Alternative Evaluation Model for Tower Crane Operation Plan in Modular Construction - Focusing on Modular Unit Installation and Finishing works -  

Kim, Joo Ho (Department of Architectural and Architectural Engineering, Seoul National University)
Park, Moonseo (Department of Architecture and Architectural Engineering, Seoul National University)
Lee, Hyun-Soo (Department of Architectural and Architectural Engineering, Seoul National University)
Hyun, Hosang (Department of Architectural and Architectural Engineering, Seoul National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.19, no.2, 2018 , pp. 50-60 More about this Journal
Abstract
Recently, modular construction method has been widely applied to projects with repetitive processes including dormitory, the residential facility, and the hotel construction due to reduced labor input and shortened construction schedule. Generally, about 40% of total on-site construction cost excluding unit installation cost, is put on exterior finishing work, and thus management of finishing work is deemed important in maintaining the targeted schedule and cost. Since limited equipment is shared so that subsequent activities are not affected while carrying out on-site installation and finishing work, lifting plan becomes more important for modular projects with greater portion of finishing work load. In this regard, tower crane operation plan may take the form of a single cycle or multiple cycles in which equipment efficiency can be affected. However, difficulties exist in evaluating alternatives to tower crane operation plans supporting unit installation and finishing work. Therefore, this study aims to evaluate the alternative of tower crane operation method according to the cyclic period setting in modular building site to determine the effect on T/C uptime and process by parameterizing lifting time for unit and exterior finishing material, lift cycle for unit and exterior finishing material and time required for finishing work. Accordingly, this study develops a simulation model that can increase the tower crane efficiency by controlling the work speed. An academic contribution of this study is to suggest a resource leveling method applying the concept of lifting cycle, and further is expected to be managerially used as a basis for an alternative evaluation of equipment plan.
Keywords
Tower Crane Operational Efficiency; Discrete Event Simulation; Alternative Evaluation; Modular Construction;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 Li, H., Chan, N. K., and Skitmore, M. (2012). "The use of virtual prototyping to rehearse the sequence of construction work involving mobile cranes." Construction Innovation, 12(4), pp. 429-446.   DOI
2 Martinez, J. C. (1996). "STROBOSCOPE : State and Resource Based Simulation of Construction Processes." Ph.D. Thesis, The University of Michigan, Ann Arbor, MI, USA.
3 Modular Building Institute (MBI). (2015). Permanent modualr construction 2015 annual report.
4 Mohsen, O. M., Knytl, P. J., Abdulaal, B., Olearczyk, J. , and Al-Hussein, M. (2008). "Simulation of modular building construction." Proceedings of the 40th Conference on Winter Simulation.
5 Tantisevi, K., and Akinci, B. (2008). "Simulation-based identification of possible locations for mobile cranes on construction sites." Journal of computing in civil engineering, 22(1), pp. 21-30.   DOI
6 Tubaileh, A. (2016). "Working time optimal planning of construction site served by a single tower crane." Journal of Mechanical Science and Technology, 30(6), pp. 2793-2804.   DOI
7 Pritsker, A. A. B. (1986). Introduction to stimulation and Slam II. West Lafayette, Indiana: Systems Publishing Corp.
8 Neelamkavil, J. (2009). "Automation in the prefab and modular construction industry." The 26th Symposium on Construction Robotics ISARC.
9 Olearczyk, J., Al-Hussein, M., and Bouferguene, A. (2014). "Evolution of the crane selection and on-site utilization process for modular construction multilifts." Automation in Construction, 43, pp. 59-72.   DOI
10 Olearczyk, J., Al-Hussein, M., Bouferguene, A., and Telyas, A. (2009). "Virtual construction automation for modular assembly operations." Construction Research Congress 2009 : Building a Sustainable Future.
11 Shin, S. H., and Kim, K. H. (2009). "Hoist Scheduling Chart and Lifting Load Leveling Method for Applying JIT(Just-In-Time) in Construction." Journal of the Architectural Institute of Korea Structure & Construction, 25(2), pp. 149-157.
12 Smith, R. E. (2011). Prefab architecture: A guide to modular design and construction : John Wiley & Sons.
13 Cho, C. Y., Cho, M. Y., and Shin, Y. S. (2012). "Prediction Model for Hoisting Times of Tower Crane using Discrete-Event Simulation in High-rise Building Construction." Journal of the Architectural Institute of Korea Structure & Construction, 28(1), pp. 151-158.   DOI
14 Yang, K., Lee, H. S., Park, M., Jung, M., and Hwang, S. (2013). "A study of the tower crane hoisting time estimation simulation model with climate element for the high-rise building construction." Korean Journal of Construction Engineering and Management, KICEM, 14(2), pp. 96-107.   DOI
15 Kim, S., Kim, S., Jean, J., and An, S. H. (2016). "Optimization of T/C Lifting Plan using Dependency Structure Matrix (DSM)." Journal of the Korea Institute of Building Construction, 16(2), pp. 151-159.   DOI
16 Leung, A. W., and Tam, C. (1999). "Models for assessing hoisting times of tower cranes." Journal of Construction Engineering and Management, 125(6), pp. 385-391.   DOI
17 Ahn, B. J., Yang, J. Y., Baik, J. K., and Kim, J. J. (2003). "Developing a Transportation and Procurement System for Curtain-Wall Materials focused on JIT Management." Journal of the Architectural Institute of Korea Structure & Construction, 19(8), pp. 153-162.
18 Alvanchi, A., Azimi, R., Lee, S., AbouRizk, S. M., and Zubick, P. (2011). "Off-site construction planning using discrete event simulation." Journal of architectural engineering, 18(2), pp. 114-122.   DOI
19 Boyd, N., Khalfan, M. M., and Maqsood, T. (2012). "Off-site construction of apartment buildings." Journal of architectural engineering, 19(1), pp. 51-57.   DOI
20 Chehayeb, N. N., and AbouRizk, S. M. (1998). "Simulation-based scheduling with continuous activity relationships." Journal of Construction Engineering and Management, 124(2), pp. 107-115.   DOI
21 Generalova, E. M., Generalov, V. P., and Kuznetsova, A. A. (2016). "Modular buildings in modern construction." Procedia Engineering, 153, pp. 167-172.   DOI
22 Halpin, D. W. (1973). "An investigation of the use of simulation networks for modeling construction operations." Ph.D. Thesis, University of Illinois at Urbana-Champaign, IL, USA.
23 Han, S. H., Hasan, S., Bouferguene, A., Al-Hussein, M., and Kosa, J. (2014). "Utilization of 3D visualization of mobile crane operations for modular construction on-site assembly." Journal of Management in Engineering, 31(5), 04014080.   DOI
24 Kim, S. W., and Choe, M. K. (2010). "A Study on the Lifting Progress Character Tributary for the Construction Materials Moving Method." Journal of the Regional Association of Architectural Institute of Korea, 12(1), pp. 199-206.
25 Kamali, M., and Hewage, K. (2016). "Life cycle performance of modular buildings: A critical review." Renewable and Sustainable Energy Reviews, 62, pp. 1171-1183.   DOI
26 Kim, K. J. (2000). "A Study for the Implementation of Self-controlling Resource Model in the Simulation of Heavy Construction Operations." Journal of The Korean Society of Civil Engineers, 20(4D), pp. 389-402.
27 Kim, S. (2002). Business simulation. Hankyungsa.
28 Korea Institute of Civil Engineering and Building Technology (KICT). (2016). 2017 Standard of Construction Estimate, Seoul: Korea Institute of Civil Engineering and Building Technology.
29 Lawson, R. M., Ogden, R. G., and Bergin, R. (2011). "Application of modular construction in high-rise buildings." Journal of architectural engineering, 18(2), pp. 148-154.   DOI
30 Lawson, R., and Ogden, R. (2010). "Sustainability and process benefits of modular construction." Proceedings of the 18th CIB World Building Congress, TG57-Special Track, Salford, UK.
31 Lee, H. S., Chae, H., and Jang, M. H. (2002). "Development of Tower Crane Planning Process in High-rise Building Projects." Journal of the Architectural Institute of Korea Structure & Construction, 18(6), pp. 119-126.
32 Lee, K. B., Kim, K. R., Shin, D. W., and Cha, H. S. (2011). "A proposal for optimizing unit modular system process to improve efficiency in off-site manufacture, transportation and on-site installation." Korean Journal of Construction Engineering and Management, KICEM, 12(6), pp. 14-21.   DOI