC" 47th ASC Annual International Conference Proceedings.
4 CERIK (2000). The Necessity of Contingency Prediction System for Construction Projects. Construction and Economy Research Institute of Korea.
5 Exxon Mobil (2013). Project Tender Document.
6 FTA (1994). Risk Assessment in Fixed Guide way Transit System Construction.
7 Hwang, J., Choi, S., Lee, J., and Kim, Y. (2014). "Development of Bill Service Framework for Modular Housing Construction." Korean Journal of Construction Engineering and Management, KICEM, 15(5), pp. 138-146.   DOI
8 Kang, H. W. (2017). "Model of Risk Contingency Prediction Based on Risk Information in Construction Projects." Thesis of Ph.D The University of Chung-Ang.
9 Kang, H. W., Won, Y. M., Kang, M. G., and Kim, Y. S. (2012). "An Analysis on the Probability Costs Variation Ranges of the Cost Items from the Risk Factor Model for Construction Phase of Overseas Gas Plant Projects." Journal of the Architectural Institute of Korea, AIK, 28(1), pp. 191-198.
10 Kang, H. W., Kim, M. S., Kim, S. H., and Kim, Y. S. (2012). "A Study on the Analysis of Risk Factors in Engineering, Procurement and Construction Phase for Overseas Plant Project." Journal of the Architectural Institute of Korea, AIK, 28(5), pp. 111-118.
11 Kim, J. W. (2017). "Scenario-based Risk Factor and Risk Cost Analysis Model for Modular Plant Construction." Thesis of M.S. The University of Chung-Ang.
12 Kim, S. G. (2015). "Risk Value Calculation Method for Moderate Risk Concentration Type at Qualitative Risk Analysis Phase." Korean Journal of Construction Engineering and Management, KICEM, 16(2), pp. 38-45.   DOI
13 Kim, S. G. (2007). "A Model of the Construction Risk Management System for Site Personnel in the Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 8(2), pp. 90-98.
14 Lee, H. C., Lee, G., Yeo, S. K., and Go, S. S. (2009). "A Study on the Risk Evaluation of Construction Management Based on Risk Identification." Korean Journal of Construction Engineering and Management, KICEM, 10(3), pp. 83-91.
15 Park, C. Y., Kim. H. J., Won, J. W., Jang, W. S., and Han, S. H. (2016). "A Study for Selecting Modular Construction Method." Korean Journal of Construction Engineering and Management, KICEM, 17(4), pp. 12-19.   DOI
16 Lee, H. C., Shin, S. B., Hong, J. H., and Go, S. S. (2009). "A Study on the Risk Evaluation of Apartment Development Project based on VE." Korean Journal of Construction Engineering and Management, KICEM, 10(4), pp. 14-25.
17 Murtaza, M. B., Fisher, D. J., and Skibniewski, M. J. (1993). "Knowledge-based approach to modular construction decision support." Journal of Construction Engineering and Management, 119(1), pp. 115-130.   DOI
18 Park, K. J. (2012). "Introduction of Module Construction Method for Overseas Plant Projects." Korean Journal of Construction Engineering and Management, KICEM, 13(1), pp. 21-24.
19 Rogan, A. L., Lawson, R. M., and Bates-Brkljac, N. (2000). "Value and benefits assessment of modular construction." The Steel Construction Institute, Ascot.
20 Tatum, C. B., Vanegas, J. A., and Williams, J. M. (1987). "Construction Improvement using Prefabrication." Pre-assembly and Modularization, Technical Report 297, Austin: Construction Industry Institute.
21 Texas (2010). Risk-Based Construction Cost Estimating Reference Guide. Texas Department of Transportation.