Improvement of Design Performance for the Minimization of Public Grievances Based on a Construction Public Grievance Breakdown Structure  

Moon, Sungwoo (Department of Civil and Environmental Engineering, Pusan National University)
Jo, Hwani (Department of Civil and Environmental Engineering, Pusan National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.19, no.1, 2018 , pp. 12-20 More about this Journal
Abstract
Construction projects are often large in magnitude and high in construction amount. Therefore, construction activities have great impacts on business economics and social lives in the surrounding regional area. The residents can have public grievances if they are badly affected by the construction activities. Project owners should try to minimize adverse impacts in planning and design as well as in construction. The objective of this paper is to establish a public grievance breakdown structure and apply this breakdown structure to improving design functions in an effort to minimize public grievances. This research has been done in three steps of 1) analyzing the characteristics of public grievances in construction projects; 2) developing a public grievance breakdown structure; and 3) based on the public grievance breakdown structure, generating design alternatives that can improve the preparedness against public grievances. A case study has been done to demonstrate the applicability of the public grievance breakdown structure in generating design alternatives to minimize public grievances.
Keywords
Construction Projects; Public Grievances; Public Grievances Breakdown Structure; Value Engineering; Value Improvement;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Son, C. B., and Kwon, J. S. (2007). "Risk assessment and preventive measures for the civil appeals in building construction sites." Journal of the Architectural Institute of Korea Structure & Construction, 23(11), pp. 185-192.
2 Lee, J. S. (2007). "The Impacts of Time Extension on Construction Costs-Focused on Domestic Public Construction Projects." Journal of the Architectural Institute of Korea Structure & Construction, 23(4), pp. 157-164.
3 Ministry of the Interior and Safety (2017). "Law on the administration of public grievances."
4 Ministry of Land, Infrastructure and Transport (2016). "The status of schedule delay in the public highway construction projects over the past 10 years."
5 Kim, E. S., Hwang, C. S. and Park, T. K. (2005). "A Countermeasure of prevention for public resentment by construction work noise." Proceedings of Korea Institute of Construction Engineering and Management Student Presentation Conference, pp. 283-287.
6 Kwon, J. S. and Son, C. B. (2008). "Assessment method on the preventive management levels of civil appeals in apartment construction sites." Journal of the Architectural Institute of Korea Structure & Construction, 24(10), pp. 151-158.
7 Doo, S. K. (2016). "A Study on the Reasonable public greivances Process of Construction Projects." Construction Issue Focus, 26.
8 Jeongup City (2017). "The status of public grievances in the construction projects over the past 5 years."
9 Shin, J. W. (2001). A Study about Improvement through the Case of Public Petition on Construction, Master's Thesis, Chonnam National University.
10 Son, C. B., and Lee, D. C. (2002). "An analysis on the factors decreasing productivity of building construction." Journal of the Architectural Institute of Korea Structure & Construction, 18(12), pp. 125-132.