Application of Accrual Basis for Calculation of Prolongation Cost in Construction Projects  

Jeong, Kichang (Korea Institute of Construction Management)
Lee, Jaeseob (Division of Architectural Engineering, Dongguk University)
Publication Information
Korean Journal of Construction Engineering and Management / v.19, no.5, 2018 , pp. 111-120 More about this Journal
Abstract
Recently, Domestic public construction projects are experiencing a great deal of disputes because of the growing uncertainty about the criteria for calculating the prolongation cost. In addition, researchers have been studying various systems and proper cost estimates in an effort to reduce the uncertainty of these systems and the occurrence of disputes. However, there is no standard yet for social consensus. Meanwhile, The study on the classification system according to the recognition standard of accounting has been systematically studied. As a result, the concepts of accrual and cash basis are defined separately. The purpose of this study is to verify the possibility of applying the concept of 'accrual basis' to the Standard for calculation of prolongation cost. Therefore, As a result of analyzing the occurrence pattern of Job-site overhead cost, it is confirmed that actual costs can not be calculated by the cash-basis method. In particular, the implications of the necessity of the accrual-basis method should be more strictly indicated in the case of items such as indirect labor costs and welfare benefits. In addition, the contractor 's claim report and the appraisal report were examined. As a result, it was confirmed that the calculation situations of prolongation costs are biased to the cash-basis method. In this way, it is suggested that necessary to supplement the calculation standard of the actual costs from the point of view of accrual basis.
Keywords
Prolongation Cost; Time Extension; Delay Cost; Accrual Basis; Cash Basis;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Adrian, James J. (1993). "Construction claims : A Quantitative Approach." Illinois, Stipes Publishing Company.
2 Cushman R. F., Carter J. D., Gorman P. J., and Coppi D. F. (2001). "Proving and Pricing Construction Claims." New York, Aspen Publishers.
3 Jeong, K. (2016a). "A Model to Estimate Additional Indirect Costs for Extended Construction Times." Ph.D., Dongguk Univ. of Seoul, Korea.
4 Jeong, K., and Lee, J. (2016b). "Improvement of the Calculation Standard for Prolongation cost of Domestic Public Construction Project." Korean Journal of Construction Engineering and Management, KICEM, 17(4), pp. 95-102.   DOI
5 Jeong, K., Park, Y., and Lee, J. (2012). "Study on introduction of 'Pre-Agreement system for Additional Incidental Cost' related to construction time extension." Korean Journal of Construction Engineering and Management, KICEM, 13(6), pp. 33-44.   DOI
6 Kim, K. (2018). "An Estimation Model for the Additional Overhead Cost of Extended Duration of Construction by using the Case Based Reasoning(CBR) method." MS., Univ. of Seoul, Korea.
7 Lee, G., and Kim, Y. (2001). "A Case Study on the Calculation of Delay Damages for Contractors according to the Extension of Contract Period." Proceedings of KICEM Annual Conference, KICEM, 11, pp. 305-310.
8 Lim, D. (2007). "(A) comparative study on the institutionalization the system of double entry and accrual budget accounting." Ph.D., Seoul Univ. of Seoul, Korea.
9 Shin, Y. (2012). "Improvement of the Calculation Method on the Additional Costs due to Construction Delay." Ph.D., Dongguk Univ. of Seoul, Korea.
10 Yoon, Y. (2006). "New Financial Administration." Daeyoung co., Seoul, Korea.