An Estimating Model for Job-Site Overhead Costs according to Progress Rate  

Jeong, Kichang (Korea Institute of Construction Management)
Lee, Jaeseob (Division of Architectural Engineering, Dongguk University)
Publication Information
Korean Journal of Construction Engineering and Management / v.19, no.5, 2018 , pp. 43-52 More about this Journal
Abstract
Generally, research on construction cost has been done mostly regarding its direct cost, thus model regarding indirect cost lacks attention. This research seeks to introduce a model to predict on-site overhead cost for apartment construction projects, which constitutes a big portion in Korean construction industry. We devised an equation of 9th degree via curve-fitting, using multiple on-site actual expense data, which can be used to calculate per-progress rate, per-day on-site overhead cost. We further show prospective usage of the model by applying it on construction projects sizing about 30 billion won. Regarding the fact that previous studies could not recognize pattern changes of a total on-site overhead cost, this model is worthy of its conveniency and thoroughness, as well as providing reasonal ground for its derivation in predicting on-site overhead cost of apartment construction projects.
Keywords
Job-Site Overhead Costs; Apartment; Progress Rate; Construction Cost; Curve Fitting;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 Jeong, K., and Lee, J. (2016). "Improvement of the Calculation Standard for Prolongation cost of Domestic Public Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 17(4), pp. 95-102.   DOI
2 Jeong, K., and Lee, J. (2017). "Improvement of the Calculation Standard for Prolongation cost of Long-term Continuing Contracts Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 18(2), pp. 30-37.   DOI
3 Jeong, K., Park, Y., and Lee, J. (2012). "Study on introduction of 'Pre-Agreement system for Additional Incidental Cost' related to construction time extension." Korean Journal of Construction Engineering and Management, KICEM, 13(6), pp. 33-44.   DOI
4 Kim, H. (2011). "Study on a Model to Deploy Apartment Project Management Manpower." KyungHee Univ, of Seoul, Korea.
5 Kwon, K., Kim, S., Son, H., Choi, J., and Lee, D. (2010). "Investigation on the Manpower Staffing Plan Utiling Density Analysis Method." Proceedings of the Korean Institute of Building Construction Conference, The Korean Institute of Building Construction, pp. 119-123.
6 Kwon, M. (2015). "A study on human resources planning for building projects." Hanyang Univ, of Seoul, Korea.
7 Lee, W., Kim, S., Kim, S., Lee, D., and Won, I. (2010). "A Preliminary Studty on the Efficient Management Manpower Staffing According to the Building Size." Proceedings of the Korean Institute of Building Construction Conference, pp. 191-194.
8 Woo, H. (2012). "A Study of Cost Management and reduction strategy in construction work." Ulsan Univ, of Ulsan, Korea.
9 Yang, W. (2017). "A model about manpower allocation of engineer for apartment complex construction using effect of the project risk." Sungkyunkwan University, of Seoul, Korea.